Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
When a generator loses synchronism, the angle between its internal voltage and the grid's keeps turning: each turn is a pole slip, with current and torque peaks that damage the shaft and the winding. The differential and the backup protection do not see it.
The 78 watches how the impedance seen by the relay at the terminals moves: in a slip it crosses the R-X diagram from one side to the other, and in a fault it jumps at once.
How it operates
- With two sources of equal voltage the impedance moves along a line through the electrical centre, at half the total reactance between the two sources.
- Two blinders parallel to that line and a mho circle bound the zone. There is a slip if the impedance enters through one blinder, takes longer than the minimum time and leaves through the other inside the mho.
- A stable swing enters and comes back on the same side, and a fault jumps inside at once: neither of them trips.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The test set sets the impedance with three-phase voltages and currents: the plan gives the boundaries of each blinder on the electrical-centre line and the mho reaches on the X axis.
The time is measured with a test-set swing at the simulated slip frequency, from the load angle; two more points check that it does not trip on a stable swing or on a fault jump.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The two sources have the same voltage; with different voltages the locus is a circle and the angles change.
- The reactances are pure: neither the resistance nor the variation of X'd during the swing is modelled.
- The swing is generated with a state file or an angle ramp of the test set; the tool gives the expected time, not the sequence.
Frequently asked questions
What is the electrical centre?
The point of the network where the voltage becomes zero when the two sources are 180° apart. With 12 Ω of X'd, 5 Ω of transformer and 3 Ω of grid, the total reactance is 20 Ω and the centre falls 2 Ω inside the generator.
Why not trip as soon as the impedance enters?
Because a stable swing also enters and then comes back. The 78 waits for it to leave through the opposite side, which confirms the angle went past 180°.
How is a fault told from a slip?
By the time between blinders: in a fault the impedance jumps inside within a cycle; in a 1 Hz slip it takes tens or hundreds of milliseconds to cross.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
