Home / Tools / Supervision before the CND
CND supervision indicators
Enter the points your plant sends to the CND with their events of the month and, if you have them, the samples received. The tool calculates the supervision percentage, the reliability of each point and of the plant, the sending period and the report deadlines, and lets you simulate a link outage or a frozen measurement on the plant drawing.
CNO 1411 de 2021§ art. 2points to superviseCNO 1411 de 2021§ art. 3 y 4supervision and reliabilityCNO 1411 de 2021§ art. 5report deadlinesCREG 060 de 2019§ Anexo 3.3.1.1data and sending periodsCREG 060 de 2019§ Anexo 3.3.6meteorological variablesCREG 070 de 1998§ Anexo 11.3.7, 12.3.5supervision of SDL plantsCREG 101 104 de 2026§ art. 8post-operation follow-up, 10 samples per second
Results
—
—
—
—
—
—
Charts
- Point reliability
- Target
- Reliability
- Supervision
- Target
How it was calculated and standards
Step-by-step calculation
Result per point
| Point | Group | Supervised | Unavailable | Reliability | Good samples | Period |
|---|
What it is for
Every month the CND publishes a report on the supervision of the SIN assets: which points reach its SCADA and for how long they arrive correctly. A solar PV or wind plant on the STN or the STR appears in that report with its active and reactive power, voltage, current and the positions of its switching devices.
This tool runs that calculation with the events your control center logged, before the preliminary report comes out, so you can request adjustments in time. It also checks the sending periods and the meteorological variables CREG 060 requires, and lets you simulate a link outage to see how much margin you have.
How it is calculated
CNO 1411 de 2021§ art. 3, art. 4 a, bsupervision percentage
Supervision percentage
%S = Nsupervised / Npoints · 100A point is supervised when it is exchanged with the CND by a means the CND accepted: it counts 100%; otherwise 0%. Points the regulation requires that are missing from the table count as not supervised. The percentage is defined in article 3 and calculated per article 4.
CNO 1411 de 2021§ art. 4 c, d; art. 6 areliability of a point
Reliability of a point
Ci = (Ti − Tunav,i) / Ti · 100, Tunav,i = Σ events ≥ 60 sT<sub>i</sub> is the window of the point in seconds: the whole month, or from its commercial operation date (FPO) to the end of the month if it entered later. The events are a measurement that is not refreshed, has an inverted sign or a wrong value, and for states, indeterminate, not refreshed, removed by the CND or manual. Those shorter than one minute do not count when they are isolated.
CNO 1411 de 2021§ art. 4 e, fplant reliability and target
Plant reliability
Cplant = Σ (Ti − Tunav,i) / Σ Ti · 100, Tunav,max = T · (100 − target) / 100The available times of the supervised points are added and divided by the sum of their windows; with equal windows it is the mean of the points. In Advanced mode you can count unsupervised points as 0% (conservative reading). The CNO sets the target every year in a separate agreement; if you enter it, the tool gives the maximum unavailability of a point.
CREG 060 de 2019§ Anexo 3.3.1.1, 3.3.6sending periods
Period and samples
Nexp = ⌊T / period⌋, availability = Nrec / Nexp, quality = Ngood / NrecPower, voltage, current, states and set points every 4 s or less; maximum instantaneous capacity every 5 min or less; meteorological variables every 10 min or less. The sample count is our own follow-up indicator, not one of the agreement.
CNO 1411 de 2021§ art. 5report deadlines
Deadlines of the monthly report
In the month after the evaluated one: business day 3, preliminary report of the CND; business day 8, last day for the agent to request adjustments with its justification; business day 15, answer of the CND; business day 16, final report.
Limits of the calculation
- Pending: the CNO sets the yearly target of the reliability indicator in an agreement the tool does not have. Without a target, the reliability is shown without a verdict; enter the one in force in Advanced mode.
- Pending: the CNO protocol for meteorological variables (measurement, storage, resolution and reporting) is not in the tool. Their availability is calculated with the same time criterion as Agreement 1411, by analogy.
- The formulas of Agreement 1411 are images that were not read. They are computed from its definitions: the supervision percentage as the share of supervised points and the reliability as the time the point arrives correctly, averaged over the points.
- Assumption: reliability is calculated over the supervised points. In Advanced mode you can count unsupervised points as 0%, because they never reach the CND SCADA (conservative reading).
- The one-month calculation window is our inference: the agreement publishes the report every month, but the window is in a formula that was not read.
- Simultaneous events of the same point are added: if they overlap, enter the duration of their union.
- The CND report also counts the bay points of the plant substation (P, Q, V, I), the on-load tap changer position and the voltage of each bus segment (Agreement 1411, art. 2, num. 1). The tool models only the generator point.
- On the SDL the points and periods are those of CREG 070: up to 4 s in chapter 11 (numeral 11.3.1) and up to 5 min in chapter 12 (numeral 12.3.1), plus the plant connection-state signal, shown as an informative point. SDL meteorological variables are not checked for period.
- The states and set points of the controls and the maximum capacity (CREG 060, 3.3.1.1 c to i) are not in the agreement's list of points; they are calculated separately. The CND may request more points, for example those of each bay.
- SDL plant: while the grid operator (OR) cannot supervise it, the CND supervises it directly and follows up the quality and availability of its data (CREG 070 of 1998, Annex, numerals 11.3.7 and 12.3.5, as modified by articles 13 and 17 of CREG 101 104 of 2026). Those texts do not define a methodology or target for the SDL: the calculation uses the Agreement 1411 criterion as a reference.
- Post-operation follow-up: the reports of electrical variables the agent delivers to the CND for that follow-up must have at least 10 samples per second, or more if a CNO agreement sets it (Código de Operación, numeral 7.7, as modified by article 8 of CREG 101 104 of 2026). That is separate from real-time telemetry: the tool does not calculate it.
- A point that enters commercial operation mid-month is calculated from that day («From day» column, art. 6 a). Business days exclude Colombian holidays per Ley 51 de 1983, whose text is not in the tool; enter other non-business days if there are any.
Frequently asked questions
What is the supervision percentage before the CND?
It is the share of the points the plant must send that is actually configured on the link to the CND. Each point counts 100% if supervised and 0% if not. For a solar PV or wind plant the report points are active and reactive power, voltage, current and the positions of the breaker, disconnectors and earthing switches.
How is the reliability of a measurement calculated?
It is the share of the month in which the point reaches the CND SCADA correctly. The events that affect it are subtracted: value not refreshed, inverted sign, wrong value, indeterminate or manual state. Events shorter than one minute do not count when they are isolated. The CNO sets the target every year in another agreement.
How often must a solar plant send its measurements to the CND?
Power, voltage, current, control states and set points every 4 seconds or less; the maximum instantaneous possible capacity every 5 minutes or less; and the meteorological variables every 10 minutes or less, per CREG 060 of 2019. The time stamp may not be off by more than ±200 ms (CREG 070, numeral 11.3.1; the CREG 060 text reads «200 m»).
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws