Short-circuit current at the secondary of a transformer

Estimate the bolted three-phase fault at the secondary terminals with IEC 60909-0 or with the simple estimate, with or without the upstream source, and see the peak current with full asymmetry. It does not replace a short-circuit study.

IEC 60909-0§ 6.3.3transformer KT correctionIEC 60909-0voltage factor c, table 1IEC 60909-0peak current, factor κ

Example cases
Short-circuit current at the secondary of a transformer
E1Transformer
kVA

From the nameplate.

V

Line to line.

%

From the nameplate, on the rated power base.

Only for the peak current. Use the value from the test report.

E2Upstream source
MVA

Given by the utility at the point of connection.

E3Method

Up to 1 kV; above it, c = 1.10.

Only for the waveform.

Use a decimal point. The calculation runs in your browser and updates as you type.

Three-phase fault I″k

— kA

Peak current ip

— kA

Short-circuit power

— MVA

Rated current

— A

Times rated current

—

IEC 60909 versus simple

— %

Fault current versus source strength
  • IEC 60909-0
  • Simple estimate
  • Infinite bus, IEC
  • Selected source
Source short-circuit power on a logarithmic scale. As the source gets stronger, the current approaches the infinite-bus value, limited only by the transformer.
Current with full asymmetry
  • i(t) with DC component
  • Symmetrical
  • Peak ip
Fault at the voltage zero crossing, with the X/R entered. The vertical divisions are cycles. The peak of the curve matches κ · √2 · I″k within 2 %.

Step-by-step calculation

What it means for your equipment

    What it is for

    The three-phase fault at the secondary terminals is the first figure you need to choose the interrupting rating of a switchboard, check an instantaneous setting or size busbars. This tool gives a quick estimate with the IEC 60909-0 method and compares it with the simple estimate many engineers use from memory, so you can see how far short it falls.

    How it is calculated

    Rated current

    In = Sn / (√3 · Un)

    IEC 60909-0§ 6.3.3KT correctionIEC 60909-0factor c, table 1

    IEC 60909-0 method (maximum initial symmetrical current)

    I″k = cmax · In / (KT · uk + zQ) · KT = 0.95 · cmax / (1 + 0.6 · xT)

    With uk = uk% / 100. The voltage factor cmax is 1.05 or 1.10 at low voltage depending on the system tolerance, and 1.10 above 1 kV. Here xT = uk, which gives the highest current. The upstream source is modelled as ZQ = cQ · UnQ² / S″kQ, which in per unit on the transformer base becomes zQ = cQ · Sn / S″kQ, with cQ = 1.10. With an infinite bus, zQ = 0. Since cmax / KT = (1 + 0.6 · xT) / 0.95, on an infinite bus the result does not depend on cmax.

    Simple estimate

    Ik = In / (uk + Sn / S″kQ)

    Without the c factor or KT, it gives 5 % to 10 % less than IEC 60909, so it is not suitable for choosing the interrupting rating. The short-circuit power is S″k = √3 · Un · I″k in both methods.

    IEC 60909-0peak current

    ip = κ · √2 · I″k · κ = 1.02 + 0.98 · e−3R/X

    The waveform on the screen is i(t) = √2 · I″k · (e−t/T − cos ωt), with T = (X/R) / ω: the fault that starts at the voltage zero crossing, which has the largest asymmetry.

    Limits of the calculation

    • Bolted three-phase fault at the secondary terminals, with the transformer on the nominal tap.
    • Impedances added in magnitude, without separating resistance and reactance; the X/R is used only for the peak current.
    • No contribution from motors, generators or inverters on the low-voltage side, and no cable or busbar impedance up to the fault, so the value is on the high side at the terminals.
    • A study per IEC 60909-0 (or IEEE 551) models the whole network, separates R and X, adds the contributions of rotating machines and converter-based generation, and also calculates the unbalanced faults. That is the result to use for specifying equipment and setting protection.

    Frequently asked questions

    How is the short-circuit current at a transformer secondary calculated?

    The simple estimate divides the rated current by the per-unit impedance: Ik = In / (uk% / 100). IEC 60909-0 adds the voltage factor c and the K_T correction of the transformer impedance, which gives a higher value. For example, 1000 kVA, 440 V and 5.75 % give 22.8 kA with the simple estimate and 24.9 kA with IEC 60909 on an infinite bus.

    What is the IEC 60909 K_T factor?

    It is the impedance correction of a network transformer for the maximum-current calculation: K_T = 0.95 · c_max / (1 + 0.6 · x_T), with x_T the relative reactance. Since K_T is below 1 for usual transformers, it lowers the impedance and raises the calculated fault current.

    What is the peak current ip and what is it used for?

    It is the maximum instantaneous value of the fault current, DC component included: ip = κ · √2 · I″k, with κ = 1.02 + 0.98 · e^(−3R/X) per IEC 60909-0. It is used to check the making capacity of circuit breakers and the dynamic forces on busbars and supports.

    We carry out your short-circuit study

    We model your system with the utility data and your equipment nameplates, calculate the faults per IEC 60909 or IEEE 551, and deliver the interrupting-rating check and the protection coordination.

    Other tools

    COMTRADE generatorCreate a COMTRADE fault record (.cfg/.dat or .cff) for your test set: fault, DC offset and breaker opening.ANSI / IEEE C37.2 device numbersDevice function numbers 1 to 94, common suffixes and their IEC 61850 logical node, with search.Relay coordinationUp to six relays, reclosers and fuses on a log-log plot, with the IEEE C57.109 damage curve, inrush and the coordination margin of each pair.Inverse-time curvesCalculator and log-log plot of the IEC 60255-151 and IEEE C37.112 curves, with the coordination margin.CT burdenLead resistance, relay burden and comparison with the rated burden of the current transformer.COMTRADE viewerOpen .cfg/.dat or .cff fault records in your browser: waveforms, digital channels, cursor and RMS. The file is not uploaded.IEC 61850 SCL viewerOpen .scd, .cid or .icd files in your browser: IEDs, GOOSE and SV addresses, datasets, subscribers and checks. The file is not uploaded.GOOSE and SV addressesCheck IEC 61850 multicast MAC, APPID, VLAN and priority, find duplicates and export the table as CSV.Process bus networkSV and GOOSE bandwidth, worst-case latency, PRP, HSR or RSTP redundancy and PTP time error of an IEC 61850 network.Interlocking table and CILO equationsInterlocking matrix per device, IEC 61850 EnaOpn and EnaCls equations, GOOSE signals between bays and FAT/SAT test cases per configuration.Per-unit base conversionBase current and impedance, conversion between %, pu and ohms, and change of base for transformers, generators and lines.Harmonic distortion THD and TDDVoltage THD and current TDD against the IEEE 519-2022 limits, with the spectrum as a bar chart.Symmetrical componentsPhase quantities to zero, positive and negative sequence and back (Fortescue), with phasor diagrams and what they mean for 46, 67Q and 51N.Vector group compensation (87T)TAP of each winding, phase compensation matrix, zero-sequence removal and the HV-to-LV clock diagram.Primary and secondary impedance (21)Primary to secondary ohms with the CT and VT ratios, line Z1, Z0 and k0, and zone reaches on the R-X plane.CT saturationRequired versus available voltage (5P/10P, PX or C class), time to saturation and the saturated waveform.DGA interpretationIEEE C57.104-2019 DGA status, Duval triangles 1, 4 and 5, IEC 60599 ratios and CO₂/CO of your transformer.Insulation temperature correctionInsulation resistance at 40 °C (IEEE 43) or 20 °C, PI, DAR and power factor of transformers and bushings, with the trend.Capacitor bankkvar to correct the power factor, steps of the automatic bank, capacitance and resonance with the transformer.Cable voltage dropΔV and % with R and X per km, copper or aluminium, mm² or AWG/kcmil, and the short-circuit check of the cable size.Battery sizingAh, number of cells and charger of a DC battery bank from its duty cycle, per IEEE 485 and IEEE 1115.Grounding resistanceGround rods, horizontal conductor and grid (BS 7430, IEEE 80), and soil resistivity from Wenner measurements.Technical glossarySubstation, protection and communications terms, explained in one or two sentences.