Solar and wind plants and the grid code: CREG 060 of 2019
Choose the technology and the connection, and type your plant data in each tab: the tool checks the available reactive power against the P-Q curve, voltage control, frequency response, ramp rate, a voltage dip profile against the LVRT and HVRT curves and the fast reactive current, citing the article of CREG 060 of 2019 in each check.
CREG 060 de 2019§ art. 14voltage control, P-Q curve, LVRT/HVRT and fast reactive currentCREG 060 de 2019§ art. 12power and frequency controlCREG 060 de 2019§ art. 15rampCREG 060 de 2019§ art. 4clearing timesCREG 148 de 2021§ cap. 11SDL plants of 5 MW or moreCREG 101 011 de 2022§ cap. 12SDL plants of 1 to less than 5 MWAcuerdo CNO 1603§ art. 3 y 4voltage dips on the SDLAcuerdo CNO 2193§ anexo, num. 1 a 3ROCOF on the STN, the STR and the SDL
Results
—
—
—
—
—
—
Charts
- Available at the point of connection
- Required (art. 14 b)
- Q(V) with the droop
- Curve limit
- Power with the droop
- Available power
- Deadband
- Event profile
- LVRT and HVRT (art. 14 c)
- ΔIr/In with gain k
- Assumed deadband
How it was calculated and standards
Step-by-step calculation
What it is for
Resolution CREG 060 of 2019 sets, on a transitional basis, what a solar PV or wind plant connected to the STN (national transmission system) or STR (regional transmission system) must do for the grid: supply and absorb reactive power, regulate voltage, respond to frequency, limit its ramp rate and stay connected during voltage dips. This tool checks each requirement with your plant data before the tests with the CND (national dispatch center).
Plants connected to the SDL follow other rules: CREG 148 of 2021 from 5 MW and CREG 101 011 of 2022 from 1 to less than 5 MW. Choose «SDL» as the point of connection and the tool switches its checks to the regime that applies by capacity and dispatch.
It is used in engineering, to size inverters, transformer and compensation, and in commissioning, to read the results of the power plant controller (PPC) tests against the applicable article.
How it is calculated
CREG 060 de 2019§ art. 14 bcapability curve
Reactive power at the point of connection
Qcap = √((Sinv·V)² − P²) − xT·S²/(V²·ST)The inverters deliver the apparent power their current allows; the transformer consumes reactive power with the square of the current. The capacitive and inductive reactive power left is compared with what the curve requires at each corner: (0.1; 0.1), (0.2; 0.33), (0.95; 0.33) and (1.0; 0.228), in multiples of Pn.
CREG 060 de 2019§ art. 12droop and deadband
Frequency response
ΔP/Pn = −(Δfef/fn)/RR is the droop (2 % to 6 %) and Δfef the deviation outside the deadband (0 to 120 mHz, initially 30 mHz or less). Whether the deadband is subtracted from the deviation is a setting. The control must have Tr of 2 s or less and Te of 15 s or less.
CREG 060 de 2019§ art. 14 c, 14 ddips and reactive current
Fast reactive current
ΔIr/In = k·ΔU/Un, |ΔIr| ≤ InΔU and ΔIr are measured from the pre-event values. 90 % of the change must be reached in less than 50 ms, detection included, and held for 500 ms after the voltage returns to the band. The voltage profile is checked point by point against the LVRT and HVRT curves; at 500 kV the HVRT drops to 1.05 p.u.
CREG 060 de 2019§ art. 15ramp
Start and stop ramp
|P(t + 60 s) − P(t)| ≤ 0.14·PnThe ramp is evaluated over any one-minute window. It applies to start and stop with the resource available: a drop caused by clouds is not a controller ramp.
Limits of the calculation
- The fast reactive current follows literal d) of numeral 5.7 of the Código de Operación as rewritten by CREG 101 104 of 2026: the tool calculates the positive sequence of a balanced event; the negative sequence (k from 0 to −10) and the active-current priority function, set by a CNO agreement, are not calculated.
- Whether the deadband is subtracted from the frequency deviation is a setting: the resolution does not say. Use the one you agree on with the CND.
- The resolution gives a 20 % tolerance to the 90 %-in-50 ms requirement, but does not say whether it applies to time or amplitude. The tool shows it and does not apply it.
- A storage-only plant is out of scope and is not calculated. A solar plant with batteries is checked at the point of connection.
- Inverter reactive power is calculated with a first-order model: inverter voltage is taken equal to the voltage at the point of connection. The reactive power base of the voltage control is assumed to be 0.33 Pn; the CND defines it.
- CREG 101 104 of 2026 changed in CREG 060 the fast reactive current (num. 5.7 d), ROCOF (num. 2.2.5), the tests (num. 7.7) and the models, and added transient overvoltages (num. 5.7.1), which refer to IEEE 2800-2022: that standard is paid and its curve is not in the tool. It also modified chapters 11 and 12 of the Distribution Code; the current texts are used.
- SDL: the points of the LVRT and HVRT curves of chapter 11 (num. 11.2.4) and CNO Agreement 1603 (art. 3) are in figures the tool does not have, and so are the transient-overvoltage curve of numeral 5.7.1 of the Código de Operación and the CNO agreements on SDL voltage control and fast current. Those checks show as pending.
- SDL: the ramp has no fixed limit; it is compared with the value the CND publishes, assumed in % of Pn per minute. The spacing of successive dips is measured between starts and the wind-dip energy is expressed in Pn·s: these are our own readings.
- The CNO agreements that detail the tests are not in the tool. It does not replace the connection study or the validated plant models.
Frequently asked questions
Which rule applies to a solar plant connected to the SDL?
If its net effective capacity is 5 MW or more, chapter 11 that CREG 148 of 2021 added to the Distribution Code. If it is 1 to less than 5 MW, chapter 12 of CREG 101 011 of 2022, unless it opts for central dispatch: then it follows the 5 MW-or-more rules. The dip curves for 1 to 5 MW are in CNO Agreement 1603.
What reactive power curve does CREG 060 require of a solar plant?
Between 20 % and 95 % of rated power the plant must be able to supply or absorb reactive power of 0.33 times Pn; at full power, 0.228 times Pn; at 10 % of Pn, 0.1 times Pn. Below 10 % there is no requirement, but reactive power must not exceed 5 % of Pn. It is measured at the point of connection, so the plant transformer reduces the capability.
When may the plant disconnect during a voltage dip?
Only when the line-to-line voltage at the point of connection leaves the area of the LVRT and HVRT curves of article 14. While the profile is inside, the plant must stay connected, inject fast reactive current and, when the dip ends, recover 90 % of its active power in one second or less.
Must the plant respond to under-frequency?
Not for now: paragraph 2 of article 12 exempts solar and wind plants from primary under-frequency response. They must reduce power on over-frequency, with a droop of 2 % to 6 % and a deadband of up to 120 mHz, initially 30 mHz or less.
We prepare your plant for the tests with the CND
We review the capability curve, the plant controller settings and the dip ride-through of your solar plant against CREG 060, and support you during the tests.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws