Synchronizing and closing 25 and 78
Enter the voltages, frequencies and angle of both sides, the breaker closing time and the 25 relay settings. The tool calculates the slip, the advance angle, when the timed relay gives permission, at what angle the breaker closes and the maximum slip; if you enable it, also the time between the 78 blinders.
IEEE C50.12 / C50.13generator limits, quoted by SEL 2012SEL 2012generator synchronizing (Thompson)SEL 2003§ pp. 10-1378 blinder timer (Tziouvaras and Hou)
Results
—
—
—
—
—
—
—
—
—
—
—
—
—
—
—
Charts
- Live side
- Changing signal
- Angle between voltages
- Voltage across contacts
- Time marks
- Angle at its slip
- At the maximum slip
- Permission and contacts
- Total impedance
- Swing path
- Outer blinders
- Inner blinders
How it was calculated and standards
Step-by-step calculation
Loading these settings into a relay? We configure it remotely.
What it is for
Before closing a breaker between two sources, a generator onto the bus or a line between two substations, three things must be compared: voltage, frequency and angle. This tool calculates the slip, the speed at which the angle turns, the advance angle a synchronizer needs and what a timed 25 relay does with its window: when it gives permission, at what angle the breaker closes and up to what slip the close lands inside the window.
If the incoming side is a generator, it compares the close with the design limits SEL quotes from IEEE C50.12 and C50.13. With the 78 block enabled it calculates the angle at which the swing crosses each blinder, the time between them and the electrical centre, to review the timer of the out-of-step protection.
How it is calculated
Own derivationrotating phasor
Slip, angle speed and beat voltage
s = f2 − f1 · φ(t) = φ0 + 360·s·t · Vb = √(V1² + V2² − 2·V1·V2·cos φ)The incoming side at frequency f2 turns relative to the bus at frequency f1. A positive slip (incoming side faster) brings the angle to zero from the negative side; a negative one, from the positive side. A full turn takes 1/|s| seconds. The beat voltage is what a voltmeter reads between the two sides of the open breaker.
SEL 2012advance angle
Advance angle and residual
θadv = 360 · s · tclose · error = 360 · s · Δttclose adds the breaker time, the relay output and the auxiliaries. The synchronizer sends the command θadv before zero so the contacts touch in phase; an uncertainty Δt in the closing time leaves a residual angle.
Own derivationtimed 25 relay SEL 2012permissive contact
Timed window
tw = 2·Δφ / (360·|s|) · smax = 2·Δφ / (360·(tsup + tclose))The relay gives permission if the angle stays inside ±Δφ for tsup; permission comes with the angle at −Δφ + 360·|s|·tsup (with its real sign) and the contacts touch tclose later. Permission lasts tw − tsup; if that is shorter than tclose, the permissive contact opens while the closing coil is still energized. At zero slip the angle does not move: there is permission only if it already sits inside the window.
Own derivationtwo-machine model SEL 2003§ pp. 10-13blinder timer
Out-of-step blinders (78)
δ = 2·atan(|Ztot| / (2·d)) · tcross = (δin − δout) / (360·fslip)With equal sources and all impedances at the same angle, the impedance measured during the swing travels along the perpendicular bisector of Ztot = Zg + Zt + Zs, at a distance (|Ztot|/2)·cot(δ/2) from that line. The electrical centre, at δ = 180°, is the midpoint of Ztot. The function recognizes the swing if tcross exceeds the timer; the largest slip it detects is (δin − δout)/(360·t78).
Limits of the calculation
- The voltage, slip and angle windows, the timer, the live and dead thresholds and the blinders are data of your installation: the relay manufacturer, the study and the grid operator set them. The tool does not propose settings.
- The limits of ±10°, 0 to +5 % and ±0.067 Hz are design limits of the generator that SEL (Thompson, 2012) quotes from IEEE C50.12 and C50.13; those standards were not consulted. They are shown only when the incoming side is a generator and they are not settings of an installation.
- The slip is assumed constant while the angle crosses the window: generator acceleration, the voltage regulator and breaker pole scatter are not modeled.
- The dead-bus or dead-line state is classified with the thresholds you enter; the logic that allows closing under those conditions depends on how it is enabled in your relay.
- The 78 block uses our own two-machine model with sources of equal magnitude and all impedances at the same angle. With unequal sources the path is no longer a straight line. Blinders, timer and slips are set from the stability study (SEL, Tziouvaras and Hou, 2003).
- IEEE C37.102, IEEE 1547-2018 and the IEC 60255 parts on synchronism check were not consulted. It does not replace the stability study or the tests of the synchronizing scheme.
Frequently asked questions
What is the advance angle and how is it calculated?
It is the angle the phase difference travels while the breaker closes. If the command goes out as the angle passes through zero, the contacts touch later, with the angle already moved on. The synchronizer sends the command that many degrees early: 360 × slip × closing time. With 0.1 Hz and 100 ms of closing time that is 3.6°. The closing time includes the breaker, the relay output and the auxiliaries; an error in that time leaves a residual angle of 360 × slip × error.
Why does a timed 25 relay limit the slip?
The relay gives permission only if the angle stays inside the window for the supervision timer. The angle crosses a ±Δφ window in 2·Δφ/(360·|s|) seconds; if that time is shorter than the timer, there is no permission. That is why the timer replaces a slip measurement: with ±10° and 300 ms, permission is given up to 0.185 Hz, and the close stays inside the window up to a somewhat lower slip, because the closing time adds to the timer.
How are the 78 blinders related to the slip?
During a swing the measured impedance moves with the angle between the sources. Each blinder corresponds to an angle, and the time between the outer and the inner blinder is the angle difference divided by 360 times the slip. If the impedance crosses faster than the timer, the function does not recognize the swing; that is why the timer is set from the fastest slip of the stability study.
We review your synchronizing scheme
We review the settings of the 25 relay or the synchronizer against the real time of your breaker, and the 78 blinders against your stability study, with no travel.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSecondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws