Overcurrent and Breaker Failure for Capacitor Banks

ANSI 50BF

What overcurrent 50/51, 51N and breaker failure 50BF protect in a shunt capacitor bank, and how to avoid false trips on energization.

By Shadai García, CEO and protection engineer at Tiza Group.

source AQasource BQbbus52TCbankNeutral CT50/51 · 51N50BFenergization: peak through the neutralovercurrent in the bankbank breaker does not open50BF trips the adjacent onesEnergization: the current peakflows through the bank neutralOvercurrent: the 50/51 ordersthe bank breaker to openBreaker failure: the bankbreaker does not openThe 50BF trips the adjacentbreakers and de-energizes the bankChainEnergization50/51 · 51N52 failure50BFAdjacent© tizagrp.comsource AQasource BQbbus52TCbankNeutral CT50/51 · 51N50BFenergization: peak through the neutralovercurrent in the bankbank breaker does not open50BF trips the adjacent onesEnergization: the current peakflows through the bank neutralOvercurrent: the 50/51 ordersthe bank breaker to openBreaker failure: the bankbreaker does not openThe 50BF trips the adjacentbreakers and de-energizes the bankChainEnergization50/51 · 51N52 failure50BFAdjacent© tizagrp.com
Bank overcurrent and breaker failure: 50/51 and 51N, and the 50BF that trips the adjacent breakers. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Overcurrent protects the capacitor bank from large faults, but it does not see arcing or small internal faults. When a grounded-wye bank is energized, the charging current can approach the ground trip level and cause false trips. IEEE C37.99-2000 also describes breaker failure for the bank, with tripping of neighboring breakers after a delay, and the role of surge arresters.

Short answer

Overcurrent covers the large faults of a capacitor bank: phase to phase or phase to ground. It does not cover well the small faults inside the bank or arcing, which are the job of unbalance protection. When the bank is energized, the charging current can look like a ground fault. If the bank breaker does not open, breaker failure protection (50BF) isolates the bank by tripping the neighboring breakers.

IEEE C37.99-2000 deals with these points in clauses 7.2.1, 7.2.3, 7.2.6 and 7.2.7.

What overcurrent covers and what it does not

The standard separates two types of fault:

  • Major fault, such as phase to phase or phase to ground. It requires protection external to the bank: power fuses, breakers or circuit switchers with their relays. For the best protection, the relays are set as low and as fast as possible, with just enough delay not to trip on external system disturbances.
  • External arcing within the bank. Overcurrent is usually not sensitive to an arc in the bank and, if it detects it, it is normally very slow. Unbalance protection governs there. In large banks, the standard suggests redundant unbalance protection and an unbalance current or negative-sequence function.

In large extra-high-voltage banks, the standard shows two sets of three-phase 50/51 overcurrent relays, with instantaneous and short-time functions, as redundant protection against short circuits inside the bank.

The arc that overcurrent does not see is covered in external arcing and rack faults; the voltage protection that goes with it, in bank voltage protection (59, 59B and 27B).

Overcurrent points according to the standard

TopicIEEE C37.99-2000 criterion
Minimum pickup of inverse timeDesirable 135 % of rated phase current in grounded-wye banks and 125 % in ungrounded banks
InstantaneousIf used, it must be set high to ride through inrush and outrush transients
Relays with fundamental filterModern relays with a bandpass filter at fundamental frequency are not sensitive to inrush or outrush
Neutral 51N relay with low burdenReduces the high voltages at the current transformer secondary caused by high-frequency outrush current during an external fault
System not effectively grounded and ungrounded bankThe 51N is set to a low tap to detect and clear low-magnitude ground faults fast
Effectively grounded system and grounded-wye bankThe outrush current to an external fault does not usually operate the 51N, but the unbalanced bank load from that fault can make it pick up if set too low. Its trip is set above the capacitor phase current

These are references from the standard, not the setting of your relay. The real setting depends on your bank, your current transformers and your network.

Energization: the current that looks like a fault

Each time a large grounded-wye bank is energized, the momentary charging currents of the capacitors, in one phase and in the neutral, can approach the ground fault trip level. When a bank is already energized in parallel, those currents can be in the order of thousands of amperes.

The standard lists the possible consequences:

  • Spurious relay operations.
  • Relay failures.
  • Current transformer failures.
  • Energized substation fences.
  • Problems in the ground grid.

To limit the problem, the standard asks that the neutral connection between several banks not run through the ground grid. A single-point or peninsula ground should be used. The same transients also reach the current transformers and the control cables.

That current and its limits are in switching a capacitor bank, and its effect on CTs and relays, in switching transients in CTs, VTs and control circuits.

Bank breaker failure

If the bank switching device is a breaker or a circuit switcher, the standard contemplates a breaker failure scheme as local backup. If the device fails, the bank is isolated by tripping, after a delay, the adjacent breakers connected to it. In some cases a remote trip may be needed.

Bank breaker failure sequence
  1. Fault in the bank. The protective relay orders the bank breaker to trip
  2. The breaker does not open. Current continues and an overcurrent element confirms it
  3. Breaker failure starts. An auxiliary relay starts it and a delay runs
  4. Adjacent breakers trip. The bank is isolated from the system
  5. Remote trip if needed. Order to the remote end when local isolation is not enough

Two precautions from the standard:

  • Breaker failure detection is initiated with auxiliary relays. The usual schemes supervise the timer start with an overcurrent element, or supervise the timer output.
  • Those overcurrent elements must operate for all types of bank fault, including currents lower than rated. A phase level of 50 % of the normal rated bank current is generally considered adequate in grounded and ungrounded banks.

The standard also asks you to check the capacitive current switching capability of the adjacent breakers that will trip. That capability is explained in classes C1 and C2.

Surge arresters

Lightning and switching overvoltages are controlled with standard surge arresters. The bank absorbs overvoltages because, for sudden voltage changes, it behaves for an instant like a short circuit. Overvoltages around the bank are greatly reduced, but the protection is not complete. The overvoltage on the bank depends on the line length between the bank and the point where the transient is generated, and on the duration of the surge. More on the equipment in surge arrester.

Common mistakes

  • Expecting overcurrent to detect an arc inside the bank. Unbalance is there for that.
  • Setting the 51N too low in a grounded bank. The unbalanced load from an external fault makes it trip without a fault in the bank.
  • Joining the neutrals of several banks through the grid. It increases transients in the grid and in the secondaries.
  • Not checking the adjacent breakers. The breaker failure scheme depends on their ability to switch capacitive currents.

What we do at Tiza Group

In our remote relay configuration service we review the overcurrent, the 51N and the breaker failure protection of your bank and their coordination with the unbalance protection. We work remotely, worldwide. Contact us and we will quote the review.

References

  • IEEE Std C37.99-2000, IEEE Guide for the Protection of Shunt Capacitor Banks, clauses 7.2.1, 7.2.3, 7.2.6 and 7.2.7, Figure 6.

Frequently asked questions

Why does overcurrent not protect a capacitor bank from an internal arc?

Because it is not sensitive to an arc inside the bank and, if it detects anything, it does so late. IEEE C37.99-2000 assigns that task to unbalance protection and, in large banks, to redundant unbalance protection or to a negative-sequence current function.

Why does ground protection trip when a grounded-wye bank is energized?

Because the charging current of the capacitors, in one phase and in the neutral, can approach the ground fault trip level for an instant. If another bank is already energized in parallel, the current can be in the order of thousands of amperes.

What happens to the neighboring breakers when the bank breaker fails?

If the bank breaker does not open, breaker failure protection trips the adjacent breakers that feed the bank, after a delay. In some cases a remote trip is required. The standard reminds you to verify that those breakers can handle capacitive current switching.