Function 46BC: broken conductor

Broken conductor from the I2/I1 ratio: minimum and maximum I1, long delay, inside the relay and a test plan for the injection kit.

IEEE C37.2§ 3.1.46function numbersGE F60 1601-0093-AB2§ 5.9.0.8broken conductor

Example cases
Function 46BC: broken conductor

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
%

With one phase open and the other two unchanged the ratio is 50%: set it below that. Range 20 to 100% in the GE F60.

pu of In

With less load the ratio is not reliable and the function does not operate.

pu of In

Above it the condition is treated as a fault; set it below the maximum load according to the cited manual.

s

Long, to coordinate with the dead time of single-pole reclosing.

E3Simulation
A
% of the other phases

100% is normal service; 0% is the phase A conductor broken. The change is taken as sudden, from normal service.

E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
percentage points

Estimate: the GE F60 manual 1601-0093-AB2 does not state the accuracy of broken conductor detection. Enter your relay's value.

%

Estimate: the GE F60 manual 1601-0093-AB2 does not state the accuracy of broken conductor detection. Enter your relay's value.

% of In

Estimate: the GE F60 manual 1601-0093-AB2 does not state the accuracy of broken conductor detection. Enter your relay's value.

%

Estimate: the GE F60 manual 1601-0093-AB2 does not state the accuracy of broken conductor detection. Enter your relay's value.

cycles

Estimate: the GE F60 manual 1601-0093-AB2 does not state the accuracy of broken conductor detection. Enter your relay's value.

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

I2/I1 ratio

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 46BC detects a broken conductor or a breaker pole that did not close. If the conductor falls without touching ground there is no fault current: the overcurrent protection does not see it, but the load stays fed by two phases and the currents become unbalanced.

It measures the ratio between the negative-sequence and positive-sequence currents, which does not depend on how much load the line carries.

How it operates

  • With a healthy network I2/I1 is almost zero. If one phase opens and the other two keep the same current, the ratio rises to 50%; with other loads it can reach 100%.
  • The relay of the cited manual also requires one phase to have dropped suddenly below the minimum I1: so a load unbalance, even with a high ratio, is not taken as a broken conductor.
  • Below a minimum I1 the ratio is not reliable, and above a maximum I1 the condition is taken as a fault: in those cases the function does not operate.
  • The delay is long so that it does not act during the dead time of a single-pole reclose or on fault transients.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The plan opens phase A suddenly and finds the I2/I1 pickup by turning the angle between IB and IC: at 120° the ratio is 50% and at 60° it is zero. It measures the delay by opening phase A suddenly, and checks that an unbalance without a lost phase does not operate.

With phase A open it finds the minimum I1 by raising the other two phases and the maximum by continuing until the function resets. It checks that it does not operate with a balanced set or with fault I1.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • It only detects one broken conductor; with two or three open the ratio is not useful, as the cited manual warns.
  • A load in which the healthy phases do not change is simulated; the real ratio depends on the load and the source.
  • The tolerances are an estimate: the manual does not state the accuracy of this function. Other relays, such as the SEL-751 with the Arc Sense option, use another method: the line charging current.

Frequently asked questions

Why is the ratio 50% with one phase open?

With phase A at zero and the other two equal at 120°, I1 is two thirds of the phase current and I2 is one third: the ratio is one half.

Why not use only the negative-sequence current?

Because I2 grows with the load: with little load a broken conductor gives little I2. The I2/I1 ratio is the same at any load, so a single setting works.

Why is the delay so long?

So that it does not trip during the dead time of a single-pole reclose, when a phase is open on purpose, or on fault transients. The cited manual has 20 s by default.