Function 87B: bus differential

Low-impedance bus differential: sum of currents, stabilization, check zone, CT saturation and test plan with a test set.

Siemens SIPROTEC 5 7SS85§ 6.2busbar differentialSiemens SIPROTEC 5 7SS85§ 9.4characteristic testIEEE C37.2§ 2008function numbers

Example cases
Function 87B: bus differential

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
I/InObj
I/InObj
E2Settings, part two
I/InObj
I/InObj
E3Simulation
I/InObj

Positive toward the bus.

°
I/InObj
°
I/InObj
°

180° = the current leaves the bus through this feeder.

%
E4Installation and test set
A
A
A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
mA
%
ms
ms
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Restraint ratio

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 87B protects the bus with Kirchhoff's current law: what enters the bus through all the feeders has to leave. If the sum is not zero, the current is going down a path it should not, that is, through a fault on the bus.

A bus fault takes out of service every feeder connected, so the protection requires two measurements: that of the bus section and that of the check zone, which sums all the feeders without looking at the disconnectors.

How it operates

  • The differential current is the signed sum of the feeder currents; the restraint current is the sum of their magnitudes. The relay trips when the differential exceeds the threshold and k times the restraint.
  • In a large external fault the CT of the faulted feeder can saturate and create a false differential: factor k covers it as long as the saturation is not extreme.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

All the feeders of the test with the same CT ratio. The plan raises the current of a single feeder until the trip, which must match the threshold, and measures the time at double.

For the slope it injects two feeders at 180°: it keeps the first fixed and lowers the second until it trips. At the boundary I1·(1 − k) = I2·(1 + k). Disable the differential current supervision during the test.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • A single bus section: the check zone sees the same feeders. Buses with a coupler need the disconnector replica.
  • The restraint is taken without the smoothing or the saturation detection of the real relay.
  • The trip time is the approximate one from the manual: estimate.

Frequently asked questions

What is the check zone for?

So that an error in the disconnector image does not trip a healthy bus. The check zone sums all the feeders of the substation, no matter which bus they are connected to, and its trip is a condition for the section trip.

How is factor k tested?

With two feeders at 180°: I1 is fixed and I2 is lowered until the trip. With k = 0.65 the trip arrives when I1 is 4.71 times I2.

How do I choose the threshold?

Above 1.3 times the highest load current of a feeder, so that an open CT does not trip, and below 0.8 times the lowest fault current on the bus.