Function 79: automatic reclosing

Automatic reclosing: cycles, dead times, reclaim time and final trip, the relay inside and a test plan with the test set.

IEEE C37.2§ 3.1.79function numbersSiemens SIPROTEC 5§ 6.12automatic reclosingSiemens SIPROTEC 5§ 11.13setting ranges

Example cases
Function 79: automatic reclosing

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings

The cited manual allows up to 8 cycles, each one with its own times.

s

Runs from the moment the 52a shows the breaker open up to the close command.

s
s
s
E2Settings, part two
s

Runs from the close command: if the protection trips before it ends, the cycle was unsuccessful.

s

After a manual close the 79 does not reclose during this time: if the breaker was closed onto a fault, the trip is final.

s

If the trip lasts longer than this, the breaker did not open in time: the 79 blocks.

s

With «Yes», without the breaker ready signal (spring charged, pressure) on BI4 the 79 neither starts nor closes.

E3Simulation
s

From the breaker closing until the protection trips again, if the fault is still there.

s

Example value: breaker opening time plus the time of its auxiliary contacts.

s

Example value: write the one of your breaker.

For example from the 50BF, the 86 or a reclosing off selector switch.

s
E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

A

Above the pickup of the protection that starts the 79 in your relay.

E5Relay tolerances
%
ms
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

End of the sequence

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 79 closes the breaker again after a fault trip, because on overhead lines many faults are arcs that die out when the line is de-energized. If the fault is still there, the protection trips again and the 79 tries the next cycle or leaves the trip as final.

This tool simulates the whole sequence with the relay signals: the trip command, the 52a contact, the close command to the close coil and the inputs that block it.

How it operates

  • Each cycle starts with a trip: when the 52a shows the breaker open, the dead time of that cycle runs and the close command comes out at its end.
  • The reclaim time starts with the close command. If the protection trips before it ends, the cycle was unsuccessful and the next one follows; if no cycles are left, the trip is final.
  • Before starting, the 79 blocks if the breaker was not closed, if it is not ready, if a block input is active or if there was a recent manual close. If the trip lasts too long, it assumes a breaker failure and does not reclose either.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The test set acts as the breaker: its BOUT1 output follows the trip and close commands of the relay and feeds the 52a input. With a permanent fault each dead time is measured from the opening of the 52a to the close command, and it is checked that no other close follows the last cycle.

The reclaim time is tested by applying the fault again a little before and a little after its setting. Then the blocks are checked: BI3 input, manual close, breaker not ready and a trip that lasts too long.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The mode with trip and without action time is simulated, with three-pole tripping only; single-pole reclosing, adaptive dead time and synchronism check are not modelled.
  • The cited manual declares no tolerances for the reclosing times: the band uses the one of the relay timers and is marked as an estimate.
  • The cited manual starts the reclaim time with the close signal in one section and when the close command is over in another: the tool counts it from the command and the test point outside the reclaim time leaves that margin.
  • The breaker and protection times are example values: write yours.

Frequently asked questions

When does the dead time start?

In the cited relay, when the auxiliary contacts show the breaker open. If the 52a is not wired, it starts when the trip command drops.

What happens if the fault returns after the reclaim time?

The relay already counted the reclose as good and returned to rest: the new fault is another event and starts again at cycle 1. If the reclaim time is shorter than the time the protection takes to trip again, a permanent fault is reclosed without end.

Why does it not reclose after a manual close?

Because if the operator closed onto a fault, reclosing only repeats the blow. During the block time after a manual close any trip is final.