Home / Tools / Function 87B bus differential
Function 87B: bus differential
Low-impedance bus differential: sum of currents, stabilization, check zone, CT saturation and test plan with a test set.
Siemens SIPROTEC 5 7SS85§ 6.2busbar differentialSiemens SIPROTEC 5 7SS85§ 9.4characteristic testIEEE C37.2§ 2008function numbers
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 87B protects the bus with Kirchhoff's current law: what enters the bus through all the feeders has to leave. If the sum is not zero, the current is going down a path it should not, that is, through a fault on the bus.
A bus fault takes out of service every feeder connected, so the protection requires two measurements: that of the bus section and that of the check zone, which sums all the feeders without looking at the disconnectors.
How it operates
- The differential current is the signed sum of the feeder currents; the restraint current is the sum of their magnitudes. The relay trips when the differential exceeds the threshold and k times the restraint.
- In a large external fault the CT of the faulted feeder can saturate and create a false differential: factor k covers it as long as the saturation is not extreme.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
All the feeders of the test with the same CT ratio. The plan raises the current of a single feeder until the trip, which must match the threshold, and measures the time at double.
For the slope it injects two feeders at 180°: it keeps the first fixed and lowers the second until it trips. At the boundary I1·(1 − k) = I2·(1 + k). Disable the differential current supervision during the test.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- A single bus section: the check zone sees the same feeders. Buses with a coupler need the disconnector replica.
- The restraint is taken without the smoothing or the saturation detection of the real relay.
- The trip time is the approximate one from the manual: estimate.
Frequently asked questions
What is the check zone for?
So that an error in the disconnector image does not trip a healthy bus. The check zone sums all the feeders of the substation, no matter which bus they are connected to, and its trip is a condition for the section trip.
How is factor k tested?
With two feeders at 180°: I1 is fixed and I2 is lowered until the trip. With k = 0.65 the trip arrives when I1 is 4.71 times I2.
How do I choose the threshold?
Above 1.3 times the highest load current of a feeder, so that an open CT does not trip, and below 0.8 times the lowest fault current on the bus.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
