Tiza Group

Home / Tools / Solar plants and the grid code

Solar and wind plants and the grid code: CREG 060 of 2019

Choose the technology and the connection, and type your plant data in each tab: the tool checks the available reactive power against the P-Q curve, voltage control, frequency response, ramp rate, a voltage dip profile against the LVRT and HVRT curves and the fast reactive current, citing the article of CREG 060 of 2019 in each check.

CREG 060 de 2019§ art. 14voltage control, P-Q curve, LVRT/HVRT and fast reactive currentCREG 060 de 2019§ art. 12power and frequency controlCREG 060 de 2019§ art. 15rampCREG 060 de 2019§ art. 4clearing timesCREG 148 de 2021§ cap. 11SDL plants of 5 MW or moreCREG 101 011 de 2022§ cap. 12SDL plants of 1 to less than 5 MWAcuerdo CNO 1603§ art. 3 y 4voltage dips on the SDLAcuerdo CNO 2193§ anexo, num. 1 a 3ROCOF on the STN, the STR and the SDL

Example cases
Solar and wind plants and the grid code: CREG 060 of 2019

Only the basic data; the rest is taken with typical values.

ALearn

E1Plant and connection
MW

On the SDL, the net effective capacity: it decides whether CREG 148 (5 MW or more) or CREG 101 011 (1 to less than 5 MW) applies.

A plant of 1 to less than 5 MW that opts for central dispatch follows the 5 MW-or-more rules (CREG 101 011, art. 10).

Large-scale self-generator: from 1 to less than 5 MW it has the services of chapter 12 and its own list of tests and certificates (CREG 101 104 of 2026).

E2Inverters and transformer
MVA

Sum of the rated apparent power of the inverters in service.

%

From the nameplate, on its own rating; add the medium-voltage collector network if it is significant.

MVA
Mvar
p.u.
p.u.
E3Voltage control
%
p.u.
% Pn
p.u.
s

Response time measured in the step test.

s

Settling time measured in the same test.

E2Frequency control
%
mHz

Controller setting: the resolution does not say whether the deadband is subtracted. Agree on it with the CND.

Hz
% Pn
% Pn

What the resource (sun or wind) allows at that moment.

From 1 to less than 5 MW, the over-frequency response is activated in operation only when the CREG decides it in another resolution (num. 12.2.1.1 d, mod. CREG 101 104 of 2026).

Today solar and wind plants are exempt (art. 12, paragraph 2).

Setting of the plant's frequency relay. CNO Agreement 2193 of 2026 sets the criterion for the STN, the STR and the SDL from 1 MW.

Hz/s
ms
ms
s
s
E3Start or stop ramp
% Pn
s
%/min

On the SDL there is no fixed limit: the CND defines and publishes the value. Leave it empty if it has not been published yet.

E2Dip profile
p.u.

Line-to-line voltage at the point of connection. Greater than 1 for an overvoltage.

s
s
p.u.
s

Measured from when the voltage returns above 0.85 p.u.

E3Fast reactive current

Adjustable from 0 to 10; set by the CND.

p.u.
p.u.
p.u.

Use a decimal point. The calculation runs in your browser and updates as you type.

Applicable regulation

—

Reactive margin at the worst point of the curve

—

Power change with frequency

—

Maximum ramp in one minute

—

Dip against LVRT and HVRT

—

Additional fast reactive current

—

Plant, controller and point of connection
The signals the check of the tab uses light up: voltage and current measured at the point of connection, the controller's set points to the inverters and the test signal. The controller frame turns green or red with the result.
Available reactive power against the capability curve
  • Available at the point of connection
  • Required (art. 14 b)
Capacitive reactive power is on the right and inductive on the left, in multiples of Pn. The colored line must stay outside the dotted area over its whole height. The circle is the point the voltage control asks for.
Reactive power requested by the voltage control
  • Q(V) with the droop
  • Curve limit
With low voltage the plant supplies capacitive reactive power and with high voltage it absorbs it, up to the curve limit for the active power at that moment.
Active power against frequency
  • Power with the droop
  • Available power
  • Deadband
On over-frequency the plant reduces power according to the droop. On under-frequency it only increases power if it has headroom and the response is enabled.
Voltage profile against the LVRT and HVRT curves
  • Event profile
  • LVRT and HVRT (art. 14 c)
While the profile stays between the two curves, the plant must remain connected. Where the profile leaves the area, the plant may disconnect.
Fast reactive current against voltage
  • ΔIr/In with gain k
  • Assumed deadband
Positive is capacitive current, injected at low voltage. Outside the deadband the whole deviation from the pre-event voltage counts; the additional current is limited to rated current.

Step-by-step calculation

What it is for

Resolution CREG 060 of 2019 sets, on a transitional basis, what a solar PV or wind plant connected to the STN (national transmission system) or STR (regional transmission system) must do for the grid: supply and absorb reactive power, regulate voltage, respond to frequency, limit its ramp rate and stay connected during voltage dips. This tool checks each requirement with your plant data before the tests with the CND (national dispatch center).

Plants connected to the SDL follow other rules: CREG 148 of 2021 from 5 MW and CREG 101 011 of 2022 from 1 to less than 5 MW. Choose «SDL» as the point of connection and the tool switches its checks to the regime that applies by capacity and dispatch.

It is used in engineering, to size inverters, transformer and compensation, and in commissioning, to read the results of the power plant controller (PPC) tests against the applicable article.

How it is calculated

CREG 060 de 2019§ art. 14 bcapability curve

Reactive power at the point of connection

Qcap = √((Sinv·V)² − P²) − xT·S²/(V²·ST)

The inverters deliver the apparent power their current allows; the transformer consumes reactive power with the square of the current. The capacitive and inductive reactive power left is compared with what the curve requires at each corner: (0.1; 0.1), (0.2; 0.33), (0.95; 0.33) and (1.0; 0.228), in multiples of Pn.

CREG 060 de 2019§ art. 12droop and deadband

Frequency response

ΔP/Pn = −(Δfef/fn)/R

R is the droop (2 % to 6 %) and Δfef the deviation outside the deadband (0 to 120 mHz, initially 30 mHz or less). Whether the deadband is subtracted from the deviation is a setting. The control must have Tr of 2 s or less and Te of 15 s or less.

CREG 060 de 2019§ art. 14 c, 14 ddips and reactive current

Fast reactive current

ΔIr/In = k·ΔU/Un, |ΔIr| ≤ In

ΔU and ΔIr are measured from the pre-event values. 90 % of the change must be reached in less than 50 ms, detection included, and held for 500 ms after the voltage returns to the band. The voltage profile is checked point by point against the LVRT and HVRT curves; at 500 kV the HVRT drops to 1.05 p.u.

CREG 060 de 2019§ art. 15ramp

Start and stop ramp

|P(t + 60 s) − P(t)| ≤ 0.14·Pn

The ramp is evaluated over any one-minute window. It applies to start and stop with the resource available: a drop caused by clouds is not a controller ramp.

Limits of the calculation

  • The fast reactive current follows literal d) of numeral 5.7 of the Código de Operación as rewritten by CREG 101 104 of 2026: the tool calculates the positive sequence of a balanced event; the negative sequence (k from 0 to −10) and the active-current priority function, set by a CNO agreement, are not calculated.
  • Whether the deadband is subtracted from the frequency deviation is a setting: the resolution does not say. Use the one you agree on with the CND.
  • The resolution gives a 20 % tolerance to the 90 %-in-50 ms requirement, but does not say whether it applies to time or amplitude. The tool shows it and does not apply it.
  • A storage-only plant is out of scope and is not calculated. A solar plant with batteries is checked at the point of connection.
  • Inverter reactive power is calculated with a first-order model: inverter voltage is taken equal to the voltage at the point of connection. The reactive power base of the voltage control is assumed to be 0.33 Pn; the CND defines it.
  • CREG 101 104 of 2026 changed in CREG 060 the fast reactive current (num. 5.7 d), ROCOF (num. 2.2.5), the tests (num. 7.7) and the models, and added transient overvoltages (num. 5.7.1), which refer to IEEE 2800-2022: that standard is paid and its curve is not in the tool. It also modified chapters 11 and 12 of the Distribution Code; the current texts are used.
  • SDL: the points of the LVRT and HVRT curves of chapter 11 (num. 11.2.4) and CNO Agreement 1603 (art. 3) are in figures the tool does not have, and so are the transient-overvoltage curve of numeral 5.7.1 of the Código de Operación and the CNO agreements on SDL voltage control and fast current. Those checks show as pending.
  • SDL: the ramp has no fixed limit; it is compared with the value the CND publishes, assumed in % of Pn per minute. The spacing of successive dips is measured between starts and the wind-dip energy is expressed in Pn·s: these are our own readings.
  • The CNO agreements that detail the tests are not in the tool. It does not replace the connection study or the validated plant models.

Frequently asked questions

Which rule applies to a solar plant connected to the SDL?

If its net effective capacity is 5 MW or more, chapter 11 that CREG 148 of 2021 added to the Distribution Code. If it is 1 to less than 5 MW, chapter 12 of CREG 101 011 of 2022, unless it opts for central dispatch: then it follows the 5 MW-or-more rules. The dip curves for 1 to 5 MW are in CNO Agreement 1603.

What reactive power curve does CREG 060 require of a solar plant?

Between 20 % and 95 % of rated power the plant must be able to supply or absorb reactive power of 0.33 times Pn; at full power, 0.228 times Pn; at 10 % of Pn, 0.1 times Pn. Below 10 % there is no requirement, but reactive power must not exceed 5 % of Pn. It is measured at the point of connection, so the plant transformer reduces the capability.

When may the plant disconnect during a voltage dip?

Only when the line-to-line voltage at the point of connection leaves the area of the LVRT and HVRT curves of article 14. While the profile is inside, the plant must stay connected, inject fast reactive current and, when the dip ends, recover 90 % of its active power in one second or less.

Must the plant respond to under-frequency?

Not for now: paragraph 2 of article 12 exempts solar and wind plants from primary under-frequency response. They must reduce power on over-frequency, with a droop of 2 % to 6 % and a deadband of up to 120 mHz, initially 30 mHz or less.

We prepare your plant for the tests with the CND

We review the capability curve, the plant controller settings and the dip ride-through of your solar plant against CREG 060, and support you during the tests.

Related guides

Other tools

All tools
WhatsApp