Function 49: thermal overload

Thermal image with k factor and time constant: alarms, cold and preloaded trip, the relay inside and an injection test plan.

Siemens SIPROTEC 5§ 6.40thermal imageSiemens SIPROTEC 5§ 11.45tolerancesIEEE C37.2§ 2008function numbers

Example cases
Function 49: thermal overload

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings

Permissible continuous current divided by the rated current of the protected equipment.

A
s
%
A
%

The trip command is withdrawn when the image falls below this value.

E3Simulation
A
A
E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
% of In
%
s

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Alarm

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 49 calculates the equipment temperature from the current flowing through it, as if it were a body that heats up and cools down with a time constant. It trips when that image reaches 100 %, which is the final temperature at the permissible continuous current k·In.

It is used in cables, transformers and motors, where a moderate overload is tolerated for a time and a larger one for less.

How it operates

  • The image tends to (I/(k·In))² with time constant τ: with rated current and k = 1.1 it settles at 83 %.
  • Trip time depends on the previous load: a hot equipment trips sooner.
  • The thermal alarm warns before the trip, and the current alarm warns of an overload even if the image is still low.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The plan measures the cold times at 1.5, 2 and 3 times k·In, where the manual declares the time class. Before each point the thermal image must be reset with the reset binary input.

It also measures the time to the thermal alarm and the pickup of the current alarm.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The model is that of a homogeneous body; it does not consider ambient temperature.
  • Below 1.25 times k·In the manual does not state the time tolerance.
  • The limiting of the image at very high overcurrents is not modeled.

Frequently asked questions

What is the thermal time constant?

The time in which the equipment reaches 63 % of its final heating under a constant load. It is given by the manufacturer of the protected equipment.

Why does the time change with the previous load?

Because the equipment is already hot: the image starts higher and reaches 100 % sooner. With 6 A, k·In = 4.4 A, τ = 600 s and 3 A beforehand, the trip comes in about 290 s; from cold, in about 460 s.

How do you reset the image before each test?

With the thermal image reset binary input or with a parameter change, according to the cited manual. Without resetting it, each point starts with the heat of the previous one.