Phasor diagram

Learn what each arrow represents, how a fault, a reversed CT or a Dyn11 transformer reads, and use the Advanced mode with your real measurements: symmetrical components, powers, impedance per loop and load-check diagnosis.

IEEE C37.118.1§ 4.1phasor definition, RMS valueIEC 60050-131IEV 131-11-26, phasorIEC 60076-1clock numberIEC 60909-0§ 5.3.2symmetrical components

Example cases
Phasor diagram

Only the basic data; the rest is taken with typical values.

ALearn

E1Measurements (side 1)
Measured phasors

One row per phasor: name, RMS magnitude and angle (°).

RowPhasorMag. or ReV, A∠ or Im°Remove

E2Side 2 or pre-fault
Phasors of the second set

For the 87: the CTs of both sides pointing into the object.

RowPhasorMag. or ReV, A∠ or Im°Remove

E3Format, CT and VT

Current ratio: 600/5 = 120.

Voltage ratio: 115 kV/115 V = 1000.

E4Reference
°

Empty: automatic. Radius of the outer ring.

E5Expected
kV
kV

k0 = (Z0 − Z1)/(3·Z1) of the line.

°
Ω

Optional: drawn on the R-X plane, in the same units shown.

°

Use a decimal point. The calculation runs in your browser and updates as you type.

Diagnosis

—

Phase rotation

—

Voltage-current angle φ

— °

Total active power

—

Total reactive power

—

Current unbalance I2/I1

— %

Phasor diagram and sine waves
Positive angles counter-clockwise; each arrow measures the RMS value. Voltages in solid line, currents in dashed line; phase colours per IEC 60445 (A brown, B black, C grey). Drag the tip of a phasor to change it; Ctrl + wheel or the buttons zoom; drag the background to pan.
P-Q plane: quadrants
Load convention: P > 0 enters the measured object, Q > 0 inductive. With the generator convention the signs flip. Large dot: total; small ones: each phase.
Apparent impedance per loop (R-X)
Phase-to-ground loops with k0 compensation and phase-to-phase loops. The dashed line is the line impedance if you give it. With load, the points sit far from the origin; in a fault, the faulted loop falls on the line.

Load-check diagnosis

    Verified rules for commissioning. It never replaces the engineer's judgement nor gives setting values.

    Phasors, sequences and powers

    PhasorPolarRectangular
    PhasePQSPF

    Angle of each phasor from another

    Row from column: positive, the row leads.

    LoopZR + jX

    Relay did not operate as expected? We review its settings and correct them remotely.

    What it is for

    A phasor diagram sums up in one picture how the voltages and currents of a three-phase circuit are: whether they are balanced, in which order they turn, whether energy goes in or out and what kind of fault there is. It is the tool used to review a commissioning and to analyse a trip.

    • Essential mode: type the voltages and currents of the three phases (magnitude and angle) and see the diagram, the sine waves, the rotation, P, Q, the power factor, the unbalance and the load-check diagnosis.
    • Advanced mode: your measurements in primary or secondary, one or two sides (87T, 87L) or pre-fault and fault; symmetrical components, powers, apparent impedance per loop, angles between phasors and the diagnosis of the load and polarity check. Exports to PNG, SVG, PDF and CSV.
    • Learn to read phasor diagrams: a separate option, with the button in the input panel. Guided lessons from what a phasor is, the rectangular form, the j operator and adding and subtracting phasors to how faults, a reversed CT, a Dyn11 transformer or an open delta look, plus challenges to check what you learned. Each lesson has its own link.

    How to read it

    Each rule of the lessons and of the diagnosis, with its source.

    IEEE C37.118.1§ 4.1phasor definitionIEC 60050-131IEV 131-11-26

    What a phasor is. The wave x(t) = Xm·cos(ωt + φ) is represented by the complex number X = (Xm/√2)∠φ: the length is the RMS value and the angle, the initial phase. The arrow turns counter-clockwise at ω; its projection on the real axis, multiplied by √2, is the instantaneous value. That is why a phasor diagram is the snapshot of the instant ωt = 0.

    IEC 60050-131IEV 131-11-26IEEE C37.118.1§ 4.1RMS value

    Rectangular form and the j operator. The same phasor is written |X|∠θ (polar) or x + jy (rectangular), with x = |X|·cos θ, y = |X|·sin θ, |X| = √(x² + y²) and θ = atan2(y, x); atan2 looks at the signs of x and y, so it never confuses opposite phasors. Multiplying by j = 1∠90° turns the phasor 90° without changing its length (j² = −1), and by −j turns it −90°. The length is the RMS value (IEEE C37.118.1); the peak of the wave is √2 times larger (Blackburn, Symmetrical Components for Power Systems Engineering).

    IEC 60909-0§ 5.3.2operator a

    The a operator. a = 1∠120° = −1/2 + j√3/2 and a² = 1∠240°: a³ = 1 and 1 + a + a² = 0. IEC 60909-0 writes the symmetrical components with it: in ABC, VB = a²·VA and VC = a·VA.

    IEC 60050-131IEV 131-11-26

    Sum and difference. Two phasors of the same frequency are added part by part in rectangular form, which is the parallelogram rule; the difference X1 − X2 is the sum with −X2, the other diagonal. The instantaneous value of the sum is the sum of the instantaneous values. Phasors of different frequencies cannot be added this way, because the angle between them changes at every instant. This gives the line-to-line voltage VAB = VA − VB and the residual current 3I0 = IA + IB + IC (Blackburn, Protective Relaying, «Phasors and Polarity»).

    IEC 60909-0§ 5.3.2operator a

    Phase rotation. In ABC, VB = a²·VA (lags by 120°) and VC = a·VA, with a = 1∠120°. In ACB, B and C swap. The line voltage VAB = VA − VB is √3 times the phase voltage and leads by 30° in ABC (lags by 30° in ACB): Glover, Sarma and Overbye, Power System Analysis and Design, ch. 2.

    IEC 60050-131IEV 131-11-39IEC 62053-23four quadrantsIEC 60375sign conventions

    Current versus voltage. Complex power is S = V·I*. With the load convention (current arrow entering the object), a positive φ = ∠V − ∠I is an inductive load (Q > 0) and a negative one is capacitive. Quadrant I: absorbs P and Q; II: delivers P and absorbs Q; III: delivers P and Q; IV: absorbs P and delivers Q. The generator convention reverses the arrow and, with it, the signs (IEEE 1459 for the definitions of P, Q, S and PF).

    IEC 60076-1clock numberIEEE C57.12.00angular displacement

    The transformer clock. The HV phase-A voltage goes at 12 o'clock and each hour is 30°: the number says how much the LV lags (Dyn1: 30°; Dyn11: 330°, that is, it leads by 30°). IEEE C57.12.00 sets that in Y-Δ and Δ-Y the HV leads the LV by 30°. After compensating the group, the currents of both sides of an 87T must be equal and at 180° (Costello, SEL).

    SELRelay-Assisted Commissioning

    • Load check: with balanced load you detect a CT connected to the wrong tap, crossed phases and reversed polarity by comparing the angle of each phase with a reference (Labuschagne and Fischer, «Relay-Assisted Commissioning», SEL, WPRC 2005).
    • Reversed CT: that current appears turned 180° (IB at 60° instead of −120°) and the residual equals twice the phase current; in the test by Peterson, Scharlach and Baltazar (IEEE PPIC 2009), reversing IA gave 3I2 ≈ 212 A and IG ≈ 213 A.
    • Crossed phases: the currents turn the other way and almost all the load shows as I2; the SEL check declares crossed phases when I1 is below 10 % of I2.
    • Before handover: verify with the line in service the magnitude and angle of voltages and currents (NERC, Lessons Learned LL20200702), using the relay metering, its events or synchrophasors (Zimmerman, SEL, 2008).

    Faults. Single line to ground: I0 = I1 = I2 and 3I0 appears. Phase-phase: I2 = −I1, no I0. Two phases to ground: the healthy phase carries no fault current and there is I0. Three-phase: positive sequence only. Open phase without neutral: I2 equal to I1 (Blackburn, Symmetrical Components for Power Systems Engineering, and Protective Relaying, chapter «Phasors and Polarity»).

    Open delta and broken delta. Two VTs A-B and B-C give the three line-to-line voltages (VCA = −(VAB + VBC)) but not the phase voltages or V0. Three VTs with the secondary in delta open at one corner give 3V0 for the 59N (Basler, note PC-59N01).

    Motor starting. Locked-rotor current close to 6 times rated with a power factor of 0.15 to 0.20 (IEEE 399, default values of motor-starting studies): a large, strongly lagging and balanced current.

    How it is calculated

    X = |X|∠θ = x + jy · x = |X|·cos θ · y = |X|·sin θ · |X| = √(x² + y²) · θ = atan2(y, x)X1 ± X2 = (x1 ± x2) + j(y1 ± y2) · j = 1∠90° · a = 1∠120° = −1/2 + j√3/2
    x(t) = √2·|X|·cos(ωt + φ)VAB = VA − VB · VCA = −(VAB + VBC)S = V·I* = P + jQ · FP = ΣP / |ΣS|

    The total power factor uses the vector apparent power |ΣS| (IEEE 1459).

    IEC 60909-0§ 5.3.2symmetrical components

    X0 = (Xa + Xb + Xc)/3 · X1 = (Xa + a·Xb + a²·Xc)/3 · X2 = (Xa + a²·Xb + a·Xc)/3

    The same functions as the site's symmetrical components calculator. Voltage unbalance u2 = V2/V1 (IEC 61000-4-30; 2 % compatibility level in IEC 61000-2-2) and, for reference, the NEMA MG 1 definition: maximum deviation from the average divided by the average.

    ZAG = VA / (IA + k0·3I0) · k0 = (Z0 − Z1)/(3·Z1) · ZAB = (VA − VB)/(IA − IB)

    Six loops: AG, BG, CG, AB, BC and CA (Kockott, Line Distance Protection Fundamentals, ABB, 2015; Dase et al., SEL; Ziegler, Numerical Distance Protection, 3.2). Primary to secondary: Zsec = Zpri·CTR/VTR.

    Faults in the lessons. Sequence networks with the source behind the relay and the fault at the end of the line section, no pre-fault load and Z2 = Z1: single line to ground I0 = I1 = I2 = E/(2Z1 + Z0 + 3Rf); phase-phase I1 = −I2 = E/(2Z1 + Rf); two phases to ground I1 = E/(Z1 + Z2‖(Z0 + 3Rf)); three-phase I1 = E/(Z1 + Rf). The tests check that every faulted loop measures the line impedance.

    87T. Each side is taken to primary amperes with its CT ratio, multiplied by its rated voltage (common MVA base) and the vector-group compensation matrix of the 87T compensation tool is applied. Differential = |I1 + I2| compensated, in % of the larger one.

    Diagnosis thresholds

    • Balanced set: I2/I1 and I0/I1 below 10 % (this tool's convention, equal to the SEL crossed-phase criterion).
    • One phase angle out of line: the three voltage-current angles spread over more than 10° (this tool's convention).
    • Differential after compensation above 10 % of the through current, or a leftover shift above 20° (this tool's convention for the load check; the relay threshold is set by its settings, not by this tool).
    • Lost voltage: a phase below 50 % of the largest; open current: below 10 % (this tool's convention). Voltage unbalance: 2 % (IEC 61000-2-2).

    Limits of the calculation

    • It works with fundamental-frequency phasors taken at the same instant and with the same reference. In an oscillography with DC offset or harmonics, use the filtered phasors of the relay or of the COMTRADE viewer.
    • The diagnosis recognises wiring patterns with reasonably balanced load; with very unbalanced or near-zero load the rules lose strength and it says so.
    • The faults in the lessons are ideal (no pre-fault load, simple radial network): they are for learning to read them, not a short-circuit study.
    • It never gives setting values: the diagnosis thresholds are for review, not for protection.

    Frequently asked questions

    How do you read a phasor diagram?

    Each arrow is a voltage or a current: its length is the RMS value and its angle, the shift from a reference (usually VA at 0°). Angles grow counter-clockwise and the arrow that is ahead in that rotation leads. You read it by comparing: three equal voltages at 120°, each current close to its voltage and the angle between them according to the type of load.

    How are two phasors added?

    Convert them to rectangular form, add the real parts and the imaginary parts separately and take the result back to polar form: magnitude √(x² + y²) and angle atan2(y, x). That is the parallelogram rule. For example, 80∠0° + 60∠90° = 80 + j60 = 100∠36.87°, not 140. It only holds for phasors of the same frequency.

    Why does the angle between voltage and current show the direction of power?

    With the load convention, complex power is S = V·I*. If the current is within 90° of its voltage, active power enters the measured object; if it is more than 90° away, it leaves. The sign of the reactive power says whether the current lags (inductive) or leads (capacitive).

    How do you detect a CT with reversed polarity in the load check?

    The current of that phase appears turned 180° from where it should be, close to the opposite voltage, and with balanced load the residual current equals twice the phase current. Turning that current by 180° makes the set balanced again: that is how this tool identifies it.

    We set and test your relays

    If your load check shows a reversed polarity, crossed phases or a differential that does not close, we review it with you. We set and verify your protections remotely, and on site we do the secondary injection and the load check.

    Related guides

    Other tools

    FreeCOMTRADE generatorCreate a COMTRADE fault record (.cfg/.dat or .cff) for your test set: fault, DC offset and breaker opening.FreeANSI / IEEE C37.2 device numbersDevice function numbers 1 to 94, common suffixes and their IEC 61850 logical node, with search.FreeRelay coordinationOnline protection coordination, no Excel sheet: up to six relays, reclosers and fuses on a log-log plot, with the IEEE C57.109 damage curve, inrush and the margin of each pair.FreeInverse-time curvesCalculator and log-log plot of the IEC 60255-151 and IEEE C37.112 curves, with the coordination margin.FreeCT burdenLead resistance, relay burden and comparison with the rated burden of the current transformer.FreeShort-circuit currentQuick estimate of the three-phase fault at the secondary of a transformer.FreeCOMTRADE viewerOpen .cfg/.dat or .cff fault records in your browser: waveforms, digital channels, cursor and RMS. The file is not uploaded.FreeIEC 61850 SCL viewerOpen .scd, .cid or .icd files in your browser: IEDs, GOOSE and SV addresses, datasets, subscribers and checks. The file is not uploaded.FreeGOOSE and SV addressesCheck IEC 61850 multicast MAC, APPID, VLAN and priority, find duplicates and export the table as CSV.FreeProcess bus networkSV and GOOSE bandwidth, worst-case latency, PRP, HSR or RSTP redundancy and PTP time error of an IEC 61850 network.FreeInterlocking table and CILO equationsInterlocking matrix per device, IEC 61850 EnaOpn and EnaCls equations, GOOSE signals between bays and FAT/SAT test cases per configuration.FreePer-unit base conversionBase current and impedance, conversion between %, pu and ohms, and change of base for transformers, generators and lines.FreeHarmonic distortion THD and TDDVoltage THD and current TDD against the IEEE 519-2022 limits, with the spectrum as a bar chart.FreeSymmetrical componentsPhase quantities to zero, positive and negative sequence and back (Fortescue), with phasor diagrams and what they mean for 46, 67Q and 51N.FreeVector group compensation (87T)TAP of each winding, phase compensation matrix, zero-sequence removal and the HV-to-LV clock diagram.FreePrimary and secondary impedance (21)Primary to secondary ohms with the CT and VT ratios, line Z1, Z0 and k0, and zone reaches on the R-X plane.FreeCT saturationRequired versus available voltage (5P/10P, PX or C class), time to saturation and the saturated waveform.FreeCommissioning checklistWhat to verify cold, at energization and hot for each piece of equipment, with its IEC, IEEE or NETA standard, a check box and a remark. PDF and CSV.FreeDGA interpretationIEEE C57.104-2019 DGA status, Duval triangles 1, 4 and 5, IEC 60599 ratios and CO₂/CO of your transformer.FreeInsulation temperature correctionInsulation resistance at 40 °C (IEEE 43) or 20 °C, PI, DAR and power factor of transformers and bushings, with the trend.FreeCapacitor bankkvar to correct the power factor, steps of the automatic bank, capacitance and resonance with the transformer.FreeCable voltage dropΔV and % with R and X per km, copper or aluminium, mm² or AWG/kcmil, and the short-circuit check of the cable size.FreeBattery sizingAh, number of cells and charger of a DC battery bank from its duty cycle, per IEEE 485 and IEEE 1115.FreeGrounding resistanceGround rods, horizontal conductor and grid (BS 7430, IEEE 80), and soil resistivity from Wenner measurements.FreeTechnical glossarySubstation, protection and communications terms, explained in one or two sentences.