Direct or Multiplexed Fiber for 87L Line Differential

ANSI 87L

Dedicated fiber or a C37.94 multiplexer for 87L: delay, asymmetry, ping-pong or GPS compensation, and the effect of route switching on the relay.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

S/E AS/E B87L87Ldirect fibergo = returnMUXMUXSDH ringlong routedirect fibergo1 msreturn1 msSDH ringgo3 ms5 msreturn3 msgo = return: alignment error 0°error = (5 − 3) / 2 = 1 ms → 21.6°go path moved to the long routefalse differential current87L assumes go = return to align samples60 Hz: 21.6° per ms of errorChannelDirect fiberMultiplexerSDH ringAlignment© tizagrp.comS/E AS/E B87L87Ldirect fibergo = returnMUXMUXSDH ringlong routedirect fibergo1 msreturn1 msSDH ringgo3 ms5 msreturn3 msgo = return: alignment error 0°error = (5 − 3) / 2 = 1 ms → 21.6°go path moved to the long routefalse differential current87L assumes go = return to align samples60 Hz: 21.6° per ms of errorChannelDirect fiberMultiplexerSDH ringAlignment© tizagrp.com
87L channel: direct or multiplexed fiber. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

The 87L line differential can communicate over a dedicated fiber between the two relays or through a multiplexer, with an IEEE C37.94 or G.703 interface, over an SDH or packet network. Direct fiber gives a fixed, symmetrical delay, but its reach depends on the relay's transceiver. The multiplexer uses the existing telecom network, at the cost of delays that can change and become asymmetrical when the network switches routes, which 87L sees as an angle error.

The decision

Every line differential 87L needs a digital channel between the relays at the two terminals to exchange the measured currents. There are two ways to give it that channel:

  • Direct (dedicated) fiber: the optical port of the relay at one terminal connects through a fiber pair to the relay at the other terminal, with no equipment in between.
  • Multiplexed channel: the relay connects to a multiplexer of the telecom network, usually with the IEEE C37.94 optical interface or with a 64 kbit/s G.703 electrical interface, and the network carries the channel to the multiplexer at the other terminal.

The choice affects delay, channel symmetry, reach, availability and who is responsible for what. There is no single answer: it depends on the line length, the fibers available and the utility’s telecom network.

Why the channel matters so much for 87L

To compare currents, 87L needs the samples from both terminals to correspond to the same instant. There are two main methods to align them:

  • Round trip (ping-pong): the relay measures how long a message takes to go and come back, and assumes each direction takes half.
  • External time reference: each terminal time-stamps its samples with a common reference, usually GNSS, and needs to assume nothing about the channel.

With the first method, any difference between the go and return delays becomes an alignment error equal to half that difference, and the alignment error shows up as an angle error: 21.6 degrees per millisecond at 60 Hz and 18 degrees at 50 Hz. An angle error between the two currents produces a false differential current, which under heavy load can approach the operating threshold.

Direct fiber

With dedicated fiber, the go and return paths run through the same cable with the same length, with no intermediate equipment adding variable delays. The channel is symmetrical and stable by construction, and the round-trip method works without surprises.

Its limits are different:

  • Reach: set by the relay’s optical transceiver against the total link loss, including splices, connectors and the aging margin. Multimode interfaces cover short distances and long-reach single-mode ones cover longer lines. The guide on the multiplexer and fiber optic network covers the physical medium.
  • Fiber use: each relay takes a fiber pair end to end, which is no longer available for other services.
  • No network supervision: the fiber has no management system to report its degradation; the relay itself watches it with its error counters and channel alarms.

Multiplexed channel

With a multiplexer, 87L shares the telecom network with teleprotection, SCADA and voice. It is the natural option when the line is long, when there are no free fibers end to end or when the network already has routes through other substations.

Here the risks that direct fiber does not have appear:

  • Longer, variable delay, from passing through the equipment and from the route chosen.
  • Route switching: in an SDH ring, when a section fails, the network switches traffic to the protection route. If the switchover affects only one direction, the go and return paths take routes of different length and the channel becomes asymmetrical.
  • Packet networks: when transport migrates from SDH to IP or MPLS networks, the 87L channel travels by circuit emulation, and delay variation and symmetry depend on how that network is designed.

Publications from a relay manufacturer indicate that SDH networks have a natural asymmetry of a fraction of a millisecond and that an asymmetry of around 1 to 2 ms can already cause unwanted operations. That is why, when 87L goes through a multiplexer, the network is configured to switch both directions together, the delay and asymmetry alarms are set in the relay, or alignment by external time reference is used.

CriterionDirect fiberMultiplexed channel
Channel symmetrySymmetrical by constructionDepends on the network configuration
DelayLow and fixedLonger; changes with the route
ReachLimited by the relay’s transceiverThat of the telecom network
Fibers usedOne pair end to end per relayShares the network with other services
Who owns the channelThe protection groupShared with the telecom group
Typical riskLoss from splices or connectorsAsymmetry after a route switchover
Which channel to use for 87L
  • Is there a free fiber pair end to end within the reach of the relay's transceiver?
    • YesDirect fiber, with a verified optical budget and the relay's channel alarms
    • NoDoes the telecom network guarantee bidirectional switching and symmetrical delay?
      • YesMultiplexer with C37.94 or G.703, with delay and asymmetry alarms set
      • NoMultiplexer with alignment by external time reference, or review the network before using it

Many important lines combine both options: one channel over direct fiber and the other through a multiplexer, on different routes, as the second channel of the same 87L or as the channel of the second main protection.

What not to do

  • Raise the 87L threshold to “tolerate” asymmetry instead of fixing the channel.
  • Accept a multiplexed network without knowing how each service switches.
  • Use alignment by external reference without supervising synchronization at both terminals.
  • Test 87L only with the channel on its normal route: the problem shows up when the network switches.

How it is checked

In general terms, commissioning an 87L with a multiplexed channel verifies the delay and asymmetry reported by the relay on the normal route and on each protection route, forcing the network switchovers with the function under test. The end-to-end test, with synchronized injection at both terminals, confirms that the protection operates for internal faults and stays stable for external ones. If your 87L already shows channel alarms or tripped with no fault, the guide on 87L tripping on channel failure describes the diagnosis.

How we help

At Tiza Group we review the channel settings, the delay and asymmetry alarms and the alignment method of your 87L relays with our remote relay configuration service, for the main brands, on high and extra-high voltage lines. To check the relay and channel together in the field, we carry out the end-to-end test at both terminals, in Colombia or elsewhere on request. Contact us with the brand and model of your relays.

References

  • IEEE C37.94, Standard for N Times 64 Kilobit Per Second Optical Fiber Interfaces Between Teleprotection and Multiplexer Equipment.
  • ITU-T G.703, Physical/electrical characteristics of hierarchical digital interfaces.
  • IEC 60834-1, Teleprotection equipment of power systems – Performance and testing – Part 1: Command systems.
  • IEEE C37.243-2015, Guide for Application of Digital Line Current Differential Relays Using Digital Communication (under revision).
  • IEC TR 61850-90-12:2020, Wide area network engineering guidelines.

Frequently asked questions

Why does channel asymmetry affect 87L but not teleprotection?

Because 87L compares the currents at both terminals at the same instant, and to align them it assumes the go and return paths take the same time. If they do not, it compares samples from different instants and a false differential current appears. Teleprotection only sends a command; a different delay makes it arrive slightly later, but does not falsify it.

Is a GPS-synchronized 87L no longer sensitive to asymmetry?

Yes, because each terminal time-stamps its samples with a common time reference and does not need to assume the channel is symmetrical. In exchange it depends on synchronization: if one terminal loses the reference, the relay must fall back to another alignment method or block, depending on its design.

How far can 87L reach over direct fiber?

It depends on the relay's optical transceiver and on the actual fiber loss, including splices and connectors. Manufacturers offer short-distance multimode interfaces and long-reach single-mode ones. The optical budget calculation with the measured loss is what confirms whether the link works with margin.