Home / Tools / PPC control tests
PPC control tests
Pick the test in the tabs, enter the controller settings and simulate the plant or paste your record. The tool finds each step, measures Tr, Te and overshoot with the 3 % bands, estimates the droop and deadband, measures the worst-minute ramp and the mean rate, and compares each result with CREG 060 and the CNO agreements.
CREG 060 de 2019§ art. 2 y 14 aTr, Te and voltage controlCREG 060 de 2019§ art. 12power and frequency controlCREG 060 de 2019§ art. 15start-up and shutdown rampCREG 101 104 de 2026§ art. 8 (num. 7.7)tests before commercial operationAcuerdo CNO 1987§ anexo 1, num. 4.2voltage control testsAcuerdo CNO 1826§ annex (pending)power and frequency testsAcuerdo CNO 1849§ Annexes 1 and 2 (pending)load take-up and drop rate
Results
—
—
—
—
—
—
Charts
- Recorded response
- Set point or frequency
- 3 % bands
- Record points and fitted line
- Setting characteristic
- Deadband
- Recorded power
- Maximum ramp in force
- 60 s window
How it was calculated and standards
Step-by-step calculation
What it is for
Before commercial operation, a solar or wind plant connected to the STN or the STR must show the CND that its power plant controller (PPC) regulates voltage, responds to frequency and limits its ramp as CREG 060 of 2019 requires. This tool reads the record of each test, or simulates a plant for practice, and gives the figures that are reported: Tr, Te and overshoot of each step, estimated droop and deadband, worst-minute ramp and mean rate.
Use it to prepare the tests, tune the controller before the site visit and review the records in the field, before writing the report.
The list of tests comes from numeral 7.7 of the Código de Operación, as amended by article 8 of CREG 101 104 of 2026: power and frequency control (ii), start-up and shutdown ramp, which accepts laboratory or factory certificates and field tests (iii), and reactive power and voltage control (iv). After commercial operation starts, the CND follows up with records of at least 10 samples per second; the voltage test record still requires 100 samples per second (CNO Agreement 1987). CREG 101 104 de 2026§ art. 8num. 7.7, tests
How it is calculated
CREG 060 de 2019§ art. 2Tr and Te Acuerdo CNO 1987§ anexo 1, num. 4.2steps
Step times
|y(t0 + Tr) − y0| = 0.03·Δ · |y(t) − yf| ≤ 0.03·Δ for t ≥ t0 + Te · Δ = |yf − y0|t0 is the instant the set point or the frequency changes; y0, the steady value before the step, and yf, the expected final value. In voltage control the reactive power is read and Tr under 2 s and Te under 10 s are required; in frequency the active power is read and Tr of 2 s or less and Te of 15 s or less are required. The overshoot is how far the signal goes past yf, as a percentage of Δ.
CREG 060 de 2019§ art. 2voltage droop
Voltage droop from the record
Vref − V = s · Q/QbaseA least-squares line is fitted to the steady value of each plateau; its slope is the droop s. It is compared with the droop set in the controller. The reactive power base is assumed to be 0.33 Pn.
CREG 060 de 2019§ art. 12droop and deadband
Frequency droop and deadband
ΔP/Pn = −(Δf − b)/(fn·R)R is the droop and b the deadband. With two or more plateaus outside the deadband, the fitted line gives R by its slope and b by where it crosses the frequency axis; with a single plateau the deadband setting is used. The resolution requires R of 2 % to 6 % and b of 0 to 120 mHz, initially 30 mHz or less.
CREG 060 de 2019§ art. 15ramp Acuerdo CNO 1849§ considerationsdeclared rate
Ramp and load take-up rate
max |P(t + 60 s) − P(t)| ≤ r·Pn · v = 0.94·ΔP/(t97 − t3) · |tmeasured − tdeclared| ≤ 0.05·tdeclaredr is the maximum ramp in force, 14 % per minute at first. The mean rate v is measured between 3 % and 97 % of the change, our own criterion while the method of Annex 1 of CNO Agreement 1849 is pending. The 5 % tolerance on the declared time is the one that agreement quotes from numeral 7.6 of CREG 025 of 1995.
Limits of the calculation
- Pending: the annex of CNO Agreement 1826, with the procedure of the power and frequency test (size and number of steps, record resolution and format), and article 5 of CREG 023 of 2001, which says how the response is verified at the point of connection. The tool applies only the values of article 12 of CREG 060.
- Pending: Annexes 1 and 2 of CNO Agreement 1849, with the test plan, the rate calculation and the report format. The mean rate between 3 % and 97 % is our own criterion, and the 5 % tolerance is applied to the recorded span, although CREG 025 writes it from 0 MW to the effective capacity.
- The expected final value of each step is taken from the record (mean of the last second of each plateau), unless you pick the set point or the droop law in Advanced mode.
- The reactive power base of the voltage droop is not defined in the resolution: 0.33 Pn is assumed and can be changed.
- The local and remote set point reception test, the capability curve, voltage dips and fast reactive current are not calculated here. SDL plants have other rules.
- The simulated plant is our own teaching model, not the validated model of your plant.
- A step whose record ends before the maximum Te plus the steady value window, or that is still changing at the end, stays pending: it is not taken as a pass.
- The 5 % tolerance of the declared rate is read without a sign: the measured time must be within 5 % of the declared time, above or below.
- CREG 101 104 of 2026 did not change the voltage control (num. 5.7 a), power and frequency (art. 12) or ramp (num. 5.8) requirements this tool uses.
- On the SDL, CREG 070 (chapter 11, num. 11.2.1.2 g, and chapter 12, num. 12.2.1.2 g) requires the same Tr of 2 s or less and Te of 15 s or less from the power and frequency control, but chapter 12 sets no Tr or Te for the voltage control. This tool does not calculate SDL plants.
Frequently asked questions
How are Tr and Te measured in the voltage control test?
On the reactive power record at the point of connection, counted from the moment the set point is sent. Tr is the time for the reactive power to move 3 % of the expected change; Te, the time for it to enter the ±3 % band around the final value and not leave it again. CREG 060 requires Tr under 2 s and Te under 10 s in the voltage, reactive power and power factor modes.
What does the frequency control test of a solar plant require?
The control must have a droop adjustable from 2 % to 6 % and a deadband from 0 to 120 mHz, initially 30 mHz or less, and respond to a step with Tr of 2 s or less and Te of 15 s or less, without oscillating. Today solar and wind plants are exempt from the low-frequency response. The detailed procedure is in the annex of CNO Agreement 1826.
What ramp may a solar plant have at start-up?
CREG 060 sets an initial maximum ramp of 14 % of rated power per minute at start-up and shutdown, with the primary resource available; the CND may revise it. Separately, the agent declares its load take-up and drop rate to the CND and demonstrates it with a test, under CNO Agreement 1849.
Related guides
Other tools
All tools
Solar energy
PV system sizingPV production and energy costPV I-V curveAGPE classifier and connection proceduresCable voltage dropSolar plants and the grid codeP-Q capability testPlant model validationCND supervision indicatorsPMU tests and commissioningRenewable energy tax incentives (Colombia)
Protection
Function 50/51 overcurrentFunction 27/59 voltageFunction 81 frequencyFunction 67/67N directionalFunction 46 negative sequenceFunction 49 thermal overloadFunction 25 synchronism checkFunction 32 reverse powerFunction 51V voltage overcurrentFunction 64G stator groundFunction 27TN third harmonicFunction 64F rotor groundFunction 78 out-of-stepFunction 50/27 inadvertent energizationFunction 37 undercurrentFunction 38 bearingsFunction 48 incomplete sequenceFunction 66 starts per hourFunction 51LR locked rotorFunction 14 underspeedFunction 47 phase sequenceFunction 59N residual overvoltageFunction 60 fuse failureFunction 55 power factorFunction 46BC broken conductorFunction 68 power swing blockingFunction 87N restricted earth faultFunction 63 Buchholz and pressureFunction 26 oil temperatureFunction 71 oil levelFunction 87B bus differentialFunction 60C bank unbalanceFunction 51G neutral groundFunction 79 reclosingFunction 86 lockoutFunction 94 tripFunction 74 trip supervisionFunction 87L line differentialPhasor diagramRelay coordinationCurrent transformer: burden and saturationVector group compensation (87T)Frequency df/dt rampBreaker failure 50BF87 differential settingCT and VT selectorDistance setting 21MV feeder coordinationMotor protectionBoundary meteringGenerator protectionLoad shedding 81 and UVLSShunt reactorSynchronizing and closing 25/78Secondary arc and single-pole reclosing
Analysis and communications
COMTRADE records: viewer and generatorOscillography analysisIEC 61850 SCL viewerIEC 61850 SCL auditorIEC 61850 network: GOOSE/SV addresses and process busIEC 60870-5-104 APDU decoderIEC 61850 to IEC 60870-5-104 and 101 mappingICCP bilateral table checkerIP and VLAN planDNP3 and Modbus decoderTeleprotection channel timeOptical and radio link budgetTime synchronisationMMS control sequenceGOOSE simulatorIEC 61850 station networkInterlocking table and CILO equationsCause-and-effect matrix and logic checkerZones and conduits (IEC 62443-3-2)Zone firewall rule reviewerRoles and permissions (IEC 62351-8)IED X.509 certificate verifierDevice hardening baselineIncident response exercise (CNO 2188)Cybersecurity gap: CNO and IEC 62443
Equipment testing and diagnostics
Commissioning checklistCurrent transformer testsDisconnector and GIS switchgear testsGrounding system testsPower cable testsVoltage transformer testsInsulation diagnosis: dissolved gases (DGA) and temperature correctionTransformer TTR testTransformer winding resistanceTransformer insulation, PI and DARTransformer power factor and capacitanceTransformer excitation currentTransformer SFRATransformer leakage reactanceTap changer dynamic resistanceCalibration and uncertaintyPCB equipment: classification and deadlinesRETIE pre-inspectionTransformer test interpreterCircuit breaker testsTest budgetMaintenance plan and health indexSF6 inventory and leakage
Electrical studies
Lightning protectionShort circuit and per-unit systemGround fault and neutralShort-circuit checkerPower transformerTransformer noiseSafety clearancesArc flashGrounding resistancePower-frequency electric and magnetic fieldsCurrent split factor SfApproach boundariesSubstation configuration selectorBusbar stressesInsulation co-ordinationTRV and short-line faultGenerator circuit-breakerInductive load switchingSwitch-fuse combinationDisconnector and earthing switchMV switchgear and GIS specifierMV cable insulation levelInsulator strings: mechanical checkSeismic qualification of substation equipmentSurge protective device selectionElectric vehicle charging station
Yard equipment control
Circuit breaker controlDisconnector controlTransformer controlMV switchgear controlCapacitor bank controlAuxiliary services controlIEC 61850 bay controllerRecloser control
Industry and power quality
Motor startingHarmonic distortion THD and TDDEquipment harmonic emissionHarmonic emission allocationCapacitor bankBattery sizingRegulatory quality indicatorsCapacitor bank protectionSubstation DC systemsPower qualityGenerating sets to ISO 8528Lighting design to RETILAPControl valve Cv and Kv and affinity laws