Home / Tools / Function 86 lockout
Function 86: lockout relay
Lockout relay 86: latched trip, local or remote reset, close and 79 blocking, the relay inside and a test plan with the test set.
IEEE C37.2§ 3.1.86function numbersSiemens SIPROTEC 5§ 3.1.9latched outputsSiemens SIPROTEC 5§ 5.5.5.2trip command
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 86 is the lockout relay: when an important protection trips (the differential of a transformer, breaker failure, the Buchholz), the 86 opens the breakers and stays operated. While it stays operated the equipment cannot be energized again.
In numerical relays the 86 is usually a latched output: it stays active until someone resets it with the front key, a binary input or a remote command, as each utility allows.
How it operates
- Any trip that reaches the 86 operates it and leaves it latched, even if the trip goes away.
- The reset only works if the path is allowed and the cause is gone: while the protection keeps tripping, the 86 sets again.
- With the 86 operated, one of its contacts opens the close circuit and a signal blocks the reclosing, so nobody energizes the equipment before the fault is checked.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The BOUT3 output of the test set energizes the trip input to the 86 and its binary input reads BO1. The operating time is measured and it is checked that the output does not reset when the trip is removed.
Then the reset paths are tested: with the trip still present it must not reset; without the trip, each allowed path resets and each path that is not allowed does not. Finally the close and 79 blocks are checked.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The time between the input and the output is not declared in the manual: the expected value is the sum of the input and output times, plus an editable margin, and it is marked as an estimate.
- That the reset does not act with the trip present is the behaviour of this model; check the one of your relay.
- An electromechanical 86 with an electrical reset coil is not simulated.
Frequently asked questions
What is the difference between the 86 and the 94?
The 94 gives the trip command and resets by itself once the fault is cleared. The 86 stays operated and does not allow closing until someone resets it.
Why does the 86 not reset if the trip is still present?
Because the cause is still there: the memory sets again as soon as the reset is released. The trip has to be removed first, for example by resetting the Buchholz alarm.
Can the 86 be reset remotely?
The relay usually allows it through a binary input or the station protocol, but many utilities forbid it so that the equipment is checked on site.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws