Function 46: negative sequence

Unbalanced load of a machine: continuous I2, K factor, alarm and trip with tolerance, the relay inside and an injection test plan.

Siemens SIPROTEC 5 7UT§ 6.16unbalanced loadIEEE C37.2§ 2008function numbers

Example cases
Function 46: negative sequence

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
% of machine In

The one the machine withstands without a time limit; it is given by its manufacturer.

s

Seconds the machine withstands with an I2 equal to its rated current.

s
s
A
E3Simulation
% of machine In
%
E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
% of In
%
ms
%
ms
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Alarm

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 46 protects a machine from negative-sequence current, which appears with unbalanced loads, an open phase or asymmetrical faults. That current induces double-frequency currents in the rotor and heats it.

Each machine withstands a continuous I2 and an unbalance energy expressed by the factor K; both are given by its manufacturer.

How it operates

  • Above the permanent I2 the function integrates (I2/In)² over time and trips when the integral reaches K. With a constant I2 the time is K/(I2/In)².
  • Above 10 times the permanent I2 the time stops decreasing, so that it does not trip before the protection for the external fault.
  • The thermal image cools in the set time; an unbalance during cooling trips sooner.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The test set injects three equal currents in A-C-B sequence: that set is purely negative sequence, so I2 equals the current of each phase.

Before each time point, reset the relay thermal memory; otherwise the measured time is shorter.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The tolerances are those of the cited manual; enter those of your relay.
  • The I2 of a specific fault is not calculated: enter it from your study.
  • Memory is simulated as a percentage of K at the start of the event.

Frequently asked questions

What does the factor K mean?

The seconds the machine withstands with a negative-sequence current equal to its rated current. With K = 10 s and an I2 of 30 % of rated, the time is 10/0.3² = 111 s.

Why inject in A-C-B sequence?

Because three equal currents with reversed phase order have no positive or zero sequence: everything is negative sequence, and the I2 the relay measures is that of each phase.

Why does the memory have to be reset?

Because the function remembers the earlier heating. If it is not reset, the second test point starts with accumulated heat and trips before the expected time.