Function 50/51 and 50N/51N: overcurrent

Phase and ground overcurrent with IEC and IEEE curves: pickup, reset, times with tolerance, the relay inside and an injection test plan.

Siemens SIPROTEC 5§ 11.15curves and tolerancesIEC 60255-151§ 2009curvesIEEE C37.2§ 2008function numbers

Example cases
Function 50/51 and 50N/51N: overcurrent

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
A

Secondary current above which the curve runs.

s
A
s
E2Settings, part two
A
s
A
s
E3Simulation
A

Secondary current of the faulted phases.

Logic selectivity: the downstream relay blocks the 50 of this relay while it clears the fault.

E4Installation and test set
A

Only to show the primary values.

A

Example value: enter that of your test set. Points that exceed it are marked.

E5Relay tolerances
%
% of In
%
ms
%
%
ms
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Reset

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 50/51 is the overcurrent protection: it trips when the current exceeds a set value. The 51 waits a time that depends on the current (inverse-time curve) or a fixed time; the 50 trips with no delay or a short one. The 50N/51N does the same with the residual current 3I0, which is almost zero in normal service and appears mainly in ground faults.

This tool shows where each signal comes from: the bay CTs, the relay current inputs, the logic that combines the steps and the output that energizes the breaker trip coil.

How it operates

  • Pickup: for the IEC and IEEE curves the Siemens SIPROTEC 5 manual states that the curve runs from 1.1 times the setting and that the stage resets below 1.045 times.
  • Time: the inverse-time curve gives the time at the current the relay sees; the definite-time stages wait for their time delay.
  • Selectivity: the blocking input lets the downstream relay stop the 50 of this relay while it clears its fault.
  • Earth: with the CTs in star, the sum of the three phases enters through the IN input; in a single-phase fault it equals the current of the faulted phase.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

The plan looks for pickup with a ramp that starts 5 times the tolerance below and advances in steps of one tenth of the tolerance, for reset with the ramp reversed, and for the times at 2, 5 and 10 times the setting.

The phases are tested with a balanced three-phase set, so the 51N sees no current. Earth is tested with a single phase: block the phase functions with the blocking input, or disable them during that test.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The default tolerances are those of the cited manual: enter those of your relay.
  • CT saturation, inrush blocking and dynamic pickup are not modeled.
  • Definite-time delays do not include the relay's own operating time or that of the output.

Frequently asked questions

Why does the inverse-time curve not pick up exactly at the setting?

Because that is what the manufacturer states: in the Siemens SIPROTEC 5 manual the curve runs from 1.1 times the setting and resets at 1.045 times. Other manufacturers use other factors; look them up in your relay's manual.

At what currents are the 51 times tested?

At 2, 5 and 10 times the setting, within the 2 to 20 times range in which the manufacturer declares the time accuracy. If the 50 operates first at any of these points, the plan flags it so you can block or disable it.

How do you test the 51N without tripping the phases?

Injecting through a single phase and blocking the phase functions with the blocking input, or disabling them while ground is tested. The plan flags the points where the ground current exceeds the phase pickup.