Function 25: synchronism check

Synchronism check with voltage, frequency and angle windows, dead-line closing, the relay inside and an injection test plan.

Siemens SIPROTEC 5§ 11.55synchronizationIEEE C37.2§ 2008function numbers

Example cases
Function 25: synchronism check

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
V
Hz
°
V
V
s

How the relay compares the bus with the line; the line VT delivers the same connection.

s
E3Simulation
V
V
Hz

The bus frequency is the nominal one.

°
E4Installation and test set
V
V

Example value: enter that of your test set.

E5Relay tolerances
ms
V
mHz
°
%
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Closing angle

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 25 allows a breaker to close only if the voltages on both sides are similar: voltage, frequency and angle differences within their windows. This way closing does not cause a current inrush or stress on the machines.

It also allows closing with one side dead, for example to energize a dead line from a live bus, if the mode permits it.

How it operates

  • It compares U1 of the bus with U2 of the line: both must be above the live-side threshold and their differences within the windows.
  • With frequency slip the angle rotates 360·Δf degrees per second; during the time delay and the breaker closing time it keeps rotating.
  • The close command leaves through the binary output to the breaker close coil.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The test set generates the bus voltage on its three outputs and the line voltage on a fourth, with its own frequency and angle. The plan finds the boundaries of ΔV, Δf and Δφ and the live and dead side thresholds.

To measure the time delay, the binary output of the test set activates the close request and its input reads the close command.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The ΔV window is taken as symmetrical; the cited manual allows different settings for U2 > U1 and U2 < U1.
  • Closing with lead is not calculated for asynchronous networks: the synchronizing and closing tool does that.
  • The line voltage is taken on the same phase and connection as the bus voltage.

Frequently asked questions

Why does the breaker closing time matter?

Because the angle keeps rotating while the contacts travel. With 0.05 Hz of slip and 160 ms between the command and the contact, the angle advances 2.9°.

What is closing on a dead line?

Close when the line has no voltage and the bus is live, to energize it. The function allows it only if the mode authorizes it and the line voltage is below the dead-side threshold.

What does the test set need to test the 25?

Generate two voltage systems with different frequencies: the bus on outputs 1 to 3 and the line on output 4, with control of the angle between them.