Home / Tools / Function 14 underspeed
Function 14: underspeed at start
Motor speed switch at the start: trip and warning delays, contact sense, the relay inside and a test plan with the injection kit.
IEEE C37.2§ 2008 §3.1.14underspeedIEEE C37.96§ 2000 §5.2.7speed switchSEL-710-5§ Specificationsspeed switch (14)
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 14 confirms that the rotor started turning. A speed switch on the shaft tells the relay when the motor passes a low speed; if no signal arrives when the delay runs out, the rotor is locked and the relay takes the motor out.
It is the answer for high-inertia loads, whose start lasts longer than the locked-rotor time: the current cannot tell a long start from a locked rotor, the rotation can.
How it operates
- The relay recognises the start when the current exceeds the start current with the breaker closed, and starts the timer.
- If input BI3 reports rotation before the delay, nothing happens; if not, it trips. An alarm with a shorter delay can warn first.
- The contact sense is a setting: some switches close when turning and others, the zero-speed ones, open.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The kit simulates the start with a current step and the speed switch with one of its binary outputs on BI3.
The trip is measured without rotation; then check that it does not trip if rotation comes before the delay and that it does if it comes after. Block the 51LR and the 48, which see the same current.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The switch is simulated as a contact that changes once; bounce and sensor failures are not modelled.
- The current that recognises a start has no declared value in our sources.
- The virtual speed switch some relays calculate is not modelled.
Frequently asked questions
Why is a speed switch needed?
Because with a high-inertia load the normal start lasts longer than the locked-rotor time: an overcurrent set to protect the rotor would trip on every start.
How is the delay set?
Longer than the time the rotor takes to pass the switch speed in a healthy start and shorter than the locked-rotor time the motor withstands.
Which number does it carry, 12 or 14?
IEEE C37.2-2008 calls the underspeed device 14; the guide IEEE C37.96-2000 numbers the zero-speed switch 12 in its figure. Use the one on your project drawings.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
