Home / Tools / Function 32 reverse power
Function 32: generator reverse power
Generator motoring: reverse power, delay, sequential trip with the stop valve closed, the relay inside and a test-set test plan.
IEEE C37.102§ 4.5.5.3reverse powerSEL-700G§ p. 43tolerancesIEEE C37.2§ 2008function numbers
Results
—
—
—
—
Charts
- Power
- Active signal
- Characteristic
- Tolerance band and point
How it was calculated and standards
Test plan with injection test set Pro
| # | Test | Injection | Expected | Minimum | Maximum | Measured | Result |
|---|
What each parameter is
| Parameter | Value | What it does |
|---|
Loading these settings into a relay? We configure it remotely.
What it is for
The 32 protects the turbine, not the generator: when the turbine stops driving, the machine stays on the grid as a synchronous motor and draws active power. In a steam turbine this heats the blades by friction with the steam; in a diesel engine there may be unburned fuel.
The power the machine draws when motoring depends on the turbine: it is large for a gas turbine and very small for a steam turbine or a hydro unit with the blades out of the water. The setting goes below that power.
How it operates
- The relay calculates the three-phase power from the VT voltages and the CT currents and picks up when the power flowing into the machine exceeds the setting.
- It always has a delay, so it does not trip on power swings or during synchronizing.
- In sequential tripping the turbine stops first and the 32 opens the breaker afterwards; with the stop valve closed a second stage trips with a short delay.
The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.
Test plan
The test set injects balanced nominal voltages and currents at an angle of 180°: all the power is then active and negative. The pickup is searched by raising the current in small steps.
Times are measured at twice the pickup; a point with a lot of reactive power checks the measurement at low power factor and another with power toward the grid checks that it does not operate. The fast stage is tested with test-set output 3 on BI3.
Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.
Limits of the calculation
- The declared tolerance holds at unity power factor; at low power factor the angle error of the CT and the VT weighs more and is not modelled.
- The relay pickup time, under 10 cycles according to the cited data sheet, is added as an estimate to the upper limit of the times.
- The motoring power of your turbine comes from its manufacturer: the ranges in IEEE C37.102 are a guide.
Frequently asked questions
Why is the setting so low?
Because a steam turbine with no steam needs very little power to keep turning: between 0.5 % and 3 % of the rating according to IEEE C37.102-2006 §4.5.5.3. A higher setting would not detect it.
Why does the 32 have such a long delay?
Because during a power swing or while synchronizing the power can be negative for a moment. The cited guide speaks of up to 60 s, typically 30 s for steam; the exact time depends on how long the turbine withstands motoring.
How is reverse power injected with the test set?
With balanced voltages at 0°, −120° and 120° and the currents shifted 180° from their voltage. With 115 V line to line and 0.2 A per phase the power is −√3·115·0.2 = −39.8 W.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
