Transformer excitation current

Enter the test voltage and the current of each phase at each tap: the tool draws the UST connection for the vector group, compares the two higher currents with the FIST 3-31 criterion, and checks the centre-leg pattern and the comparison with the previous test.

USBR FIST 3-31:2003§ 8.3rule of the two higher currentsMegger ZM-AH02E:2010§ Table 3.3UST connection

Example cases
Transformer excitation current

Only the basic data; the rest is taken with typical values.

ALearn

E0Equipment and test
E1Transformer and test
kV
kV

The same at every tap and phase. No more than the winding voltage.

E2Currents measured per tap
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
mA
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
E3Connection in the drawing

In "I place them" choose the terminal of each lead: the tool tells you whether it is right.

E4Previous or factory test

Taken at the same test voltage.

mA
mA
mA

Use a decimal point. The calculation runs in your browser and updates as you type.

Difference of the two higher currents

—

Pattern at the drawn tap

—

Test set connection

—

Change against the reference

—

Test set connection on the equipment
Hover over a part to see its name. Yellow: what the test set energizes; white: what it measures; red: a lead connected wrongly. Change the phase, the tap or the connection mode in the data.
Excitation current per tap and phase
  • Phase A
  • Phase B
  • Phase C
Each group of bars is one tap. Phase B, on the centre leg, is usually the lowest.

Test planPro

Results sheetPro

Step-by-step calculation

What it measures

The excitation current is the current an HV winding draws with the other winding open. It is the current that magnetizes the core. Shorted turns, a poor tap changer contact, shorted core laminations or a loose connection raise it.

One phase is measured at a time, at each tap, at rated frequency and with a voltage of up to about 10 kV. The test set gives the current in milliamperes and, if it can, the losses in watts.

How it is connected

The measurement is made in UST: the test set high-voltage lead goes to one end of the HV winding and the red measuring lead to the other. The test set counts only the current returning through the red lead. The tank and the test set chassis go to the substation ground.

On a wye with neutral each line terminal is measured against H0, with the HV neutral disconnected from ground. On a delta each winding is measured between its two terminals and the third terminal is grounded. The LV side is left floating, except its wye neutral, which stays grounded as in service.

On an HV wye without a neutral bushing there is no access to a single winding: the tool draws the measurement between two line terminals, with the third one floating. Follow your test set manual for that connection.

Corrections

The excitation current is not corrected for temperature. Nor is it proportional to voltage: only readings taken at the same voltage are compared. That is why the tool asks for a single test voltage for every tap and phase.

The test goes before any DC test. The residual magnetism left by the winding resistance test raises the current and changes the pattern between phases.

How to interpret it

USBR FIST 3-31 compares the two higher currents: less than 10 % difference below 50 mA and less than 5 % from 50 mA. The tool uses the higher of the two to pick the limit and does not accept a difference equal to the limit.

On a three-legged core the normal pattern is high, low, high: the centre-leg phase needs less current because its magnetic path is shorter. An outer phase lower than the centre one, or a phase that rises at every tap, is checked with the ratio and winding resistance tests.

Against the previous or factory test, at the same voltage, the tool flags a change of 10 % or more for review. This is a Tiza convention: FIST 3-31 asks for the comparison but gives no number.

Tool limits

  • Only two-winding transformers in wye or delta; zigzag windings and autotransformers are out of scope.
  • The high, low, high pattern is judged only on three-legged cores. On five-legged, shell-type cores or banks of single-phase units the tool shows the pattern without judging it.
  • On a wye without a neutral bushing the tool draws the measurement between two line terminals, with two windings in series. Make that connection as your test set manual says.

Frequently asked questions

What difference is accepted between the phase excitation currents?

The USBR FIST 3-31 manual compares only the two higher currents. Below 50 mA their difference should be under 10 %; from 50 mA, under 5 %. The third phase, on the centre leg, is usually lower.

Why is the excitation current measured before the winding resistance?

Because the direct current of the winding resistance test leaves residual magnetism in the core, and with it the excitation current reads higher and uneven. If a DC test has already been made, the core must be demagnetized first.

What is done with the third terminal of a delta winding?

It is grounded. The second winding that reaches the energized terminal then takes its current to ground without passing through the measurement, and the third is left with no voltage: the test set measures a single winding.