Home / Tools / Generator circuit-breaker
Generator circuit-breaker: asymmetry, delayed zeros and classes G1/G2
Type the data of the generator, the step-up transformer, the network and the breaker, and choose where the fault occurs. The tool draws the current of each phase with its DC component, finds the first zero after contact separation and compares it with the maximum arcing time. It also checks class G1 or G2 and the current when closing out of phase.
IEC/IEEE 62271-37-013:2015§ 4.101 a 4.104, 8.103.6, 8.103.9generator circuit-breakerIEEE C37.013-1997§ 5.8.2, 6.2.9.2, 7.3.9generator circuit-breaker
Results
—
—
—
—
—
Charts
- Most offset phase
- Other phases
- DC component
- Separation and maximum arc
How it was calculated and standards
Step-by-step calculation
Need it for a real project? We carry out the full study, with its report.
What it is for
The generator circuit-breaker sits between the generator and its step-up transformer. It must break two very different faults: the one fed by the network through the transformer, with a lot of current, and the one fed by the generator itself, with less current but with a DC component that can keep the current from passing through zero.
This tool simulates both, finds the first current zero of each phase and compares it with the maximum arcing time of the breaker. It also checks the class G1 or G2 the application needs and the current if the generator is connected out of phase.
How it is calculated
IEC/IEEE 62271-37-013:2015§ anexo E.4generator-source fault
AC component of the generator
I(t) = E·In·[1/xd + (1/x′d − 1/xd)·e−t/T′d + (1/x″d − 1/x′d)·e−t/T″d]The DC component of a phase is √2·E·In/x″d·cos α·e−t/Ta with x″q = x″d (otherwise the mean of 1/x″d and 1/x″q is used), with α the angle of its voltage at fault inception. The degree of asymmetry is the DC over the peak of the AC.
IEC/IEEE 62271-37-013:2015§ 8.103.6.3.3system-source fault
System current and asymmetrical capability
Isc = E·U/(√3·|Znet + ZT|) · Iasym = Isc·√(1 + 2·Asy²) · Asy = e−t/τThe standard tests the breaker with τ = 133 ms and a separation equal to the half-cycle delay plus the minimum opening time.
IEC/IEEE 62271-37-013:2015§ 8.103.9.1phase opposition
Out-of-phase current
Ioph = δ·In/(x″d + xt + xs) · δ = 2·sin(φ/2)δ is √2 at 90° and 2 at 180°. The rated out-of-phase current is 50 % of the system-source breaking current, on a 90° basis.
Limits of the calculation
- The generator is at no load before the fault. With load and a leading power factor the asymmetry can be higher, and the standard asks for a simulation with the real data.
- The arc at the fault location, which lowers the asymmetry, and the contribution of the auxiliary motors are not included.
- The class is checked only with the generator at no load (8.103.6.3.7.3). With previous lagging or leading load the standard also asks for a simulation (8.103.6.3.7.2 and 8.103.6.3.7.4), and the three conditions must be met at the same time.
- Each phase is looked at on its own: the change in the other phases after the first pole clears is not calculated.
- The arc-voltage effect is an estimate. The capability proof is made with the manufacturer's arc characteristic.
Frequently asked questions
Why may the generator current not pass through zero?
Because the AC component decays with the subtransient and transient constants of the generator and the DC decays with the armature one, which is longer. If at contact separation the DC exceeds the AC peak, the asymmetry passes 100 % and the current takes a while to cross zero. The breaker must force that zero with its arc voltage within its maximum arcing time.
What is the difference between classes G1 and G2?
Both are defined in IEC/IEEE 62271-37-013:2015. A class G1 is tested with an asymmetry of 110 % with its rated generator-source current and of 130 % with 74 % of that current. A class G2 is tested with 130 % with the full current.
Which fault gives the generator circuit-breaker more current?
In almost every power plant the system-source one, through the step-up transformer, because the reactance of the transformer and the network is lower than the generator's. The generator-source fault gives less current but more asymmetry.
We review the application of your generator circuit-breaker
We calculate the fault currents of your power plant and check the class and timing of the breaker with the data of your equipment.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws