Breaker failure 50BF and transfer trip

Enter the times of your protection, your breaker and your teleprotection channel: the tool calculates the minimum 50BF delay and the total backup clearing time with the transfer trip, compares it with the critical time and tells you what happens with a fault in the dead zone.

ABB REB670§ 3.6.3equation 46 of the backup delayCDEC-SING 1406-UIS-GT3§ 4.4detector and timersIEC 61850-7-4logical node RBRF

Example cases
Breaker failure 50BF and transfer trip

Only the basic data; the rest is taken with typical values.

ALearn

E1Protection and breaker
ms

From fault inception to the trip command, which also starts the 50BF.

ms

Opening plus arcing. Use the maximum measured in the timing test, not the catalogue value.

ms
ms
E250BF timer
ms

Your company's criterion: none of the sources consulted sets a value.

ms

150 ms is the ABB REB670 default and the value suggested by CDEC-SING.

E3Backup trip
ms
ms
ms

From the send command to the output of the remote receiver.

ms
ms
E4Critical time
ms

From the stability study, measured from fault inception.

E5Current detector
A
A

Minimum phase-to-phase or residual fault current, whichever applies.

A
E6Dead zone
ms

Use a decimal point. The calculation runs in your browser and updates as you type.

Minimum 50BF delay

— ms

Set delay t2

— ms

Total backup clearing

— ms

Dead zone

—

Breaker failure sequence
  • Failed breaker
  • Timer and channel
  • Healthy breaker
Everything is measured from fault inception. The dotted bar is what a healthy breaker would do: the detector resets before t2 expires. If the breaker does not open, t2 expires, the lockout relay 86 trips the adjacent breakers and the DTT opens the remote end.
Fault between the CT and the breaker
  • Power
  • Protection zone
A fault between the CT and the breaker lies inside the zone of one protection and beyond the reach of its breaker. With the breaker closed it is cleared by the 50BF, with its delay.

Step-by-step calculation

Loading these settings into a relay? We configure it remotely.

What it is for

Breaker failure protection (ANSI 50BF, logical node RBRF in IEC 61850) operates when a protection has ordered a breaker to open and current keeps flowing. After its delay it trips the adjacent breakers and, in a line bay, sends a direct transfer trip to the remote end.

That delay has two limits. If it is too short, the 50BF trips the bus even though the breaker opened correctly. If it is too long, the backup clearing exceeds the time the system tolerates without losing stability. This tool calculates both sides with the times of your installation.

How it is calculated

ABB REB670§ 3.6.3.2equation 46 and figure 69

Minimum backup trip delay

t2 ≥ t1 + tbreak + treset + tmargin

t1 is the retrip delay (zero without retrip), tbreak the maximum time in which the breaker interrupts the current, treset the maximum time in which the 50BF current detector recognises that the breaker opened, and tmargin a safety margin. The manual gives a typical t2 setting of 90 to 200 ms, with 150 ms by default, and a t1 of 0 to 5 ms.

ABB REB670§ 3.6.3.2critical time

Total backup clearing time

Tlocal = tprot + t2 + t86 + tbreak adjacent · Tremote = tprot + t2 + t86 + tchannel + tremote relay + tbreak remote

The total clearing time is the longer of the two. It is compared with the critical clearing time given by the stability study, measured from fault inception: the ABB REB670 manual states that the total clearing time is usually required to be shorter than that critical time.

CDEC-SING 1406-UIS-GT3§ 4.4current detector

Current detector setting

0.1 × In CT ≤ Ipickup ≤ 0.8 × Ifault min

The CDEC-SING technical guide (Chile) recommends that window for phase or residual faults. If the minimum fault is lower than 0.125 times the CT rated current, the window is empty: the auxiliary contact criterion (52a) is needed, which the same guide combines with the current criterion in an OR gate.

Dead zone and transfer trip

The dead zone is the section between the CT and the breaker. With the CT on the line side, the bus protection sees the fault and opens the breaker, but the line keeps feeding it from the other end: the remote end must be tripped. With the CT on the bus side, the line protection opens the breaker, but the bus keeps feeding the fault: the bus section must be tripped. With the breaker closed, those faults clear with the 50BF delay or by remote backup (ABB REB670 application manual, pp. 100-102).

With the breaker open, the same manual describes taking the CT measurement out of the bus zone after a time, for example 400 ms on cable or transformer feeders, or the longest reclosing dead time plus 300 ms on overhead lines, and enabling a fast overcurrent element, usually with a 40 ms delay, that trips only the remote end.

The trip to the remote end is direct: it opens without waiting for the remote protection to see the fault. In a permissive scheme such as PUTT the remote end trips only if its own element sees the fault, so it does not work as a breaker failure trip.

Limits of the calculation

  • The typical values come from a manufacturer (ABB REB670) and a system operator (CDEC-SING, Chile, installations above 100 kV). They are not a national standard. The IEEE C37.119 guide was not consulted for this tool.
  • The safety margin, the breaker, lockout relay and channel times and the critical time have no sourced typical value: they are data of your installation, of the breaker timing test and of the stability study. The example cases are illustrative.
  • It does not model each manufacturer's logic (2-out-of-4 criterion, multi-phase start, faulty breaker alarm) or the residual current of a saturated CT, which lengthens the detector reset.
  • It does not replace the stability study or the setting of your relay. It is a timing check.

Frequently asked questions

How is the 50BF delay calculated?

The backup trip delay t2 must be at least the sum of the retrip delay t1, the maximum break time of the breaker, the reset time of the current detector and a safety margin. It is equation 46 of the ABB REB670 application manual. With a healthy breaker the detector resets before t2 expires and there is no backup trip.

What is the typical breaker failure timer setting?

The ABB REB670 manual gives a typical setting of 90 to 200 ms, with 150 ms by default. The CDEC-SING technical guide (Chile) recommends 100 to 200 ms and suggests 150 ms when the breaker has no mechanical particularities. The value for your project comes from the calculation with the measured times of your breaker and relay.

Why does the 50BF of a line send a transfer trip?

Because if the line breaker does not open, the fault is still fed from the remote end. The 50BF opens the adjacent breakers in the substation and sends a direct transfer trip to the remote end, which opens without waiting for its own protection to see the fault.

We set your 50BF remotely

We review the times of your breaker and relay, calculate the delay and the backup trip destinations, and load the settings into the relay, without travelling.