ANSI device numbers table (IEEE C37.2)
The device function numbers 1 to 94 assigned by IEEE C37.2, the combinations that appear most often on protection drawings, and the matching IEC 61850 logical node where the mapping is well established.
IEEE C37.2device function numbersIEC 61850-7-4logical nodes
By number, name or logical node. A number on its own (“87”) finds that number and its combinations.
No device number matches your search.
Common combinations and suffixes
As they appear on protection one-line and three-line diagrams for substations and industry.
| Number | Name | Description | Logical node | Guide |
|---|---|---|---|---|
| 21N | Ground distance | Distance elements that measure the phase-to-ground loops with residual current compensation. | PDIS | See guide |
| 27/59 | Undervoltage and overvoltage | Pair of voltage functions in the same relay or bay. | PTUV / PTOV | See guide |
| 50BF | Breaker failure | If the breaker does not clear the fault within the set time, trips the adjacent breakers. | RBRF | |
| 50/51 | Phase instantaneous and time overcurrent | Combination of 50 and 51 in the same relay. | PIOC / PTOC | See guide |
| 50N/51N | Ground (residual) overcurrent | 50 and 51 applied to the residual current 3I0; also written 50/51N. | PIOC / PTOC | See guide |
| 50G/51G | Measured ground overcurrent | Overcurrent fed by a neutral CT or a core-balance CT, not by the sum of the phases. | PIOC / PTOC | |
| 51V | Voltage-restrained or voltage-controlled overcurrent | The inverse-time characteristic changes with voltage; used on generators (industry practice). | PVOC | See guide |
| 52a / 52b | Breaker auxiliary contacts | The «a» contact is closed when the breaker is closed; the «b» contact, when it is open. | ||
| 59N | Neutral or residual overvoltage | Measures the residual voltage 3V0 (broken delta or neutral) to detect ground faults. | PTOV | See guide |
| 67N | Directional ground overcurrent | Residual overcurrent that operates only in the set direction. | PTOC + RDIR | See guide |
| 74TC | Trip circuit supervision | Alarm on loss of continuity of the trip coil or trip circuit (industry practice). | ||
| 81O / 81U | Overfrequency and underfrequency | 81 with suffix O (over) or U (under) according to the operating direction. | PTOF / PTUF | See guide |
| 81R | Rate of change of frequency (ROCOF) | Operates on df/dt; used in load shedding and, in inverter-based generation, as one more input of a hybrid anti-islanding logic; many utilities do not accept it as the only method, and the main method is usually direct transfer trip. | PFRC | See guide |
| 87B | Bus differential | Differential with CTs in every bay connected to the bus. | PDIF | |
| 87G | Generator differential | Compares the currents on the neutral side and at the terminals of the stator. | PDIF | See guide |
| 87L | Line differential | Compares the currents at the line ends over a communications channel. | PDIF | |
| 87M | Motor differential | Stator differential of a medium-voltage motor. | PDIF | See guide |
| 87N | Restricted earth fault (REF) | Zero-sequence differential of a grounded-wye winding; also called 64REF. | PDIF | See guide |
| 87T | Transformer differential | Differential with ratio and vector group compensation and harmonic restraint. | PDIF |
Device function numbers 1 to 94
Numbers 95 to 99 are reserved by the standard for specific applications where no other number fits; each project defines their meaning.
| Number | Name | Description | Logical node | Guide |
|---|---|---|---|---|
| 1 | Master Element | Device that initiates operation, such as a control switch or a voltage relay. | ||
| 2 | Time-Delay Starting or Closing Relay | Introduces a time delay before a starting or closing sequence. | ||
| 3 | Checking or Interlocking Relay | Permits an operation only when the required position or status conditions are met. | ||
| 4 | Master Contactor | Makes and breaks the necessary control circuits, governed by the master element and the permissives. | ||
| 5 | Stopping Device | Shuts the equipment down and holds it out of operation, for example an emergency stop pushbutton. | ||
| 6 | Starting Circuit Breaker | Connects a machine to its source of starting voltage. | ||
| 7 | Rate of Change Relay | Operates when the rate of change of a quantity exceeds a set value (2008 edition). | ||
| 8 | Control Power Disconnecting Device | Switch or fuse that connects and disconnects the control power supply. | ||
| 9 | Reversing Device | Reverses the field or the phase sequence of a machine, for example the direction of rotation of a motor. | ||
| 10 | Unit Sequence Switch | Changes the order in which units are placed in or taken out of service. | ||
| 11 | Multifunction Device | Device that performs three or more functions, such as a multifunction numerical relay (2008 edition). | ||
| 12 | Overspeed Device | Operates when the machine exceeds its set speed. | ||
| 13 | Synchronous-Speed Device | Operates at or near synchronous speed. | ||
| 14 | Underspeed Device | Operates when the speed falls below the set value. | ||
| 15 | Speed or Frequency Matching Device | Matches the speed or frequency of a machine to that of another machine or the grid. | ||
| 16 | Data Communications Device | Switch, router, modem or network device that is part of the protection and control system (2008 edition). | ||
| 17 | Shunting or Discharge Switch | Opens or closes a shunting circuit, for example to discharge a capacitor. | ||
| 18 | Accelerating or Decelerating Device | Closes, or causes the closing of, the circuits that accelerate or brake a machine. | ||
| 19 | Starting-to-Running Transition Contactor | Transfers the machine from the starting connection to the running connection. | ||
| 20 | Electrically Operated Valve | Solenoid- or motor-operated valve in water, air, oil or gas circuits. | ||
| 21 | Distance Relay | Measures the impedance seen from the relay location and operates when the fault is inside its zone. | PDIS | |
| 22 | Equalizer Circuit Breaker | Controls the current-equalizing connections of machines in parallel. | ||
| 23 | Temperature Control Device | Maintains the temperature of an apparatus or enclosure, for example with a space heater. | ||
| 24 | Volts per Hertz Relay | Operates when the V/Hz ratio exceeds the set value; protects transformers and generators against overexcitation. | PVPH | See guide |
| 25 | Synchronizing or Synchronism-Check Device | Permits closing only when the voltage, angle and frequency on both sides are within limits. | RSYN | |
| 26 | Apparatus Thermal Device | Operates on the temperature of the protected apparatus, for example the oil or winding of a transformer. | See guide | |
| 27 | Undervoltage Relay | Operates when the voltage falls below the set value. | PTUV | |
| 28 | Flame Detector | Monitors the presence of the pilot or main flame, for example in a gas turbine or a boiler. | ||
| 29 | Isolating Contactor or Switch | Disconnects one circuit from another for emergency operation, maintenance or testing. | ||
| 30 | Annunciator Relay | Gives a visual indication that a protective or alarm device has operated. | ||
| 31 | Separate Excitation Device | Connects a circuit, such as the field of a machine, to a separate excitation source during starting. | ||
| 32 | Directional Power Relay | Operates when power flows in the set direction; on generators it detects motoring (reverse power). | PDOP / PDUP | |
| 33 | Position Switch | Opens or closes a contact when an apparatus or mechanism reaches a given position. | ||
| 34 | Master Sequence Device | Establishes or sets the operating sequence of the devices during starting, stopping or other switching operations. | ||
| 35 | Brush-Operating or Slip-Ring Short-Circuiting Device | Raises, lowers or shifts the brushes, or short-circuits the slip rings of a machine. | ||
| 36 | Polarity or Polarizing Voltage Device | Operates, or permits another device to operate, on a given polarity, or verifies the polarizing voltage. | ||
| 37 | Undercurrent or Underpower Relay | Operates when the current or power falls below the set value, for example on a pump running dry. | PTUC | |
| 38 | Bearing Protective Device | Operates on excessive bearing temperature or another associated mechanical condition. | ||
| 39 | Mechanical Condition Monitor | Operates on an abnormal mechanical condition other than the bearings, such as excessive vibration. | ||
| 40 | Field (Over/Under Excitation) Relay | Operates on an abnormally low value or loss of field current; protects the generator against loss of excitation. | PDIS (usual implementation) | See guide |
| 41 | Field Circuit Breaker | Applies or removes the field excitation of a machine. | ||
| 42 | Running Circuit Breaker | Connects a machine to its source of running voltage. | ||
| 43 | Manual Transfer or Selector Device | Manual selector that changes control circuits or operating modes, for example local or remote. | ||
| 44 | Unit Sequence Starting Relay | Starts the next available unit of a group when the preceding unit fails or is unavailable. | ||
| 45 | Abnormal Atmospheric Condition Monitor | Operates on an abnormal ambient condition, such as dangerous fumes, explosive gases or fire. | ||
| 46 | Reverse-Phase or Phase-Balance Current Relay | Operates on unbalanced or reverse-sequence phase currents; protects machines against negative sequence. | PTOC | |
| 47 | Phase-Sequence or Phase-Balance Voltage Relay | Operates when the voltage phase sequence is not the expected one or the voltages are unbalanced. | See guide | |
| 48 | Incomplete Sequence Relay | Returns the equipment to its normal position if a starting or operating sequence is not completed in time. | See guide | |
| 49 | Machine or Transformer Thermal Relay | Operates when the temperature (or its calculated thermal image) of a machine or transformer exceeds the limit. | PTTR | |
| 50 | Instantaneous Overcurrent Relay | Operates with no intentional time delay when the current exceeds the set value. | PIOC | See guide |
| 51 | AC Inverse Time Overcurrent Relay | Operates with a definite or inverse time characteristic with respect to the current. | PTOC | |
| 52 | AC Circuit Breaker | Power circuit breaker that closes and interrupts an AC circuit under normal and fault conditions. | XCBR | |
| 53 | Exciter or DC Generator Relay | Forces the build-up of the field of a DC machine during starting. | ||
| 54 | Turning Gear Engaging Device | Engages or disengages the turning gear (slow-roll mechanism) of a turbine shaft (2008 edition). | ||
| 55 | Power Factor Relay | Operates when the power factor leaves the set range. | ||
| 56 | Field Application Relay | Automatically controls the application of field excitation to a synchronous motor. | ||
| 57 | Short-Circuiting or Grounding Device | Short-circuits or grounds a circuit, manually or automatically. | ||
| 58 | Rectification Failure Relay | Operates on the failure of one or more elements of a power rectifier. | ||
| 59 | Overvoltage Relay | Operates when the voltage exceeds the set value. | PTOV | |
| 60 | Voltage or Current Balance Relay | Operates on a voltage or current difference between two circuits; used, for example, to detect a blown VT fuse. | ||
| 61 | Density Switch or Sensor | Operates on a gas density value, for example the SF6 of a circuit breaker (2008 edition). | ||
| 62 | Time-Delay Stopping or Opening Relay | Introduces a time delay in a stopping or opening sequence. | ||
| 63 | Pressure Switch | Operates at a given pressure or rate of change of pressure; includes the transformer sudden pressure relay. | ||
| 64 | Ground Detector Relay | Operates on failure of the insulation to ground of a machine, transformer or other apparatus. | PHIZ | See guide |
| 65 | Governor | Regulates the mechanical power of the prime mover, for example the opening of valves or wicket gates. | ||
| 66 | Notching or Jogging Device | Limits the number or frequency of successive starts of a machine. | ||
| 67 | AC Directional Overcurrent Relay | Operates on overcurrent flowing in a given direction. | PTOC + RDIR | See guide |
| 68 | Blocking or Out-of-Step Relay | Blocks a trip or a reclose under a given condition; the most common use is power swing blocking. | RPSB | See guide |
| 69 | Permissive Control Device | Permits or prevents a closing or operating action depending on its position. | ||
| 70 | Rheostat | Variable resistance in an electric circuit, manually or motor operated. | ||
| 71 | Liquid Level Switch | Operates at a given liquid level, for example the oil level in a transformer conservator. | ||
| 72 | DC Circuit Breaker | Closes and interrupts a DC power circuit under normal and fault conditions. | ||
| 73 | Load-Resistor Contactor | Connects or shorts a limiting, shunting or indicating resistor in a power circuit. | ||
| 74 | Alarm Relay | Operates a visual or audible alarm; with the TC suffix it is used for trip circuit supervision. | ||
| 75 | Position Changing Mechanism | Moves a main device from one position to another, for example the withdrawable truck of a switchgear cubicle. | ||
| 76 | DC Overcurrent Relay | Operates when the current in a DC circuit exceeds the set value. | ||
| 77 | Telemetering Device | Transmitter or receiver of remotely measured values. | ||
| 78 | Phase-Angle Measuring or Out-of-Step Protective Relay | Operates at a given phase angle between two quantities; used to trip on loss of synchronism. | PPAM | See guide |
| 79 | AC Reclosing Relay | Controls the automatic reclosing and lockout of an AC circuit breaker. | RREC | |
| 80 | Flow Switch | Operates at a given flow of a liquid or gas, or at a given rate of change of flow. | ||
| 81 | Frequency Relay | Operates when the frequency, or its rate of change, leaves the set values. | PTUF / PTOF | |
| 82 | DC Reclosing Relay | Controls the closing and automatic reclosing of a DC circuit breaker, generally in response to load. | ||
| 83 | Automatic Selective Control or Transfer Relay | Automatically selects between sources or conditions, or transfers the load between them. | ||
| 84 | Operating Mechanism | Complete electrical mechanism of a tap changer, regulator or similar apparatus. | ||
| 85 | Pilot Communications, Carrier or Pilot-Wire Relay | Teleprotection relay over power line carrier, pilot wire or another channel; receives or sends the signal to the remote end. | PSCH | |
| 86 | Lockout Relay | Trips and holds the equipment out of service until it is reset manually or electrically. | See guide | |
| 87 | Differential Protective Relay | Operates on the difference between the currents entering and leaving its protected zone. | PDIF | |
| 88 | Auxiliary Motor or Motor Generator | Drives auxiliary equipment such as pumps, fans or compressors. | ||
| 89 | Line Switch | Disconnect or isolating switch in a power circuit. | XSWI | |
| 90 | Regulating Device | Keeps a quantity, such as voltage, current or power, within limits; for example the tap changer control. | ||
| 91 | Voltage Directional Relay | Operates when the voltage across a breaker exceeds a value in a given direction. | ||
| 92 | Voltage and Power Directional Relay | Permits closing when the voltage difference is suitable and trips when power flows in the reverse direction. | ||
| 93 | Field-Changing Contactor | Changes the level of field excitation of a machine. | ||
| 94 | Tripping or Trip-Free Relay | Trips a circuit breaker, or prevents its immediate reclosing if it is closed onto a fault. | PTRC |
Most common suffixes
| N | Neutral (residual current or voltage) |
|---|---|
| G | Ground (direct measurement) or generator |
| BF | Breaker failure |
| T | Transformer |
| B | Bus, battery or blower |
| L | Line or logic |
| M | Motor or metering |
| P | Phase or pump |
| O / U | Over / under |
| X, Y, Z | Auxiliary relays |
| a / b | «a» contact: open with the device in its reference position (breaker open); «b» contact: closed in that position |
| POTT, PUTT, DCB, DCUB, DUTT | Teleprotection schemes (2008 edition acronyms) |
| SOTF | Switch onto fault |
How to read the table
IEEE C37.2 assigns a number to each device function and lets you qualify it with letter suffixes: 87T is transformer differential, 50BF is breaker failure and 51N is neutral time overcurrent. The names follow the 2008 edition of the standard, still current in its 2022 revision; numbers 7, 11, 16, 54 and 61 changed meaning in 2008, so older drawings may use them differently.
A modern numerical relay combines many functions, so on drawings it is shown with the list of numbers it has enabled or with device number 11 (multifunction device). In IEC 61850 each function is a logical node: PDIS for distance, PDIF for differential, PTOC for time overcurrent, PIOC for instantaneous overcurrent, RREC for reclosing. We show the logical node only when the mapping is the one used by the main manufacturers; each manufacturer adds its own prefixes (for example LEXPDIS for loss of excitation in ABB), and “usual implementation” means that IEC 61850-7-4 has no specific node for that function.
Some combinations, such as 81R, 51V, 21N or 74TC, are industry practice built on the suffixes of the standard, not numbers it assigns. Sources: IEEE C37.2 (official abstract at standards.ieee.org) and manufacturer reproductions and technical references; the full text of the standard is sold by IEEE.
Need these functions enabled and set in your relay? We configure them remotely.
We configure these functions in your relay
Our team enables and sets, remotely, the protection, control and communication functions of relays and recloser controls from the main manufacturers, including the IEC 61850 model. Tell us the make and model. On-site testing is available in Colombia, or elsewhere on request.