Harmonic emission limits of an MV or HV user

Type the bus data, the total capacity and the agreed power of the user: the tool shares the planning levels, works out the voltage and current limit of each order and compares them with the currents you expect from your plant.

IEC TR 61000-3-6:2008§ stages 1 to 3allocation (estimate)IEC 61000-2-12:2003§ 4.3compatibility at MVIEEE Std 519-2022§ 5.3contrast

Example cases
Harmonic emission limits of an MV or HV user

Only the basic data; the rest is taken with typical values.

ALearn

E1Network and user
kV
MVA
MVA

What shares the planning level, for example the rating of the transformer that feeds the bus.

MVA
E2Planning levels
Planning level of the bus

One row per order: the level set by the network operator, in % of the fundamental.

RowOrderL%Remove

Level of the upstream system

One row per order: the distortion coming from the upper level, in %. Empty: zero.

RowOrderL%Remove

E3User's installation
Expected harmonic currents

One row per order: the current the plant will inject, measured or from your study.

RowOrderIARemove

E4Method coefficients
MVA
%

Use a decimal point. The calculation runs in your browser and updates as you type.

Stage of the method

—

Voltage limit of the chosen order

—

Current limit of the chosen order

—

Most loaded order

—

Network, user and current limits
Top: the network with the bus where the user is evaluated and the chain of the chosen order. Bottom: the expected current of each order against the allocated limit and the IEEE 519 one.
Planning level, global contribution and share of the user
  • Planning
  • Global contribution
  • User's limit
Each order shows the planning level, what is left after the upstream share and the part of the user from S_i/S_t and α.
Planning against compatibility at MV
  • Planning
  • Compatibility IEC 61000-2-12
At medium voltage the planning level must stay below the IEC 61000-2-12 compatibility level.

Calculation per order

hαL %G %E_U %Z_h ΩE_I AI AIEEE 519 AStatus

What it is for

When a plant with drives, furnaces or rectifiers asks to connect at medium or high voltage, the network operator gives it harmonic emission limits. This tool shares the planning levels of the bus among the users and gives the voltage and current limit of each order.

It helps to prepare the connection request, check whether the plant needs filters and understand why two methods, IEC and IEEE, give different results.

How it is calculated

IEC TR 61000-3-6:2008§ stage 2estimate

Global contribution and share of the user

Gh = (Lhα − (T·Lh,up)α)1/α · EU,h,i = Gh·(Si/St)1/α

α is 1 below the 5th, 1.4 from the 5th to the 10th and 2 above. With LV load and coincidence factors, the share uses SMV = St − SLV, FML and FMV.

IEC TR 61000-3-6:2008§ stage 2estimate

From voltage to current

Zsc = U²/Ssc · Zh = kZ·h·Zsc · EI,h,i = EU,h,i·(U/√3)/Zh

The network is taken as inductive. With capacitor banks nearby the real impedance can be much higher at some orders: use the kZ factor from a harmonic study.

IEEE Std 519-2022§ 5.3contrast

The same point with IEEE 519

IL = Si/(√3·U) · Isc/IL → row of Table 2 · limit = % × IL

Limits of the calculation

  • The whole method is an estimate: we do not hold a licensed copy of IEC TR 61000-3-6 and we implement it from open publications that describe it.
  • The indicative planning levels are those published in KIEE 2007, earlier than the 2008 edition of the standard: an estimate to be confirmed. Above order 25 we give no typical value. Use your network operator's.
  • Stage 1 only compares S_i/S_sc; the weighted distorting power is not calculated.
  • The harmonic impedance is inductive and has no resonances; the IEEE 519 contrast is only made up to 69 kV.

Frequently asked questions

What is a planning level?

It is the internal quality objective that the network operator sets for the harmonic voltage of each order. It sits below the compatibility level to leave a margin, and it is the basis for sharing emission limits among the users.

Why does the limit depend on S_i/S_t?

Because the method shares the network's capacity to absorb harmonics in proportion to each user's agreed power against the total capacity that shares that level. The exponent α accounts for the harmonics of many users not adding in phase.

How does it differ from IEEE 519?

IEEE 519 gives fixed current tables by the Isc/IL ratio. The IEC method shares a planning level with formulas that use the user's power, the total capacity and the harmonic impedance of the point, so the two results need not agree.