Home / Tools / Function 27/59 voltage
Function 27/59: undervoltage and overvoltage
Definite-time undervoltage and overvoltage: pickup, reset, VT blocking, the relay inside and an injection test plan.
Siemens SIPROTEC 5§ 11.31overvoltageSiemens SIPROTEC 5§ 11.37undervoltageIEEE C37.2§ 2008function numbers
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 27 trips when the voltage falls below a value and stays there for a time; the 59 when it rises. Both take the voltage from the bus or line VT and need no current.
The 27 is blocked when the VT circuit breaker trips: without that block, an open VT secondary looks like an undervoltage and trips the bay. A blown fuse has no auxiliary contact: the relay's measuring-voltage failure supervision detects it.
How it operates
- The 27 picks up below the setting and resets when the voltage rises above the setting multiplied by its reset ratio, greater than 1.
- The 59 picks up above the setting and resets below the setting times its reset ratio, less than 1.
- With the current criterion on, the 27 picks up only if current flows, so it does not trip with the breaker open.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The plan injects a balanced three-phase set: each phase carries the phase-to-phase voltage divided by √3. It finds pickup and reset with ramps and measures the time at 80 % of the 27 setting and at 110 % of the 59 setting.
If stage 2 of the 59 already operates at that voltage, the plan marks it. At the end it checks that the 27 does not trip when the test set output activates the VT circuit breaker input.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- A balanced three-phase voltage is simulated; the single-phase, two-phase or three-phase modes of each relay are in its manual.
- The times do not include the relay's own operating time.
- IEC 60255-127 was not consulted: the tolerances are those of the cited manual.
Frequently asked questions
Why is the reset ratio of the 27 greater than 1?
Because the 27 picks up on low voltage: to reset, the voltage has to rise above the pickup. With a pickup of 92 V and a ratio of 1.05, it resets at 96.6 V.
What happens if the VT circuit breaker trips?
The voltage drops to zero and the 27 sees it as a real undervoltage. That is why the auxiliary contact of the VT circuit breaker is wired to the relay and blocks the 27. If the secondary is protected with fuses, which have no contact, the block comes from the relay's measuring-voltage failure supervision.
What voltage is applied to each phase?
With the phase-to-phase voltage divided by √3 and phase shifts of 120°: a setting of 92 V phase to phase is 53.1 V per phase.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
