Function 71: oil level

Transformer oil level: low and minimum level contacts, binary inputs, delays and test plan with a test set.

IEEE C37.91§ 2000, 4oil level detectorsSiemens SIPROTEC 5 7UT§ 11.1.3binary inputsIEEE C37.2§ 2008, 3.1.71function numbers

Example cases
Function 71: oil level

Only the basic data; the rest is taken with typical values.

ALearn

E1Settings
% of the indicator

Example value: the contact position is set by the oil level indicator manufacturer.

s
% of the indicator

Example value: the contact position is set by the oil level indicator manufacturer.

s

Prevents tripping on oil sloshing during an earthquake or a knock.

E3Simulation
%
V
E4Installation and test set
V
V
ms
E5Relay tolerances
ms
%
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Function status

—

Operating time

—

Oil level

—

Test plan

—

From the primary to the relay and the trip coil
  • Rating
  • Active signal
Magenta lines are the primary; light lines are the protection and control wiring; dashed yellow lines are the communications. What lights up in yellow is what changes in the simulation.
Function characteristic with its tolerance
  • Characteristic
  • Tolerance band and point
The curve or the steps are the settings; the yellow band is the declared tolerance; the point is the simulation.
Test set connected to the relay
Select a point in the “Test plan” tab: the drawing shows what the test set injects at each terminal. Before connecting, short-circuit the CTs and open the VTs and the trip circuit at the test block.

Test plan with injection test set Pro

#TestInjectionExpectedMinimumMaximumMeasuredResult

What each parameter is

ParameterValueWhat it does

Loading these settings into a relay? We configure it remotely.

What it is for

The 71 watches the oil level. The level indicator, almost always on the conservator tank, has two contacts: one closes with a small drop and gives the alarm; the other, at minimum level, trips before the active part is left without oil.

A level drop can come from a leak, an open valve or an incomplete filling; it also drops with cold, because the oil contracts.

How it operates

  • Each closed contact activates its binary input if the station battery voltage exceeds the input high threshold. After its delay, the alarm activates its output and the minimum level trips.
  • The trip delay prevents oil sloshing, from an earthquake or a knock, from taking the transformer out.

The relay drawing is the same in all Tiza protection functions: a generic numerical relay, not a specific brand. Its terminals, blocks and inputs light up according to the function.

Test plan

With the DC source of the test set, the voltage at each input is raised until it picks up: it must do so between the two thresholds of the manual.

With a binary output of the test set each contact is closed and the time to its output is measured. In the switchyard, check the contacts by moving the indicator needle or with your manufacturer's procedure.

Before connecting the test set: short-circuit the CT secondaries at the test block, open the VT secondaries on the yard side, and open the trip links to the breaker and to other relays. The results sheet is printed or downloaded as CSV with the measured values and the result of each point.

Limits of the calculation

  • The level is typed in by hand: the tool does not calculate the oil expansion with temperature.
  • The contact positions in the examples are ours: use those of the indicator manufacturer.
  • The own time with binary input is the approximate one from the manual: estimate.

Frequently asked questions

Why do the alarm and the trip use different contacts?

Because a small drop gives time to look for the leak and top up the oil, and a large drop leaves the core and windings without insulation or cooling.

Why does the trip have a delay?

So as not to trip on oil sloshing in the conservator during an earthquake or a knock: the level has to stay below the contact for the duration of the delay.

Does the level change with temperature?

Yes: the oil expands when it heats up and contracts when it cools. That is why the conservator indicator usually has marks for different temperatures.