Home / Tools / Function 79 reclosing
Function 79: automatic reclosing
Automatic reclosing: cycles, dead times, reclaim time and final trip, the relay inside and a test plan with the test set.
IEEE C37.2§ 3.1.79function numbersSiemens SIPROTEC 5§ 6.12automatic reclosingSiemens SIPROTEC 5§ 11.13setting ranges
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 79 closes the breaker again after a fault trip, because on overhead lines many faults are arcs that die out when the line is de-energized. If the fault is still there, the protection trips again and the 79 tries the next cycle or leaves the trip as final.
This tool simulates the whole sequence with the relay signals: the trip command, the 52a contact, the close command to the close coil and the inputs that block it.
How it operates
- Each cycle starts with a trip: when the 52a shows the breaker open, the dead time of that cycle runs and the close command comes out at its end.
- The reclaim time starts with the close command. If the protection trips before it ends, the cycle was unsuccessful and the next one follows; if no cycles are left, the trip is final.
- Before starting, the 79 blocks if the breaker was not closed, if it is not ready, if a block input is active or if there was a recent manual close. If the trip lasts too long, it assumes a breaker failure and does not reclose either.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The test set acts as the breaker: its BOUT1 output follows the trip and close commands of the relay and feeds the 52a input. With a permanent fault each dead time is measured from the opening of the 52a to the close command, and it is checked that no other close follows the last cycle.
The reclaim time is tested by applying the fault again a little before and a little after its setting. Then the blocks are checked: BI3 input, manual close, breaker not ready and a trip that lasts too long.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The mode with trip and without action time is simulated, with three-pole tripping only; single-pole reclosing, adaptive dead time and synchronism check are not modelled.
- The cited manual declares no tolerances for the reclosing times: the band uses the one of the relay timers and is marked as an estimate.
- The cited manual starts the reclaim time with the close signal in one section and when the close command is over in another: the tool counts it from the command and the test point outside the reclaim time leaves that margin.
- The breaker and protection times are example values: write yours.
Frequently asked questions
When does the dead time start?
In the cited relay, when the auxiliary contacts show the breaker open. If the 52a is not wired, it starts when the trip command drops.
What happens if the fault returns after the reclaim time?
The relay already counted the reclose as good and returned to rest: the new fault is another event and starts again at cycle 1. If the reclaim time is shorter than the time the protection takes to trip again, a permanent fault is reclosed without end.
Why does it not reclose after a manual close?
Because if the operator closed onto a fault, reclosing only repeats the blow. During the block time after a manual close any trip is final.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
