Tiza Group

Home / Tools / Function 50/27 inadvertent energization

Function 50/27: inadvertent energization

Off-line generator energized by mistake: instantaneous 50 armed by the 27, arming and disarming times, the relay inside and a test-set test plan.

IEEE C37.102§ 5.4.2.4inadvertent energizationSEL-700G§ p. 42-45tolerancesIEEE C37.2§ 2008function numbers

Example cases
Function 50/27: inadvertent energization

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
V

Line to line: with the voltage below this value for the arming time, the 50 is ready.

s

Longer than the clearing of a fault in service, so the 50/27 does not arm during a fault. Example value.

s

With the voltage already back the 50 stays armed for this time, so it can still trip on energization. Example value.

A

IEEE C37.102-2006 §5.4.2.2 and §5.4.2.5: about half of the lowest expected energizing current.

s
A
E2Settings, part two
× machine In

From your study. IEEE C37.102-2006 §5.4 gives 1 to 4 times from the grid and 0.1 to 0.2 times from the auxiliary transformer.

E3Simulation
s
A

Energization from the grid, a fault in service or the load if the VT fails.

V

Line to line, measured by the relay.

IEEE C37.102-2006 §5.4.2.4: the scheme needs VT fuse supervision so it does not trip on load.

E4Installation and test set
V
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

V

Example value: enter that of your test set.

E5Relay tolerances
%
% of In
%
V
%
cycles
cycles

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Arming

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

A generator that is stopped or on turning gear can be energized by mistake: a breaker closed in error, a contact that flashes over or a control failure. The machine starts as an induction motor and the currents induced in the rotor damage it in seconds.

With the machine stopped almost all its protections are blind or slow. The 50/27 arms itself when the generator goes off line and trips at once if current appears.

How it operates

  • The 27 watches the terminal voltage: if it is below the threshold for the arming time, the 50 is ready. That time is longer than the clearing of a fault in service.
  • When the voltage returns, the 50 stays armed for the disarming time; so it can still trip even if the energization raises the voltage.
  • A blown VT fuse also leaves the voltage at zero: the loss-of-potential supervision (60) prevents arming in service.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The plan searches the arming voltage by lowering the voltage with no current and reading the armed output, and the 50 pickup by raising the current with no voltage.

It measures the arming time, the trip time at twice the pickup and the disarming time when the rated voltage returns. It checks that it does not trip at rated voltage and that test-set output 3 on BI3 blocks it.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The event current and voltage are the ones you enter; the energization from the grid is not calculated.
  • The fault in service is simulated as 0.5 s long, an example of grid protection clearing.
  • The pickup time of the 50 and the 27, under 1.5 cycles according to the cited data sheet, is added as an estimate to the upper limit of the times.

Frequently asked questions

Why does the 50/27 not trip on a fault in service?

Because the 50 is armed only if the voltage was low for the arming time, which is set longer than the fault clearing. A 0.5 s fault with 5 s of arming does not arm it.

What current appears when a stopped generator is energized?

It depends on the grid: IEEE C37.102-2006 §5.4 speaks of 1 to 4 times the rating from the grid and 0.1 to 0.2 times if it comes from the auxiliary transformer. With 4.2 A rated and 1 time as the minimum, the pickup is about 2.1 A.

Why is the disarming time needed?

Because on energization the voltage rises and the 27 resets. Without a delayed disarming the 50 would disarm before tripping.

Related guides

Other tools

All tools
WhatsApp