Disconnector and earthing switch: induced, bus transfer and capacitive

Enter the energized line, the geometry of both lines and the earthing-switch operation: the tool calculates the currents and voltages induced by magnetic and capacitive coupling and compares them with the rated values. It also gives the bus-transfer current and voltage and the capacitive current the disconnector breaks.

IEC TR 62271-305:2009§ 4, 5.6, A, Bcapacitive currentLine theory§ Carson, Maxwellcoupling between linesCircuit theory§ Rosa–Groverbus transfer

Example cases
Disconnector and earthing switch: induced, bus transfer and capacitive

Only the basic data; the rest is taken with typical values.

ALearn

E1Energized line
kV
A

The highest it will carry while the other line is under maintenance.

E2Geometry of the two lines
m

Between the centres of the two circuits.

m

Of the conductor above ground, with the sag: the tower height minus two thirds of the sag. In the vertical arrangement, that of the middle phase.

m
km
mm
m

Between neighbouring subconductors of the bundle.

Ω·m
E3De-energized line and operation

The operation checked on the earthing switch at this end.

Ω/km

In alternating current, at operating temperature.

Ω
E4Rated values of the earthing switch

Enter below the values from the nameplate or the datasheet. Zero = not known.

A
kV
A
kV
E5Bus transfer
A
m
m

Between conductors of the same phase.

mm
μΩ/m
μΩ

Of the main circuit, from the micro-ohmmeter test.

μΩ
A

From the nameplate or the datasheet. Zero = not known.

V
E6Capacitive current
m
pF
m
μF/km

Source-side capacitance over the capacitance of the side being opened. IEC TR 62271-305 takes 0.1 as representative.

A

0.5 A is what has been assumed without testing for air-insulated disconnectors; use the agreed value if there is one.

Use a decimal point. The calculation runs in your browser and updates as you type.

Electromagnetic induced current

—

Electromagnetic induced voltage

—

Electrostatic induced current

—

Electrostatic induced voltage

—

Bus transfer

—

Capacitive current

—

De-energized line next to an energized one
Top: the two lines and the earthing switches of the line under maintenance for the chosen operation. Bottom: the cross-section with the geometry and the disconnector pole at this end. In yellow, what is induced on the earthing switch.
Bus transfer with the coupler closed
Change the operation step in E5. When disconnector A opens, the feeder current flows through the coupler and bus B, and the loop voltage drop appears across its contacts.
Capacitive current switched by the disconnector
Each contribution is the current that charges that equipment at the phase-to-earth voltage. The red line is the capability of the disconnector.
Induced values versus parallel length
  • EM I
  • EM U
  • ES I
  • ES U
With rated values, each curve is the percentage of its rated value; without them, the percentage of its value at the chosen length. The EM voltage and the ES current grow with length. The EM current grows until the line impedance exceeds the earth resistances and then hardly changes; the ES voltage does not change.

Step-by-step calculation

Need it for a real project? We carry out the full study, with its report.

What it is for

When a line is taken out for maintenance and the line next to it stays in service, the dead line picks up voltage and current from its neighbour. The earthing switch has to make and break those induced currents. This tool calculates them from the geometry and compares them with the rated values of the earthing switch.

It also checks two disconnector duties: transferring a feeder from one busbar to the other with the coupler closed, and opening an unloaded busbar, which means breaking a small capacitive current.

How it is calculated

Line theory§ Carsonmagnetic coupling

Electromagnetic voltage and current

Zik = ω·μ0/8 + j·ω·μ0/(2π)·ln(De/dik) · De = 658.5·√(ρ/f) · Ek = −Σ Zkj·Ij·L

With one end open, the voltage at the earthing switch is Ek. With both ends earthed, the three phases and the earth resistances form a system of equations that gives the current of each phase.

Line theory§ Maxwellcapacitive coupling

Electrostatic voltage and current

Pii = ln(2hi/r)/(2πε0) · Pik = ln(D'ik/dik)/(2πε0) · V = P·q · I = ω·q·L

When isolated, the dead line carries no charge and its voltage follows from that of the neighbouring line. With one end earthed its voltage is zero and the earthing switch carries the current that discharges it.

Circuit theory§ Rosa–Grovertransfer

Transfer current and voltage

It = I·Z2/(Z1 + Z2) · Ut = It·|Zloop| · Lloop of a rectangle with sides Lb and s

IEC TR 62271-305:2009§ A.4, Bcapacitive current

Capacitive current and restrike

I = Σ Ibus + ICT + U/√3·ω·(CCVT + Ccable) · UOV ≤ 1 + 2/(1 + CS/CL)

Limits of the calculation

  • The lines are taken as parallel, at constant height and with balanced load. The shield wire, which reduces the coupling, and transpositions are not modelled.
  • Carson's first-order form is used, valid at power frequency with distances much smaller than the earth-return depth.
  • It is calculated with the load current of the neighbouring line. A fault on that line induces much higher values, which are covered by the short-time current of the earthing switch, not by its class A or B.
  • Each bundled phase is taken as one conductor of equivalent radius; the subconductors sit on a circle.
  • The class A and B ratings of IEC 62271-102 are not in the tool: enter those on the nameplate or in the datasheet.
  • The transfer uses a single loop per phase and ignores the other two phases and the droppers; it is an order-of-magnitude estimate.
  • The busbar and CT currents are the typical values of IEC TR 62271-305 for air-insulated equipment; with manufacturer data the result is better.

Frequently asked questions

Why is there voltage on a de-energized line?

Because it runs next to an energized one. The current of the neighbouring line induces a voltage along the dead line, like the secondary of a transformer, and its voltage charges it like a capacitor. That is why the line is earthed at both ends before work, and the earthing switch must be able to make and break those currents.

What are classes A and B of an earthing switch?

They are two levels of induced-current switching capability defined by IEC 62271-102. Class B is for strong coupling, such as long lines or circuits on the same tower. The rated values are on the nameplate and in the datasheet: enter them and the tool compares them with the case.

How much capacitive current does an air-insulated disconnector break?

Without testing, it has been taken as 0.5 A or less, according to IEC TR 62271-305:2009. That report gives the method to test higher values, which are agreed between the user and the manufacturer.

We review your disconnectors and earthing switches

We calculate the induced currents of your line, review the equipment selection and test the disconnectors on site.