Function 51G: neutral overcurrent

Overcurrent on the transformer neutral CT: 51G curve, 50G stage, resistance grounding and test plan with a test set.

Siemens SIPROTEC 5 7UT§ 11.18-11.19single-phase overcurrentIEEE C37.91§ 2000, 6.4.4impedance-grounded neutralIEEE C37.2§ 2008function numbers

Example cases
Function 51G: neutral overcurrent

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
A

Neutral CT secondary current from which the curve runs.

s
A
s
E3Simulation
Ω
%

Only counts for the winding fault.

A

Enter it from your short-circuit study.

E4Installation and test set
kV
A
A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
% of In
%
ms
%
%
ms
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Neutral current

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 51G measures the current flowing up the transformer's grounded neutral with its own CT. Every earth fault fed by that neutral passes through it, whether in the winding or in any feeder of the network below.

That is why it is the backup of the feeder and bus earth protections, and the only one that sees small earth faults when the neutral is resistance grounded.

How it operates

  • The 51G curve runs from 1.1 times the pickup and resets below 1.045 times, like the other curves of the cited manual. The 50G is a definite-time stage with a fixed reset of 0.95.
  • With a resistance-grounded neutral the maximum current is the phase voltage divided by the resistance; a fault inside the winding gives less current the closer it is to the neutral.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The test set injects a single current into the neutral input. The plan finds the pickup and reset of each stage and measures the times at 2, 5 and 10 times the curve setting and at 2 times the 50G setting.

If at that current the 50G already operates before the curve, the plan flags it so you can block it during that test.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • With a solid neutral, enter the fault current from your study.
  • Neither the winding reactance nor the network reactance is modeled: with resistance, the current limited only by it is used.
  • The tolerances are those of the cited manual; enter those of your relay.

Frequently asked questions

Why is the 51G slow if the fault is in the transformer?

Because it is backup: it has to wait for the feeder protections to clear. Internal faults are cleared quickly by the 87T or the 87N.

How much current does a resistance-grounded neutral give?

The phase voltage divided by the resistance: with 13.8 kV and 8 Ω that is 13,800/(√3·8) = 996 A. A winding fault at 20 % from the neutral gives about 199 A.

How does it differ from the 51N?

The 51N sums the three phase currents; the 51G measures the neutral CT. The 51G does not depend on the three phase CTs being equal and sees the current even if the breaker on the wye side is open.