Harmonic distortion: THD and TDD

Enter the harmonics you measured at the point of common coupling and get voltage THD or current TDD, checked against the IEEE 519-2022 limits for the voltage level and the Isc/IL ratio.

IEEE 519-2022table 1, voltage limitsIEEE 519-2022table 2, current limits from 120 V to 69 kV

Example cases
Harmonic distortion: THD and TDD
E1What you measured
kV
A
E2Point of common coupling
A
kA
E3Spectrum

Orders 2 to 50. Separate order and value with a space, semicolon or tab; use a decimal point.

Use a decimal point. The calculation runs in your browser and updates as you type.

TDD

— %

Current THD

— %

Individual harmonics

—

Highest harmonic

—

Isc/IL ratio

—

TDD limit

— %

Harmonic spectrum
  • Measured harmonic
  • IEEE 519-2022 individual limit
Each bar is one harmonic. The yellow mark is its individual limit; red bars exceed it.

Harmonic by harmonic

OrderValueLimitLimit used

What it means at the PCC

    What it is for

    For a quick check of a power quality measurement: whether the voltage distortion the plant receives, or the current distortion it injects into the grid, stays within the IEEE 519-2022 limits, which harmonic fails and by how much. It also compares the spectrum of a drive before and after a filter.

    How it is calculated

    IEEE 519-2022definitions, harmonics up to order 50

    THD = √(Σ Mh², h = 2 a 50) / M1 · 100TDD = √(Σ Ih², h = 2 a 50) / IL · 100

    M is the voltage or current of each order and IL the maximum demand load current at the PCC (15 or 30 minute average). Individual current limits are given in % of IL, and voltage limits in % of the fundamental.

    Table 1, voltage limits at the PCC (unchanged from 2014):

    Voltage at the PCCIndividual harmonic (%)THD (%)
    V ≤ 1.0 kV5.08.0
    1 kV < V ≤ 69 kV3.05.0
    69 kV < V ≤ 161 kV1.52.5
    161 kV < V1.01.5 (2.0 if caused by an HVDC terminal)

    Table 2, current limits for systems from 120 V to 69 kV, in % of IL:

    Isc/IL2 ≤ h < 1111 ≤ h < 1717 ≤ h < 2323 ≤ h < 3535 ≤ h ≤ 50TDD
    < 20 (and all power generation)4.02.01.50.60.35.0
    20 to < 507.03.52.51.00.58.0
    50 to < 10010.04.54.01.50.712.0
    100 to < 100012.05.55.02.01.015.0
    > 100015.07.06.02.51.420.0

    IEEE 519-2022even harmonics and generation

    Even harmonics: in the 2022 edition, orders 2, 4 and 6 are limited to 50 % of the table value and even orders above 6 to 100 % (in 2014 all even harmonics were 25 %). Currents with a DC offset, such as those of half-wave converters, are not allowed. All power generation uses the Isc/IL < 20 row, whatever its actual ratio.

    Isc/IL = 1000 exactly falls between the "100 to < 1000" and "> 1000" rows; the tool uses the first one, which is the stricter.

    Values from IEEE Std 519-2022, tables 1 and 2, checked against their reproduction by manufacturers of power quality analyzers and harmonic filters. For a PCC above 69 kV (tables 3 and 4) we could not check the values against a primary source: the tool calculates TDD but does not compare it.

    Limits of the calculation

    • IEEE 519 is assessed at the point of common coupling and statistically, with measurements over a week or more (percentiles of very short and short time values), not with a single reading; this tool compares one spectrum.
    • It does not assess interharmonics, resonances or the contribution of each load.
    • If inverter-based generation at the site is at least 10 % of the average annual demand, IEEE 519-2022 refers to IEEE 1547 or IEEE 2800 for the current limits.
    • IEEE 519 applies from 120 V; the utility may set other limits in its interconnection agreement.
    • A diagnosis and a solution need a harmonic study.

    Frequently asked questions

    How is voltage THD calculated?

    It is the square root of the sum of the squares of the voltage harmonics from order 2 to 50, divided by the fundamental and multiplied by 100. For example, with 4 % fifth harmonic and 3 % seventh, THD is √(4² + 3²) = 5 %.

    What is the difference between current THD and TDD?

    THD divides the distortion by the fundamental current at that moment; TDD divides it by the maximum demand load current IL at the point of common coupling. At light load THD looks high even when the harmonic amperes are small, which is why IEEE 519 sets the current limits as TDD and as a percentage of IL.

    What is the voltage THD limit in IEEE 519-2022?

    At the point of common coupling: 8 % up to 1 kV, 5 % from 1 to 69 kV, 2.5 % from 69 to 161 kV and 1.5 % above 161 kV. Each individual harmonic has a lower limit: 5, 3, 1.5 and 1 % respectively.

    We carry out your power quality study

    We measure with class A analyzers (in Colombia, or elsewhere on request), model the network to find resonances, compare with IEEE 519 and size the solution: filters, reactors or configuration changes.

    Other tools

    COMTRADE generatorCreate a COMTRADE fault record (.cfg/.dat or .cff) for your test set: fault, DC offset and breaker opening.ANSI / IEEE C37.2 device numbersDevice function numbers 1 to 94, common suffixes and their IEC 61850 logical node, with search.Relay coordinationUp to six relays, reclosers and fuses on a log-log plot, with the IEEE C57.109 damage curve, inrush and the coordination margin of each pair.Inverse-time curvesCalculator and log-log plot of the IEC 60255-151 and IEEE C37.112 curves, with the coordination margin.CT burdenLead resistance, relay burden and comparison with the rated burden of the current transformer.Short-circuit currentQuick estimate of the three-phase fault at the secondary of a transformer.COMTRADE viewerOpen .cfg/.dat or .cff fault records in your browser: waveforms, digital channels, cursor and RMS. The file is not uploaded.IEC 61850 SCL viewerOpen .scd, .cid or .icd files in your browser: IEDs, GOOSE and SV addresses, datasets, subscribers and checks. The file is not uploaded.GOOSE and SV addressesCheck IEC 61850 multicast MAC, APPID, VLAN and priority, find duplicates and export the table as CSV.Process bus networkSV and GOOSE bandwidth, worst-case latency, PRP, HSR or RSTP redundancy and PTP time error of an IEC 61850 network.Interlocking table and CILO equationsInterlocking matrix per device, IEC 61850 EnaOpn and EnaCls equations, GOOSE signals between bays and FAT/SAT test cases per configuration.Per-unit base conversionBase current and impedance, conversion between %, pu and ohms, and change of base for transformers, generators and lines.Symmetrical componentsPhase quantities to zero, positive and negative sequence and back (Fortescue), with phasor diagrams and what they mean for 46, 67Q and 51N.Vector group compensation (87T)TAP of each winding, phase compensation matrix, zero-sequence removal and the HV-to-LV clock diagram.Primary and secondary impedance (21)Primary to secondary ohms with the CT and VT ratios, line Z1, Z0 and k0, and zone reaches on the R-X plane.CT saturationRequired versus available voltage (5P/10P, PX or C class), time to saturation and the saturated waveform.DGA interpretationIEEE C57.104-2019 DGA status, Duval triangles 1, 4 and 5, IEC 60599 ratios and CO₂/CO of your transformer.Insulation temperature correctionInsulation resistance at 40 °C (IEEE 43) or 20 °C, PI, DAR and power factor of transformers and bushings, with the trend.Capacitor bankkvar to correct the power factor, steps of the automatic bank, capacitance and resonance with the transformer.Cable voltage dropΔV and % with R and X per km, copper or aluminium, mm² or AWG/kcmil, and the short-circuit check of the cable size.Battery sizingAh, number of cells and charger of a DC battery bank from its duty cycle, per IEEE 485 and IEEE 1115.Grounding resistanceGround rods, horizontal conductor and grid (BS 7430, IEEE 80), and soil resistivity from Wenner measurements.Technical glossarySubstation, protection and communications terms, explained in one or two sentences.