Function 37: motor undercurrent

Motor load loss: undercurrent alarm and trip, blocking during the start, the relay inside and a test plan with the injection kit.

IEEE C37.96§ 2000 §8.3load lossSEL-710-5§ Specificationsundercurrent 37IEEE C37.2§ 2008 §3.1.37function number

Example cases
Function 37: motor undercurrent

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
A

The nameplate value divided by the CT ratio.

× FLA

Below this current, with the motor running, the relay takes it that the load is lost.

s
× FLA
s

Estimate: we do not have it from a manual. Enter the one of your relay.

E3Simulation
% of FLA

The relay knows whether the motor is stopped, starting or running from the 52a contact and the current.

E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
% of In
%
cycles
cycles

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Alarm

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 37 checks that the motor keeps driving its load. If a pump runs out of water, a coupling breaks or a valve closes, the current falls well below full load and the relay warns or takes the motor out.

It only makes sense with the motor running: stopped, no current flows and during the start the current is high, so the relay blocks it in those states.

How it operates

  • It compares the phase current with a setting in multiples of the full-load current (FLA). Below that value it runs its delay and trips.
  • A second stage, with more current and less time, gives the alarm before the trip.
  • It resets when the current returns above the setting multiplied by the reset ratio.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

Bring the relay to running: 52a closed and the motor rated current from the kit. Then lower the current with a ramp until the 37 picks up and raise it for the reset.

The time is measured with a step from the rated current down to half the setting. Finally open the 52a and check that the 37 does not trip.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The tolerances are those of the cited data sheet: enter those of your relay.
  • The reset ratio is an estimate: we do not have it from a manual.
  • The 37 by power (underpower), which some relays offer separately, is not modelled.

Frequently asked questions

Why does the 37 not trip with the motor stopped?

Because when stopped the current is zero and the 37 would see it as a load loss. The relay arms it only with the motor running, which it recognises from the 52a and the current.

What setting is used on a pump?

A value below the lowest current of normal operation and above the no-load or dry-running current. Both values come from measurements on the motor itself.

Why is the alarm above the trip?

Because a slight undercurrent may be a process change: the alarm warns first and the trip acts when the current falls further.