Home / Tools / Time synchronisation
Time synchronisation: PTP, IRIG-B and NTP
Choose how the time reaches the IED and for which function. The tool draws the chain from the antenna to the IED, adds up the error of each device, compares it with the accuracy the function requires and computes how long it holds after losing GPS.
Results
—
—
—
—
Charts
How it was calculated
Error budget
What it is for
Each function requires a different time accuracy: an event recorder is satisfied with one millisecond and a merging unit needs one microsecond. This tool adds up the error of each device between the GPS clock and the IED, tells which class the chain reaches and how long it holds when the satellite signal is lost.
How it is calculated
Source: IEC/IEEE 61850-9-3:2016, cl. 7
PTP
e = eGM + N · eTC or BC + Δasym / 2 + eIEDWorst case: the errors add up. The profile aims at less than 1 µs after about 15 transparent clocks or 3 boundary clocks.
Source: IRIG Standard 200
IRIG-B
e = eclock + L / (Vp · c) + edecodingIf the IED compensates the cable delay, the cable term disappears.
Source: RFC 5905
NTP
e ≤ eserver + δ / 2 + eclientδ is the round-trip delay the client measures.
Source: own derivation
Holdover and synchrophasors
tholdover = (erequired − e) / drift; tTVE 1 % = 2 · asin(0.005) / (2π f)At 60 Hz, a time error of 26.5 µs already gives 1 % TVE even if the magnitude is perfect.
Limits of the calculation
- It adds up the errors in the worst case; in practice part of them cancel out.
- The oscillator drift is taken as constant; a real oscillator changes with temperature and ageing.
- It does not model redundant grandmasters or the change of master.
- It does not replace the measurement of the time in your devices. The example cases are illustrative.
Frequently asked questions
Why is NTP not suitable for sampled values?
Because its error is bounded by half the round-trip delay of the network, which on a LAN is tenths of a millisecond. Merging units need 1 µs: only PTP with the power profile or a 1PPS signal reaches it.
How long does a merging unit hold without GPS?
As long as its oscillator takes to drift from the current error to the limit. With 450 ns of margin and an oscillator drifting 10 ns per second, that is 45 s. The holdover figure is declared by the merging unit manufacturer.
Should the IRIG-B cable be compensated?
For events, no: a few hundred nanoseconds do not matter against 1 ms. For synchrophasors or line differential, yes: 150 m of coaxial already delay about 0.76 µs.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws