Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 46 protects a machine from negative-sequence current, which appears with unbalanced loads, an open phase or asymmetrical faults. That current induces double-frequency currents in the rotor and heats it.
Each machine withstands a continuous I2 and an unbalance energy expressed by the factor K; both are given by its manufacturer.
How it operates
- Above the permanent I2 the function integrates (I2/In)² over time and trips when the integral reaches K. With a constant I2 the time is K/(I2/In)².
- Above 10 times the permanent I2 the time stops decreasing, so that it does not trip before the protection for the external fault.
- The thermal image cools in the set time; an unbalance during cooling trips sooner.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The test set injects three equal currents in A-C-B sequence: that set is purely negative sequence, so I2 equals the current of each phase.
Before each time point, reset the relay thermal memory; otherwise the measured time is shorter.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The tolerances are those of the cited manual; enter those of your relay.
- The I2 of a specific fault is not calculated: enter it from your study.
- Memory is simulated as a percentage of K at the start of the event.
Frequently asked questions
What does the factor K mean?
The seconds the machine withstands with a negative-sequence current equal to its rated current. With K = 10 s and an I2 of 30 % of rated, the time is 10/0.3² = 111 s.
Why inject in A-C-B sequence?
Because three equal currents with reversed phase order have no positive or zero sequence: everything is negative sequence, and the I2 the relay measures is that of each phase.
Why does the memory have to be reset?
Because the function remembers the earlier heating. If it is not reset, the second test point starts with accumulated heat and trips before the expected time.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
