Substation Communication Network Testing: FAT and SAT

What is checked in a substation communication network: inventory, VLANs, redundancy, time sync, load, security, GOOSE, MMS and SCADA points.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

LAN ALAN B21BCUcenter1234567891Fiber: loss2Switch: configuration3VLAN and priority4Link outage (PRP)5Clock: accuracy6Load and storms7Firewall: rules8GOOSE between IEDs9Control center linkGOOSE received by the BCU:0 lostLAN A and LAN B healthylink 4 cut: LAN B carries oneach test leaves its own recordTestsDocumentsMediumConfigurationTimeFunctionsCenter© tizagrp.comLAN ALAN B21BCUcenter1234567891Fiber: loss2Switch: configuration3VLAN and priority4Link outage (PRP)5Clock: accuracy6Load and storms7Firewall: rules8GOOSE between IEDs9Control center linkGOOSE received by the BCU:0 lostLAN A and LAN B healthylink 4 cut: LAN B carries oneach test leaves its own recordTestsDocumentsMediumConfigurationTimeFunctionsCenter© tizagrp.com
Substation communication network testing. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

Testing a substation communication network confirms that what was installed matches the design and that the network still performs when something fails: inventory and ports, VLANs and filtering, redundancy switchover, time synchronization, behavior under load, basic security, GOOSE and MMS exchange between IEDs, and points to the control center. Part of it is done at the factory (FAT) and part on site (SAT).

Why test the network

In a substation with IEC 61850, the communication network carries GOOSE trips, interlocks, controls, measurements, time synchronization and, in a digital substation, the currents and voltages themselves as sampled values. A badly configured network does not always fail right away: it can work under normal conditions and fail when a link is cut, when a burst of events arrives during a fault or when a bay is added.

That is why the network is tested as one more device of the protection and control system, with its own acceptance criteria defined in the project specification. The substation network engineering guideline IEC TR 61850-90-4 devotes a chapter to these tests.

FAT and SAT

At the factory (FAT). The system is tested assembled at the factory or in the integrator’s lab: panels, IEDs, switches, clock and local SCADA. This is the time to find configuration errors, because fixing them costs less than on site. IEC 61850-4, the part on system and project management, covers quality and testing within the project life cycle.

On site (SAT). What was installed is tested: the real fiber, the switches in their panels, the clock with its antenna, the link to the control center and coexistence with the existing equipment. It repeats the essentials of the FAT and adds what only exists in the substation.

The general standards framework is summarized in standards for commissioning, FAT and SAT.

What is checked

The items are described in general terms; the acceptance values come from the project specification.

  1. Inventory and documentation. Each device, with its name, firmware and configuration, matches the drawings and the SCD. The ports in use are the documented ones and unused ports are disabled.
  2. Physical medium. Loss of each fiber link within the optical budget, and clean connectors.
  3. VLANs, priority and filtering. Each GOOSE and each sampled value stream reaches only the ports that need it, with its VLAN and priority. No IED receives traffic it should not.
  4. Redundancy. Links are cut and switches powered down one at a time. With PRP or HSR no message may be lost; with RSTP or MRP the reconvergence and its effect are measured.
  5. Time synchronization. All IEDs share the same reference with the required accuracy, and loss of the main clock or its antenna produces the expected alarms and switchover.
  6. Load and timing. With the network loaded (for example, simulating a burst of events), trip GOOSE messages still meet their transfer time and no sampled values are lost.
  7. Basic security. Default credentials changed, individual user accounts, unnecessary services disabled, firewall rules as designed and security logs working.
  8. GOOSE and MMS interoperability. Each GOOSE subscription works between IEDs from different manufacturers, with the right reaction to loss of the message; MMS reports reach the local SCADA and controls are executed.
  9. Points to the control center. Each point arrives with the right address, type, quality and time stamp, and controls are executed from the control center.
Usual order of network tests
  1. 01Documentation and inventoryWhat is installed matches the SCD and drawings
  2. 02Physical mediumFiber and connectors within the optical budget
  3. 03Network configurationVLANs, priority, filtering and basic security
  4. 04Time and redundancySynchronization, link and switch outages
  5. 05Functions over the networkGOOSE, MMS, sampled values and timing under load
  6. 06Control centerPoint-to-point and remote controls

Tools

The tests use traffic analyzers that decode GOOSE, MMS, sampled values and PTP, relay test sets with an IEC 61850 interface to publish and subscribe messages, MMS client and control center simulators, and optical power meters or OTDRs for the fiber. To review the addresses and subscriptions of the SCD before going to site you can use our free IEC 61850 SCL viewer.

Errors that show up in testing

  • GOOSE messages reaching every IED because of missing VLANs or filtering, the origin of a traffic storm.
  • Redundancy that works with one outage but not with another, because of a badly closed ring or a wrong bridge priority.
  • An IED that does not take time from the clock everyone thinks it does, or uses a different time format.
  • GOOSE subscriptions that fail because of configuration revision differences between the SCD and the IED, a case of GOOSE that does not arrive or arrives late.
  • Points to the control center with the wrong address or scaling.
  • Switch configurations that differ from the documented ones, because of changes made on site and not recorded.

After the tests

When the SAT closes, there is a record of each test with its result, the final SCD and a backup of the configuration of each switch, clock and firewall. That baseline is what makes it possible, years later, to know whether something changed and to repeat the tests when the substation is extended. In an extension it is not enough to test the new bay: the redundancy, load and timing tests of the whole network are repeated, because the new devices change the traffic and topology that all bays share.

We help with your tests

At Tiza Group we carry out FAT and SAT of protection, control and communication systems in medium, high and extra-high voltage substations and in industrial plants, in Colombia or elsewhere on request, including network, redundancy, timing and control center tests, and end-to-end tests. The network design and its test plan are part of our communications engineering service, done remotely. Contact us.

References

  • IEC TR 61850-90-4:2020, Network engineering guidelines.
  • IEC 61850-4, edition 2.1 (2020), System and project management.
  • IEC 61850-10, Conformance testing.
  • IEC 61850-5, Communication requirements for functions and device models.
  • IEC 62439-3, Parallel Redundancy Protocol (PRP) and High-availability Seamless Redundancy (HSR).

Frequently asked questions

What is the difference between a communications FAT and SAT?

The FAT tests the system assembled at the factory or in a lab, with the real or representative IEDs and switches, before it is shipped to the substation. The SAT tests what was installed, with the real wiring, fiber, clock with its antenna and link to the control center. The SAT repeats the essentials of the FAT and adds what only exists on site.

How is network redundancy tested?

By cutting links and powering down switches one at a time while the critical traffic is monitored. With PRP or HSR no GOOSE message and no sample may be lost; with RSTP or MRP the reconvergence time is measured and it is confirmed that it does not affect the functions that depend on the network.

Does IEC 61850 conformance testing replace network testing on site?

No. Conformance to IEC 61850-10 is certified by a test lab for an IED or tool model. Site tests verify the actual system: the configuration, the network and the interaction between devices from different manufacturers in that substation.