IEC 60870-5-104 APDU frame decoder
Paste the hexadecimal frames from an IEC 60870-5-104 capture and see every field: the APCI with its I, S or U format and the N(S) and N(R) numbers, and the ASDU with its type, cause of transmission, common address and information objects with their IOA address.
IEC 60870-5-104APCI, APDU and I, S and U formatsIEC 60870-5-101ASDU, types and causes of transmissionIEC 60870-5-4information elements and CP56Time2a time
Results
—
—
—
—
Charts
Frame fields
| Octets | Field | Value | Detail |
|---|
How it was calculated and standards
Frames in the capture
| # | Direction | Summary | Status |
|---|
How the frame was read
What it means for your link
What it is for
To read a network capture of the telecontrol link between the control centre and the substation without opening a protocol analyzer: check that the master sent STARTDT and the station confirmed it, see which type of data arrives with which cause for each object, compare the common address and object addresses with the signal list, and understand why the station rejected a command.
It also helps to compare what the interoperability list says with what really travels: a type that is not on the list, a negative confirmation or an N(S) sequence with gaps show up at once.
How it is decoded
IEC 60870-5-104APCI and I, S and U formats
The APCI
APDU = 68H + L + C1 C2 C3 C4 [+ ASDU] · size = L + 2 ≤ 255 · ASDU = L − 4 ≤ 249- Start and length: the first octet is always 68H; the second, L, counts the octets that follow it. The maximum APDU length is 253 and the minimum 4 (only the four control octets).
- I format (bit 0 of C1 = 0): N(S) = (C1 + 256·C2) ÷ 2 and N(R) = (C3 + 256·C4) ÷ 2, 15-bit numbers that wrap to 0 after 32,767. It carries an ASDU.
- S format (C1 = 01): only N(R), the number of the next I frame it expects to receive. It carries no ASDU.
- U format (bits 0 and 1 of C1 = 1): a single function in bits 2 to 7 of C1. STARTDT 07 (command) and 0B (confirmation), STOPDT 13 and 23, TESTFR 43 and 83. It carries no ASDU.
IEC 60870-5-101ASDU structure and typesIEC 60870-5-104fields of 2, 2 and 3 octets
The ASDU
ASDU = TI (1) + VSQ (1) + COT (2) + CA (2) + objects · SQ = 0: N·(3 + E) · SQ = 1: 3 + N·E- TI and VSQ: the type identifies the data and its size E per object. The VSQ carries the SQ flag in bit 7 and the number N of objects or elements in bits 0 to 6.
- Cause of transmission: bits 0 to 5 are the cause, bit 6 is P/N (negative confirmation), bit 7 is T (test); the second octet is the originator address. The common address takes two octets and the information object address (IOA) three, both with the least significant octet first.
- SQ = 0: each object carries its own IOA. SQ = 1: a single IOA and N consecutive elements, with addresses IOA, IOA + 1, IOA + 2…
- Length check: the decoder adds up what the VSQ and the type require and compares it with what arrived; it warns if octets are missing or left over.
IEC 60870-5-101information elementsIEC 60870-5-4CP56Time2a and CP24Time2a
Values, quality and time
normalized = NVA ÷ 32,768 · scaled = SVA (signed 16-bit integer) · floating point = 32-bit IEEE 754 (little-endian)- Quality: IV invalid, NT not topical, SB substituted, BL blocked and, on measured values, OV overflow; on integrated totals, CA counter adjusted and CY carry.
- CP56Time2a time (7 octets): milliseconds (0 to 59,999), minute with the IV bit, hour with the SU summer-time bit, day of the month and of the week, month and a two-digit year; the decoder assumes the 2000s. CP24Time2a carries only milliseconds and minute.
- Commands: SCO (single), DCO (double: 1 open, 2 close) and RCO (step: 1 lower, 2 raise) carry the QU qualifier and the S/E bit (select or execute).
- Sequence: in one direction, the N(S) of each I frame must be the previous one plus one; unacknowledged I frames must not exceed k and the other end must acknowledge before w consecutive I frames. The decoder only checks this if you mark the direction of the frames.
The types and causes come from the interoperability lists of real devices (SIPROTEC 5, FreyrSCADA, SYS600) and from Tiza Group guides. The position of each bit inside the octets follows the structure of IEC 60870-5-101 and IEC 60870-5-104; a field that cannot be confirmed with certainty is shown as an undecoded octet. Always confirm against the edition of the standard used in your project.
Decoder limits
- Decodes the process, command and system types in common use (single and double point, step, bit string, measured values, integrated totals, commands, set points, interrogations, clock and test). Protection events, packed single points, parameters and file transfer are recognized by name but not decoded.
- It works with frames already extracted as hexadecimal; it does not open capture files or reassemble a TCP stream split into segments.
- It assumes the 104 field sizes: a 2-octet cause, a 2-octet common address and a 3-octet object address. An IEC 60870-5-101 frame is not decoded correctly.
- It cannot tell whether the time is local or UTC, or whether the common address and object addresses are those of your project: compare them with your signal list.
- Sequence checks need complete frames in order, with their direction marked with > or <.
Frequently asked questions
What is an APDU in IEC 60870-5-104?
It is the complete message that travels over the TCP connection: a six-octet control header (the APCI, with the start octet 68H, the length and four control octets) and, in the I format, an ASDU with the data. It is at most 253 octets long after the start and length octets.
How do I tell an I, S or U frame in the hexadecimal?
Look at the least significant bit of the first control octet, the one after the length. If it is 0 the frame is an I frame (it carries an ASDU and the numbers N(S) and N(R)). If it is 01 it is an S frame (acknowledgement only, with N(R)). If both bits are 11 it is a U frame: 07 and 0B are STARTDT, 13 and 23 STOPDT, 43 and 83 TESTFR.
What does the cause of transmission of a frame mean?
It says why the message is sent: 3 is a spontaneous change, 20 is the answer to a general interrogation, 6 and 7 are the activation of a command and its confirmation. With the P/N bit set to 1 the confirmation is negative, and causes 44 to 47 mean the station does not recognize the type, the cause, the common address or the object address.
We integrate and test your telecontrol link
We integrate the substation with the control centre over IEC 60870-5-104, DNP3 and IEC 61850: signal list, types and causes, commands, time and point-to-point tests against the SCADA, on site or remotely.
Related guides
Other tools
All tools (24)
Solar energy
Protection
ANSI / IEEE C37.2 device numbersPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt ramp
Analysis and communications
COMTRADE records: viewer and generatorIEC 61850 SCL viewerIEC 61850 network: GOOSE/SV addresses and process busInterlocking table and CILO equationsTechnical glossary
Equipment testing and diagnostics
Commissioning checklistInsulation diagnosis: dissolved gases (DGA) and temperature correction
Electrical studies
Short circuit and per-unit systemArc flashGrounding resistance
Industry and power quality
Motor startingHarmonic distortion THD and TDDCapacitor bankBattery sizing