P-Q capability test

Enter the points measured in the test, with the target and measured reactive power, the voltage and the time held, and the data of the measurement chain. The tool draws the plant with the test signals, compares each point with the declared and the reference curves, and checks the coverage, the 90 % of Pn rule and the content of the report.

CNO Agreement 2153 of 2026§ art. 4 to 6, Annex 1test on the STN and STRCNO Agreement 1910 of 2024§ art. 4 to 6, Annex 1test on the SDLCREG 060 of 2019§ art. 14 breference curve

Example cases
P-Q capability test

Only the basic data; the rest is taken with typical values.

ALearn

E1Plant and connection
MW

Net effective capacity, with two decimals; for self-generation, the declared maximum power.

MW

STN and STR only. The alternatives at the HV terminals of the step-up transformer use the same P-Q curve.

E2Measured points
Test points

One row per point: P, target Q (+ delivery, − absorption), corrected average measured Q, voltage, time held and what limited it.

RowPMWQ targetMvarQ meas.MvarVp.u.tsLimitRemove

Row number of the point shown on the plant and highlighted on the P-Q plane.

E3Measurement chain
A
kV
%
%
%
%
E4Coverage, night check and report

Records with delivered and absorbed reactive power above 90 % of Pn, held one minute or more.

Inverter capability curve and preliminary model showing the pending points above 90 %.

Mvar

STN and STR only. Largest |Q| recorded with the plant connected and no primary resource. Leave it empty if you do not have it.

years
s
%
% Pn
% Pn

Use a decimal point. The calculation runs in your browser and updates as you type.

Test result

—

Points that pass

—

Maximum power reached

—

Absolute error of the reactive power

—

Reference curve

—

Auditor's report

—

Plant, controller and point of connection during the test
The plant during the test: the controller drives the reactive power to the set point and the recorder takes P, Q and V at the point of connection. Next to the point of connection, the values of the chosen point; the controller frame turns green if it passes and red if it fails.
Measured points against the declared and reference curves
  • Declared
  • Band
  • CREG 060 (art. 14 b)
Reactive power delivery on the right and absorption on the left, in multiples of Pn. Each measured point carries its error rectangle: green if it passes, red if it fails, grey if it is pending. The ring marks the point shown on the drawing.

Point-by-point evaluation

#RegionPQ targetQ meas. ± errorBand fromCREG 060VtResult

Test report checklist

ContentStatusSource

What it is for

Before entering operation, a solar or wind plant shows the CND, or the grid operator on the SDL, that it delivers and absorbs the reactive power of the curve it declared. An auditor reviews the test and its report. This tool runs that review with your data: each measured point against the declared value and the reference curve, the error of the measurement chain, the coverage of the test and what the report must contain.

Use it to plan the points before the test, to read the results on the day and to review the auditor's report before sending it.

How it is calculated

CNO Agreement 2153 of 2026§ Annex 3 §5measurement error

Measurement chain error

Emr = √(ECT² + EVT² + ER²) · Ema = √3 · Emr · Iprim · Vprim

Each error is taken equal to the accuracy class of the device; the recorder's as the sum of its reading error and its range error, the most conservative reading. Ema is the absolute error of the reactive power in Mvar.

CNO Agreement 2153 of 2026§ art. 6, Annex 1 §5tolerances

When a point passes

|Qmeas| + Ema ≥ |Qtarget| · (1 − 1 %)

The measurement rectangle, the average reactive power plus or minus the error, must touch the 1 % band of the declared curve. If it falls short, the point still passes when it goes beyond the reference curve, and the curve to declare is adjusted. A point the grid did not let the plant reach, once the set points are exhausted, is declared compliant. Each point is held at least one minute.

CREG 060 of 2019§ art. 14 breference curve

Reference curve on the STN and STR

Qref(P) through (0.1; 0.1), (0.2; 0.33), (0.95; 0.33) and (1.0; 0.228) in multiples of Pn

Below 10 % of Pn there is no reactive power requirement, but the plant must not exceed 5 % of Pn. That is why the minimum-output point, when it is below 10 %, is tested with a 10 % of Pn set point and must stay limited to 5 %.

CNO Agreement 2153 of 2026§ art. 5 and 6coverage

Coverage and the 90 % rule

3 + 3 points · Pmax ≥ 0.9 · Pn

At least three points per region, at the minimum stable output, at an intermediate value and at rated power. If the plant reaches 90 % of Pn but not Pn, the test succeeds with operation records above 90 %, or with the manufacturer data sheet and the model; in that case there are 12 months to send the pending points.

Limits of the calculation

  • On the SDL the reference curve is the one of CNO Agreement 1531 of 2022, which is not in the tool: points that fall short of the declared value stay pending. The CREG 060 curve is drawn for comparison only.
  • The alternative of a P-Q curve adjusted with the Q-V curve of CNO Agreement 1546 is not calculated: it stays pending.
  • The measured reactive power must already be averaged and corrected to the test voltage with the declared Q(V) family of curves. The tool does not have that family; it only warns when the voltage leaves 0.9 to 1.1 p.u.
  • The agreements do not say what the 1 % band is taken from. It is taken from the reactive power of each declared point, the narrowest choice; change it in Advanced mode. A measured reactive power beyond the declared value counts as reaching it.
  • The level of each point (minimum stable output, intermediate or rated) is set by its power: rated from 90 % of Pn, and minimum up to 5 % of Pn above the minimum stable output.
  • CREG 101 104 of 2026 (art. 8) rewrote numeral 7.7 of the Código de Operación: before commercial operation, STN and STR plants send the CND the results of the capability curve test of literal b of numeral 5.7, the same CREG 060 curve the tool uses.
  • On the SDL, CREG 101 104 of 2026 modified numeral 11.3.7 of CREG 070: the capability curve test is run when the CNO agreement identifies it as necessary, the results go to the CND and the OR, and an independent third party runs it and delivers a detailed report. CNO Agreement 1910 predates that change.
  • The tool warns when a point's voltage leaves the normal range: 0.9 to 1.1 p.u. (1.05 p.u. at 500 kV) per numeral 5.1 of the Código de Operación for 110 to 500 kV buses, and numeral 6.2.1.1 of CREG 070 for the SDL and STR buses below 110 kV. CNO Agreement 1214 of 2019, which sets the range for reporting the curve, is not in the tool.
  • Resolutions CREG 229 of 2021 and 101 098 of 2026 are not in the tool: self-generators without surplus export and embedded generators have their own rules, not checked here.
  • The target Q of each row is compared at the measured P, as if it were the planned P. If the plant settled at another P, enter the declared Q interpolated at that P.
  • As of 10 November 2026 CNO Agreement 1910 applies; check whether the CNO updated it after CREG 101 104.

Frequently asked questions

How many points must be tested on the capability curve?

At least three delivering reactive power and three absorbing it, at the minimum stable output, at an intermediate value and at rated power. If the curve has more vertices, testing all of them is recommended. Each point is held at least one minute in voltage control and then in reactive power and power factor control.

What if the plant does not reach rated power on the test day?

If it reaches 90 % of Pn or more, the test can succeed: with operation records showing the reactive power above 90 %, or with the manufacturer data sheet and the plant model; in the latter case there are 12 months to send the missing points. Below 90 % it is not successful, and the agent has six attempts.

How is a measured point judged to pass?

The held reactive power is averaged, corrected to the test voltage, and the absolute error of the measurement chain (CT, VT and recorder) is added and subtracted. If that rectangle touches the 1 % band of the declared curve, the point passes. It also passes when it lies between the declared value and the reference curve, and then the curve to declare is adjusted.