Home / Tools / IEC 61850 station network
IEC 61850 station network: ring, PRP, HSR and RSTP
Choose the topology, the publisher and the subscriber, and click a link to fail it. The tool draws the path the frames follow, how long the traffic stays cut and the GOOSE and sampled-value frames that are lost.
Results
—
—
—
—
Charts
How it was calculated
Calculated values
What it is for
The station network links the bay IEDs, the gateway and the HMI. When a link or a switch fails, the traffic takes another path or stops. This tool shows on the drawing which path the frames take before and after the failure, how long the flow between two IEDs stays cut and what is lost in that time.
The process-bus load, the GOOSE latency and the address plan are in the GOOSE/SV addresses and process bus tool, which uses the same calculation engine.
How it is calculated
Source: R. Moore, RUGGEDCOM white paper on RSTP in a ring (2007)
Recovery of an RSTP ring
T = TL + (N − 3) · TPA for even N; T = TL + (N − 2) · TPA for odd NIt is the worst case for the failure of one link. The root is switch 1 and the blocked port sits on the farthest link. If a link of the path fails, the flow stops for T; if the blocked link fails, it does not stop.
Source: IEC 62439-3
PRP and HSR
interruption = 0 while one copy remains; with no copy, until repairedPRP sends each frame over LAN A and over LAN B; HSR sends it both ways round the ring. Each frame carries 6 more bytes.
Source: IEC 61850-8-1:2004, cl. 18; 9-2LE guideline; IEC 61869-9:2016
What is lost
SV lost = T · frames per second; GOOSE lost = T / MaxTime; alarm if T > time allowed to liveAn event that happens during the interruption arrives up to T late. If T exceeds the time allowed to live of the last frame, the subscriber flags the communication as lost.
Source: IEEE 802.3
Delay of a frame along the path
t = (S + 1) · (L + 8) · 8 / C + S · latencyS is the number of switches or nodes that forward the frame, L its length in bytes and C the link speed. It assumes store and forward without queues.
Limits of the calculation
- The RSTP time is a worst case from a manufacturer's white paper. MRP and proprietary rings have other times.
- It does not model queues or priority: the GOOSE/SV addresses and process bus tool does.
- In RSTP it assumes one IED per switch and the root on switch 1. In PRP each LAN is a single switch.
- It does not replace the tests of your substation network. The example cases are illustrative.
Frequently asked questions
Why is RSTP not suitable for sampled values?
Because frames are lost while the ring reconfigures. With 8 switches and the times of the RUGGEDCOM white paper the recovery takes about 31 ms: almost 150 sampled-value frames from each merging unit at 4800 frames per second. That is why the process bus uses PRP or HSR, which lose no frames with one failure.
What happens if exactly the blocked link of the ring fails?
Nothing in the traffic: that link carried no data. RSTP only registers the topology change. The tool shows it if you click the link marked as blocked.
Do PRP or HSR survive two failures?
Not always. PRP survives one failure in each LAN if they are not on the same path; HSR loses the nodes left isolated between the two failures. Try two failures in the tool and see which IED loses service.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPPC control testsPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws
