CND supervision indicators

Enter the points your plant sends to the CND with their events of the month and, if you have them, the samples received. The tool calculates the supervision percentage, the reliability of each point and of the plant, the sending period and the report deadlines, and lets you simulate a link outage or a frozen measurement on the plant drawing.

CNO 1411 de 2021§ art. 2points to superviseCNO 1411 de 2021§ art. 3 y 4supervision and reliabilityCNO 1411 de 2021§ art. 5report deadlinesCREG 060 de 2019§ Anexo 3.3.1.1data and sending periodsCREG 060 de 2019§ Anexo 3.3.6meteorological variablesCREG 070 de 1998§ Anexo 11.3.7, 12.3.5supervision of SDL plantsCREG 101 104 de 2026§ art. 8post-operation follow-up, 10 samples per second

Example cases
CND supervision indicators

Only the basic data; the rest is taken with typical values.

ALearn

E1Plant and evaluated month

Sets the required points and sending period: 4 s in chapter 11, up to 5 min in chapter 12.

kV
E2Simulate an event

It is added to the events of the points table.

min
E3Points sent to the CND
Points and events of the month

One row per point. Events: duration in minutes of each one, separated by spaces. Period and samples are optional; without a period, the CREG 060 maximum is used.

RowVariableSupervisedEventsminPeriodsSamples receivedGood qualityFrom dayRemove

E4Previous months
Indicators of previous months

One row per month of the CND final report: YYYY-MM, % supervision and % reliability.

RowMonthSupervision%Reliability%Remove

%

The agreement excludes them when they are isolated. Choose No if they repeat: that is the conservative reading.

By default, reliability is calculated over the supervised points.

Colombian holidays are already excluded (Ley 51 de 1983). Enter other days here, separated by spaces.

Use a decimal point. The calculation runs in your browser and updates as you type.

Scope of the supervision

—

Supervision percentage

—

Supervision reliability

—

Point with the lowest reliability

—

Availability of the meteorological variables

—

Samples with good quality

—

Plant telemetry to the CND
Top: the plant and the telemetry link to the CND, lit in yellow when data arrives. Bottom: each point with its reliability for the month: green with no unavailability, yellow with events, red when not supervised. A yellow border marks the points hit by the simulated event.
Reliability of each point
  • Point reliability
  • Target
Each bar is a point: its length is the share of the month in which it reached the CND correctly. The scale starts near the worst supervised point so the differences show.
Supervision and reliability month by month
  • Reliability
  • Supervision
  • Target
The previous months are the ones you entered; the last point is the evaluated month with the data of the table.

Step-by-step calculation

Result per point

PointGroupSupervisedUnavailableReliabilityGood samplesPeriod

What it is for

Every month the CND publishes a report on the supervision of the SIN assets: which points reach its SCADA and for how long they arrive correctly. A solar PV or wind plant on the STN or the STR appears in that report with its active and reactive power, voltage, current and the positions of its switching devices.

This tool runs that calculation with the events your control center logged, before the preliminary report comes out, so you can request adjustments in time. It also checks the sending periods and the meteorological variables CREG 060 requires, and lets you simulate a link outage to see how much margin you have.

How it is calculated

CNO 1411 de 2021§ art. 3, art. 4 a, bsupervision percentage

Supervision percentage

%S = Nsupervised / Npoints · 100

A point is supervised when it is exchanged with the CND by a means the CND accepted: it counts 100%; otherwise 0%. Points the regulation requires that are missing from the table count as not supervised. The percentage is defined in article 3 and calculated per article 4.

CNO 1411 de 2021§ art. 4 c, d; art. 6 areliability of a point

Reliability of a point

Ci = (Ti − Tunav,i) / Ti · 100, Tunav,i = Σ events ≥ 60 s

T<sub>i</sub> is the window of the point in seconds: the whole month, or from its commercial operation date (FPO) to the end of the month if it entered later. The events are a measurement that is not refreshed, has an inverted sign or a wrong value, and for states, indeterminate, not refreshed, removed by the CND or manual. Those shorter than one minute do not count when they are isolated.

CNO 1411 de 2021§ art. 4 e, fplant reliability and target

Plant reliability

Cplant = Σ (Ti − Tunav,i) / Σ Ti · 100, Tunav,max = T · (100 − target) / 100

The available times of the supervised points are added and divided by the sum of their windows; with equal windows it is the mean of the points. In Advanced mode you can count unsupervised points as 0% (conservative reading). The CNO sets the target every year in a separate agreement; if you enter it, the tool gives the maximum unavailability of a point.

CREG 060 de 2019§ Anexo 3.3.1.1, 3.3.6sending periods

Period and samples

Nexp = ⌊T / period⌋, availability = Nrec / Nexp, quality = Ngood / Nrec

Power, voltage, current, states and set points every 4 s or less; maximum instantaneous capacity every 5 min or less; meteorological variables every 10 min or less. The sample count is our own follow-up indicator, not one of the agreement.

CNO 1411 de 2021§ art. 5report deadlines

Deadlines of the monthly report

In the month after the evaluated one: business day 3, preliminary report of the CND; business day 8, last day for the agent to request adjustments with its justification; business day 15, answer of the CND; business day 16, final report.

Limits of the calculation

  • Pending: the CNO sets the yearly target of the reliability indicator in an agreement the tool does not have. Without a target, the reliability is shown without a verdict; enter the one in force in Advanced mode.
  • Pending: the CNO protocol for meteorological variables (measurement, storage, resolution and reporting) is not in the tool. Their availability is calculated with the same time criterion as Agreement 1411, by analogy.
  • The formulas of Agreement 1411 are images that were not read. They are computed from its definitions: the supervision percentage as the share of supervised points and the reliability as the time the point arrives correctly, averaged over the points.
  • Assumption: reliability is calculated over the supervised points. In Advanced mode you can count unsupervised points as 0%, because they never reach the CND SCADA (conservative reading).
  • The one-month calculation window is our inference: the agreement publishes the report every month, but the window is in a formula that was not read.
  • Simultaneous events of the same point are added: if they overlap, enter the duration of their union.
  • The CND report also counts the bay points of the plant substation (P, Q, V, I), the on-load tap changer position and the voltage of each bus segment (Agreement 1411, art. 2, num. 1). The tool models only the generator point.
  • On the SDL the points and periods are those of CREG 070: up to 4 s in chapter 11 (numeral 11.3.1) and up to 5 min in chapter 12 (numeral 12.3.1), plus the plant connection-state signal, shown as an informative point. SDL meteorological variables are not checked for period.
  • The states and set points of the controls and the maximum capacity (CREG 060, 3.3.1.1 c to i) are not in the agreement's list of points; they are calculated separately. The CND may request more points, for example those of each bay.
  • SDL plant: while the grid operator (OR) cannot supervise it, the CND supervises it directly and follows up the quality and availability of its data (CREG 070 of 1998, Annex, numerals 11.3.7 and 12.3.5, as modified by articles 13 and 17 of CREG 101 104 of 2026). Those texts do not define a methodology or target for the SDL: the calculation uses the Agreement 1411 criterion as a reference.
  • Post-operation follow-up: the reports of electrical variables the agent delivers to the CND for that follow-up must have at least 10 samples per second, or more if a CNO agreement sets it (Código de Operación, numeral 7.7, as modified by article 8 of CREG 101 104 of 2026). That is separate from real-time telemetry: the tool does not calculate it.
  • A point that enters commercial operation mid-month is calculated from that day («From day» column, art. 6 a). Business days exclude Colombian holidays per Ley 51 de 1983, whose text is not in the tool; enter other non-business days if there are any.

Frequently asked questions

What is the supervision percentage before the CND?

It is the share of the points the plant must send that is actually configured on the link to the CND. Each point counts 100% if supervised and 0% if not. For a solar PV or wind plant the report points are active and reactive power, voltage, current and the positions of the breaker, disconnectors and earthing switches.

How is the reliability of a measurement calculated?

It is the share of the month in which the point reaches the CND SCADA correctly. The events that affect it are subtracted: value not refreshed, inverted sign, wrong value, indeterminate or manual state. Events shorter than one minute do not count when they are isolated. The CNO sets the target every year in another agreement.

How often must a solar plant send its measurements to the CND?

Power, voltage, current, control states and set points every 4 seconds or less; the maximum instantaneous possible capacity every 5 minutes or less; and the meteorological variables every 10 minutes or less, per CREG 060 of 2019. The time stamp may not be off by more than ±200 ms (CREG 070, numeral 11.3.1; the CREG 060 text reads «200 m»).