Home / Tools / Function 87L line differential
Function 87L: line differential
Line differential 87L: dual-slope percentage characteristic, charging current and channel, the relay inside and a test plan with the test set.
IEEE C37.2§ 3.1.87function numbersGE Multilin L90§ 10.1.6percentage characteristicGE Multilin L90§ 9.1.3pickup test
Results
—
—
—
—
Charts
- Rating
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 87L compares the currents of both ends of the line. If what enters at one end leaves at the other, the fault is outside; if the sum of both is not zero, there is a fault inside the line and both ends trip without delay.
Each relay sends its currents to the other over a communication channel, almost always fibre. That is why the 87L depends on the channel: if it fails or is delayed too much, it blocks and the backup protection remains.
How it operates
- The differential current is the phasor sum of both currents. The restraint grows with the current of each end: with slope 1 up to the breakpoint and with slope 2 above it, because at high currents the CTs make bigger errors.
- It trips when the square of the differential exceeds twice the square of the pickup plus the restraint of both ends.
- The line draws charging current even without a fault, and that current appears as differential. With the voltages in the relay it can be compensated; without compensation the pickup has to stay well above it.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
With a single test set and the healthy channel, current is injected at the local end only: the relay sees it as differential and also as restraint, and the measured pickup is higher than the setting. It is repeated on the three phases.
In loop-back, with the channel transmitter tied to the receiver, the local current comes back as the remote one and another pickup is measured. External faults are tested with two test sets synchronized by GPS; finally it is checked that the 87L blocks without the channel.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The adaptive term of the cited manual, which grows with noise and saturation, is taken as zero: it is the case of pure sine waves.
- A two-terminal line and a single phase are simulated; the ground differential, an in-zone transformer and the direct transfer trip are not modelled.
- The charging current is split in halves between both ends, 90° ahead.
Frequently asked questions
Why is the pickup measured with local current only higher than the setting?
Because that same current also restrains. With a pickup of 0.20 pu and a slope of 30 %, the relay trips at about 0.31 pu, as the test formula of the cited manual gives.
What does channel asymmetry do?
If the go and return paths take different times, the relay aligns the currents wrongly and the remote one appears rotated. With 3 ms at 60 Hz the rotation is about 32°: a load of 1 pu already shows as 0.56 pu of differential.
When is charging current compensation needed?
On long lines and cables, where the charging current forces a much higher pickup. The cited manual asks for a pickup of at least 2.5 times that current without compensation and 1.5 times with it.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws