Home / Tools / Grounding resistance
Grounding resistance
Estimate the resistance of a ground rod, a group of rods, a horizontal conductor or a substation grid from the soil resistivity, and get that resistivity from your Wenner readings.
BS 7430:2011+A1:2015rods and horizontal conductorsIEEE 80grid resistance (Sverak) and uniform soilIEEE 81resistivity by the Wenner method
Results
— Ω
—
— m
— Ω·m
— Ω·m
—
Want an engineer to review this case? Our team reviews your data and results and quotes the study or the settings work you need.
Charts
- Estimated resistance
- Target
- Measured ρa
- Average
Calculation and details
Step-by-step calculation
What it means for your grounding system
What it is for
To estimate, before detailed design, how many rods or how much conductor a plant or substation grounding system needs, and to interpret resistivity readings in the field: whether the soil looks uniform or changes with depth. It also helps judge whether a resistance measured with the fall-of-potential test is reasonable for the installed electrode.
How it is calculated
BS 7430:2011+A1:2015single rod (Dwight)
R = ρ / (2πL) · (ln(8L/d) − 1)It is the same expression as in the 1998 edition of BS 7430 (10.2).
BS 7430:2011+A1:2015rods in parallel
Rn = R · (1 + λα) / n · α = ρ / (2π · R · s)R is the resistance of a single rod, s the spacing and n the total number of rods. λ depends on the arrangement:
| Arrangement | n | λ |
|---|---|---|
| In a line | 2 to 10 rods | 1.00 · 1.66 · 2.15 · 2.54 · 2.87 · 3.15 · 3.39 · 3.61 · 3.81 |
| Hollow square | 2 to 10, 12, 14, 16, 18, 20 per side | 2.71 · 4.51 · 5.48 · 6.14 · 6.63 · 7.03 · 7.36 · 7.65 · 7.90 · 8.32 · 8.67 · 8.96 · 9.22 · 9.40 |
In the hollow square the total number of rods is 4 · (n − 1). The standard assumes the spacing is at least equal to the rod length, and allows λ = 1.66 for three rods in a triangle or an L. The λ values are those of tables 2 and 3 of the 1998 edition.
BS 7430:2011+A1:2015straight horizontal conductor
R = ρ / (PπL) · (ln(2L² / (w · h)) + Q)With P = 2 for a single run and Q = −1 for a flat strip or −1.3 for a round conductor (1998 edition, 10.3); w is the width or diameter and h the depth, both in meters. For the round conductor, Q = −1.3 is the ln 2 − 2 of Dwight's formula as given in IEEE Std 142.
IEEE 80Sverak equation
Rg = ρ · [1/LT + 1/√(20A) · (1 + 1 / (1 + h · √(20/A)))]LT is the total buried length (conductors plus rods), A the grid area and h its depth, valid from 0.25 to 2.5 m. A rectangular grid always has its perimeter conductors: each direction has ⌈side/D⌉ + 1 conductors and the actual spacing is side / ⌈side/D⌉, never larger than requested.
IEEE 80ground potential rise
GPR = IG · RIG is the grid current: the part of the fault current 3I0 that the electrode discharges to remote earth after the split factor Sf, not the total fault current. Part of it returns through shield wires and cable sheaths.
IEEE 81Wenner methodIEEE 80uniform soil
ρa = 4πaR / (1 + 2a/√(a² + 4b²) − a/√(a² + b²))It reduces to ρa = 2πaR when b is small compared with a. For a uniform soil model, IEEE 80 suggests taking the average of the apparent resistivities or half the sum of the maximum and minimum. The tool raises an alert when the maximum exceeds 1.5 times the minimum: it is our own criterion to suggest a layered model, not a limit from a standard.
Limits of the calculation
- These are uniform-soil estimates, not a design. Real soil is almost never uniform: moisture, layers and season change the result.
- A substation grid is designed with a two or more layer model and with the IEEE 80 step and touch voltages, which this tool does not calculate.
- The formulas do not account for the conductor joining the rods or the interaction between the grid and other nearby electrodes.
- They do not check compliance with the local code.
- The actual resistance is verified with a ground resistance test after construction.
Frequently asked questions
How is the ground resistance of a rod calculated?
With Dwight's formula, as given in BS 7430: R = ρ / (2πL) · (ln(8L/d) − 1), where ρ is the soil resistivity, L the buried length and d the rod diameter. A 2.4 m, 5/8 inch rod in 100 Ω·m soil gives about 40 Ω. Length matters far more than diameter.
How many ground rods do I need?
It depends on the resistivity and on the resistance the design requires. Several rods in parallel lower the resistance, but not in proportion to their number, because they interact; BS 7430 corrects that effect with a factor for each arrangement, provided the spacing is at least equal to the rod length. In high-resistivity soil a long horizontal conductor or a grid is usually the better option.
How is soil resistivity calculated with the Wenner method?
Four electrodes are driven in line with equal spacing a, current is injected through the outer pair and the voltage is measured between the inner pair. If the electrodes are shallow compared with the spacing, the apparent resistivity is ρ = 2π · a · R (IEEE 81). Measuring at several spacings shows how it changes with depth; if it changes a lot, the soil is not uniform and a layered model is needed.