Commissioning checklist per equipment

Choose the equipment and the commissioning stage and get what to verify, with the reference standard of each point. Tick what has been verified, write remarks and download the list as PDF or CSV.

IEC 60076-1transformersIEC 62271-100circuit breakersIEC 61869-2instrument transformersIEEE C37.233protection testingIEC 62446-1photovoltaic systemsANSI/NETA ATSacceptance testing

Example cases
Commissioning checklist per equipment
E1Equipment and stage

E2Identification
Verified points

—

Pending points

—

Points with remarks

—

Points in the list

—

What to verify

CodeWhat to verifyReferenceCriterionVerifiedRemark

Reference standards of this list

StandardTitle

What it means for your project

    Result not what you expected? We check it with you on site.

    What it is for

    To prepare or review the commissioning scope of each piece of equipment before going to site, to leave no point uncovered when moving from one stage to the next, and to hand the client a signed list of what was verified and what was left with remarks. It applies to medium, high and extra-high voltage substations, industrial plants, solar plants and battery energy storage systems.

    How the list is built

    IEC 62337commissioning stages and milestonesEN 50110-1operation of electrical installations

    • Three stages: cold, with the power circuits de-energized (inspection, static tests of each item and functional tests with the auxiliary supplies); energization, with the conditions for applying voltage for the first time and what is observed when doing so; and hot, with voltage and load, where what does not exist without them is verified.
    • Closing the cold stage: every energization starts with the non-conformities resolved or accepted in writing, the temporary earths removed and an approved switching sequence with a single person in charge.

    IEC 60076-1transformersIEC 62271-100circuit breakersIEC 61869-2CTIEEE C37.233protectionIEC 62446-1photovoltaicsANSI/NETA ATSacceptance testing

    • One standard per point: each point cites the equipment standard or the guide that covers it (IEC, IEEE, NETA or NFPA). The standard and its topic are cited, never an unverified clause number.
    • Acceptance criterion: written only where the standard sets it in general terms (the ratio tolerance of IEC 60076-1, the class limit of a CT in IEC 61869-2, the auxiliary voltage range of IEC 62271-1) or where the reference is the factory test report. Every other point says «per standard and manufacturer»: the value is set by the standard, the manufacturer and the approved project test plan.
    • What, not how: the list names the check, not the procedure. Test connections, test sets, sequences and values depend on the actual equipment and its manufacturer.
    • Grid operator requirements: in solar plants and BESS some points depend on what the grid operator of each country requires; the list marks them as such, without citing a standard.

    Limits of the list

    • It is a general list per equipment type; the project test plan adds or removes points according to the technology, the voltage level and the contract.
    • It is not a procedure: it does not say how to perform each test, with which test set or in which order.
    • It carries no acceptance values of its own; where it says «per standard and manufacturer», the value comes from the standard, the factory test report and the manual.
    • Ticks and remarks are stored only in this browser; download the PDF or the CSV to keep them.
    • Work safety (isolation and lock-out, clearances, permits) follows the site rules and local regulations.

    Frequently asked questions

    What should a commissioning checklist include?

    For each piece of equipment and each stage: what is inspected and what is tested, the standard behind it, the acceptance criterion, a verified box and space for remarks. The criterion comes from the standard, the factory test report and the manufacturer's manual; a list with values and no source is not valid evidence.

    What is the difference between cold and hot commissioning?

    Cold commissioning is done with the power circuits de-energized: inspection, static tests of each item and functional tests with the auxiliary supplies. Hot commissioning starts once the installation is energized and verifies what only exists with voltage and load: phase sequence and phasing, directionality of the protections, real measurements and thermography.

    Where are the acceptance values of each test?

    In the standard of each equipment type, in the factory test report and in the manufacturer's manual, and the approved project test plan fixes them for each item. That is why the list cites them as «per standard and manufacturer» and only writes a criterion where the standard sets it in general terms, such as the accuracy class limit of a CT.

    We commission your equipment

    Our team performs the cold tests, the energization and the hot checks of substations, industrial plants and solar plants, with a signed test record for each item.

    Related guides

    Other tools

    FreeCOMTRADE generatorCreate a COMTRADE fault record (.cfg/.dat or .cff) for your test set: fault, DC offset and breaker opening.FreeANSI / IEEE C37.2 device numbersDevice function numbers 1 to 94, common suffixes and their IEC 61850 logical node, with search.FreeRelay coordinationOnline protection coordination, no Excel sheet: up to six relays, reclosers and fuses on a log-log plot, with the IEEE C57.109 damage curve, inrush and the margin of each pair.FreeInverse-time curvesCalculator and log-log plot of the IEC 60255-151 and IEEE C37.112 curves, with the coordination margin.FreeCT burdenLead resistance, relay burden and comparison with the rated burden of the current transformer.FreeShort-circuit currentQuick estimate of the three-phase fault at the secondary of a transformer.FreeCOMTRADE viewerOpen .cfg/.dat or .cff fault records in your browser: waveforms, digital channels, cursor and RMS. The file is not uploaded.FreeIEC 61850 SCL viewerOpen .scd, .cid or .icd files in your browser: IEDs, GOOSE and SV addresses, datasets, subscribers and checks. The file is not uploaded.FreeGOOSE and SV addressesCheck IEC 61850 multicast MAC, APPID, VLAN and priority, find duplicates and export the table as CSV.FreeProcess bus networkSV and GOOSE bandwidth, worst-case latency, PRP, HSR or RSTP redundancy and PTP time error of an IEC 61850 network.FreeInterlocking table and CILO equationsInterlocking matrix per device, IEC 61850 EnaOpn and EnaCls equations, GOOSE signals between bays and FAT/SAT test cases per configuration.FreePer-unit base conversionBase current and impedance, conversion between %, pu and ohms, and change of base for transformers, generators and lines.FreeHarmonic distortion THD and TDDVoltage THD and current TDD against the IEEE 519-2022 limits, with the spectrum as a bar chart.FreeSymmetrical componentsPhase quantities to zero, positive and negative sequence and back (Fortescue), with phasor diagrams and what they mean for 46, 67Q and 51N.FreeVector group compensation (87T)TAP of each winding, phase compensation matrix, zero-sequence removal and the HV-to-LV clock diagram.FreePrimary and secondary impedance (21)Primary to secondary ohms with the CT and VT ratios, line Z1, Z0 and k0, and zone reaches on the R-X plane.FreePhasor diagramLearn to read phasors with lessons and challenges, and review your load check: CT polarity, rotation, 87T, P-Q and R-X.FreeCT saturationRequired versus available voltage (5P/10P, PX or C class), time to saturation and the saturated waveform.FreeDGA interpretationIEEE C57.104-2019 DGA status, Duval triangles 1, 4 and 5, IEC 60599 ratios and CO₂/CO of your transformer.FreeInsulation temperature correctionInsulation resistance at 40 °C (IEEE 43) or 20 °C, PI, DAR and power factor of transformers and bushings, with the trend.FreeCapacitor bankkvar to correct the power factor, steps of the automatic bank, capacitance and resonance with the transformer.FreeCable voltage dropΔV and % with R and X per km, copper or aluminium, mm² or AWG/kcmil, and the short-circuit check of the cable size.FreeBattery sizingAh, number of cells and charger of a DC battery bank from its duty cycle, per IEEE 485 and IEEE 1115.FreeGrounding resistanceGround rods, horizontal conductor and grid (BS 7430, IEEE 80), and soil resistivity from Wenner measurements.FreeTechnical glossarySubstation, protection and communications terms, explained in one or two sentences.