Protection CT and VT selector and checker

Choose CT or VT. For the CT, enter the function, the fault current, the X/R and the CT and cable data: the tool calculates the saturation voltage needed, proposes the class, checks the effective ALF and the time to saturate with offset and remanence, and gives you the longest cable. For the VT it checks the burden and the cable.

IEC 61869-2:2012§ 5.6.202P and PX protection CT classesIEEE C37.110-2007§ 3.21, 7.1CT application in protectionIEC 61869-3:2011§ 5.6.302.3Protective VTsIEC 60044-1:1996+A1:2000§ 12, 13, 14old classes P, PR and PXAlstom NPAG§ 6CT and VTSiemens 7UT6x§ D.1Ktd of its differential

Example cases
Protection CT and VT selector and checker

Only the basic data; the rest is taken with typical values.

ALearn

E1Instrument
E2Function and fault
A

Primary current of the external fault, or the current the CT must measure.

%
E3Available CT
A
Ω

From the nameplate or test report, at 75 °C.

VA

Accuracy limit factor (ALF): 5, 10, 15, 20 or 30.

V
E4Cable and relay
m

Numerical: under 1 VA; electromechanical: several VA.

°C
Ω
E5Voltage transformer
VA
VA
VA
V

The actual voltage across the loads: phase to phase (for example 115 V) or phase to neutral (66.4 V) depending on the connection.

m

The one on the VT nameplate or specification.

% Un

Maximum continuous network voltage, as a % of the VT rated voltage.

E6Plate of an existing CT

The tool gives its IEC 61869-2:2012 equivalent and tells you whether it serves the function above.

Ω

At 75 °C. The ratio and the secondary are those of the «CT in hand» panel.

VA
V
Ω
A
A

If you use a tap of a multi-ratio CT, the class drops in proportion to the turns used.

VA

Use a decimal point. The calculation runs in your browser and updates as you type.

Required saturation voltage or burden

—

Available voltage or cable

—

Saturation or voltage drop

—

Proposed class or burden range

—

From the primary to the relay input
The primary, the instrument with its polarity and earthed star point, the cable out and back and the relay input. Red if the instrument does not comply with this circuit.
Required versus available
Each bar is the saturation voltage a criterion requires, given the fault and burden data. The colored bar is the one the selected function uses, and the available CT must exceed it.
Current with full DC offset
  • Actual current
  • Ideal current
The solid line is what the CT delivers; the dashed line is what it would deliver without saturating. With remanence, the CT saturates sooner.
Excitation curve and equivalent plate
  • Excitation curve (illustrative shape)
  • Characteristic voltages
The curve is anchored at the points the plate guarantees; its shape between them is illustrative. On the right, the existing plate and its IEC 61869-2:2012 equivalent.

Step-by-step calculation

Loading these settings into a relay? We configure it remotely.

What it is for

Every protection setting depends on the CT delivering a faithful current while the function makes its decision. This tool starts from the fault current, the X/R and the real secondary burden (winding, cable and relay) and calculates the saturation voltage the CT needs. With that value it proposes the class, verifies the CT you already have and gives you the maximum cable length.

It extends the “CT saturation” and “CT burden” tools, whose engines it uses without copying them: the voltage each class delivers, the time to saturation and the burden per connection. For the voltage transformer, it checks that the connected burden, including cable loss, is within the range where the class is guaranteed.

How it is calculated

Alstom NPAG§ 6.4.10.1transient factor SEL CPRE 2021Eq. 14

Required saturation voltage

Vsat ≥ K · Krem · (If/N) · (RCT + Rb)

If/N is the secondary fault current, RCT the winding resistance and Rb the external burden (leads according to the connection, relay and others). K is 1 without offset (the overcurrent criterion of IEEE C37.110-2007, 7.1, together with the time-to-saturate check), 1 + X/R to never saturate with a fully offset current (NPAG and SEL), or the Siemens 7UT6x Ktd: 3 for transformers, busbars and lines and 5 for generators and motors. Krem = 1/(1 − remanence), the criterion of the saturation tool; it is not applied with the Siemens Ktd. It is a saturation voltage (EALF for class P, Vx for class C), not the knee-point voltage.

IEC 61869-2:2012§ 5.6.202ALF voltage SEL BKPclass C

Voltage each class delivers

P: EALF = ALF · In · |RCT + Zb| · C: 20 · In · |RCT + Zstd∠60°| · PX: Ek

The rated ALF and the rated burden on the nameplate give the accuracy limit voltage. The effective ALF with the real burden is that voltage divided by In·(RCT + Rb). The tool looks for the lowest standard ALF (5, 10, 15, 20, 30) or the lowest class C that reaches the required voltage; if none does, it asks for a PX CT with Ek equal or higher, which is on the safe side because the knee point lies below saturation.

IEEE C37.110-2007§ 4.5.2time to saturation

Time to saturation with DC offset

ts = −T · ln(1 − (Ks(1 − λ) − 1)/(X/R)) · T = (X/R)/ω

Ks is the ratio between the available voltage and the voltage that the symmetrical current produces, and λ the remanence. If Ks(1 − λ) exceeds 1 + X/R, the CT never saturates; if it is below 1, it saturates with symmetrical current. Modern differential relays need a short time without saturation.

Alstom NPAG§ 6.4.8cable burden SEL BKPout and back

Cable burden and maximum length

Lmax = (Vd/(K·Krem·If,s) − RCT − Rrelay − Rothers) / (kL · rkm)

kL is 2 for a phase-to-ground fault with wye-connected CTs (the cable is traversed out and back) and 1 for a three-phase fault; rkm is the copper resistance at the conductor temperature. SEL recommends limiting cable resistance to 0.5 Ω or less.

CT and VT classes

For class 5P, the NPAG gives a current error of ±1 % and a phase displacement of ±60 minutes at rated current, and a composite error of 5 % at the accuracy limit; for 10P, ±3 % and 10 %. The standard ALF values are 5, 10, 15, 20 and 30. Class PX is defined by knee-point voltage, excitation current and winding resistance; in the IEC definition, a 10 % increase in voltage requires 50 % more excitation current.

For a CT already installed, the «Plate of an existing CT» panel translates its plate into IEC 61869-2:2012. A 5P or 10P plate of IEC 60044-1 keeps its designation, except below 5 VA: the old standard allowed the composite error to be proven at a power factor between 0.8 and 1 and the new one requires 1 below 5 VA, so the guaranteed voltage may fall to a lower ALF. A PX stays PX; it is PXR only if a remanence of 10 % or less was proven, and it is equivalent to 5P or 10P at a given burden when the limiting voltage does not exceed Ek and its exciting current meets the indirect test. A class C is converted with its voltage Vx at 20 times In and an estimated knee: that conversion is an estimate.

For protective voltage transformers, the NPAG gives class 3P with ±3.0 % and ±120 minutes and class 6P with ±6.0 % and ±240 minutes, with the burden between 25 % and 100 % of rated and power factor 0.8. IEC 61869-3:2011 (5.6.302.3) adds burden range I, from 0 to 100 % at power factor 1, and its clause 5.302 sets the voltage factor: 1.2 continuous between phases; 1.5 for 30 s phase to earth with an effectively earthed neutral; 1.9 for 30 s with a non-effectively earthed neutral and automatic tripping; 1.9 for 8 h with an isolated or resonant neutral without tripping.

Limits of the calculation

  • The distance-function factors of each manufacturer could not be verified: the conservative full DC offset criterion is used and the result is labeled an estimate. No formula was consulted for ABB RET, REL and REB670.
  • The limits of the TPX, TPY and TPZ classes (peak error, remanence, time constant) were not consulted: the tool does not calculate them. Request them with the data from the stability study and the reclosing cycle.
  • Remanence is handled with the 1/(1 − λ) factor from the saturation tool. In generators, avoiding asymmetric saturation is usually impossible, even with large CTs (SEL): use identical CTs and a relay with saturation detection.
  • The rated burden of class P CTs combines vectorially at a 0.8 power factor; class C, at 0.5. Nameplate and test-report data take precedence over any typical value.
  • For VTs the tool checks the burden against its range, the cable and the voltage factor. The cable voltage drop is compared with 0.5 %, a criterion of this tool.
  • The equivalences of IEC 185, BS 3938 and the IEEE C, K, H and L classes are estimates: those standards were not consulted, and the IEEE classes are defined by the ratio error and the terminal voltage, not by the composite error and the e.m.f. The shape of the drawn excitation curve is illustrative, anchored at the plate points; the measured curve prevails.
  • It does not replace the CT manufacturer's calculation or the relay manufacturer's sizing program (for example, Siemens CTDIM).

Frequently asked questions

How is the saturation voltage a CT needs calculated?

Multiply the secondary fault current by the total circuit resistance (CT winding, leads and relay) and by a factor. For overcurrent, IEEE C37.110-2007 (7.1) uses the symmetrical current and asks to check the time to saturate of instantaneous elements. To never saturate with a fully offset current the factor is 1 + X/R (NPAG and SEL), and with remanence it is also divided by (1 − remanence). Siemens, for its 7UT6x differential, uses a Ktd of 3 for transformers, busbars and lines and of 5 for generators and motors. The result is a saturation voltage, not the knee-point voltage: IEEE C37.110-2007 (3.21) tells them apart.

Is a 5P20 CT enough for protection?

It depends on the fault current, the X/R and the real burden. A 5P20 guarantees a 5 % composite error up to 20 times rated current with its rated burden; with more burden or with DC offset the CT saturates earlier. The tool calculates the effective ALF with your real burden and tells you which ALF or knee point you need; if not even ALF 30 is enough, you need a class PX CT: the tool asks for a knee point equal to the calculated saturation voltage, which is on the safe side.

What IEC class is a C400 CT equivalent to?

There is no exact equivalence, because IEEE defines class C by a 10 % ratio error and the terminal voltage at 20 times rated current, and IEC by the composite error and the e.m.f. As an estimate, a 5 A C400 gives its saturation voltage with 20 times In into 4 Ω, which the tool compares with a 10P at the burden you choose; for the 5P it uses an estimated knee, because IEEE C37.110-2007 (4.5.3) states that the knee is usually between 50 % and 75 % of the class voltage. If you use a tap, the class drops in proportion to the turns.

How does the secondary cable affect it?

The cable adds its resistance to the CT burden. In a phase-to-ground fault with wye-connected CTs, the current goes out and back through the cable, so twice the length counts; in a three-phase fault, once. At 1 A the cable burden is 25 times lower than at 5 A for the same resistance. The tool calculates the maximum cable length that keeps the CT from saturating.

We review the sizing of your CTs

We calculate the saturation voltage and burden for each function, check saturation with your fault current and set your protection remotely, with no travel.