Capacitor bank unbalance protection 60: how it works

ANSI 60IEC 61850: PTOC

How capacitor bank unbalance protection works: neutral current and voltage, voltage differential, inherent unbalance compensation and alarm and trip steps.

By Shadai García, CEO and protection engineer at Tiza Group.

MV busQ1Y1Y260ungrounded double wyeunbalancealarmtripunbalanceU on healthy ones0123healthy bank: no neutral currentone element failsneutral-to-neutral current: alarma second element failstrip level exceeded: Q1 opensunits replaced and bank closedn = failed elements · ZCAP: the bankIEC 61850PTOC (unbalance)PTRCGOOSEXCBR© tizagrp.comMV busQ1Y1Y260ungrounded double wyeunbalancealarmtripunbalanceU on healthy ones0123healthy bank: no neutral currentone element failsneutral-to-neutral current: alarma second element failstrip level exceeded: Q1 opensunits replaced and bank closedn = failed elements · ZCAP: the bankIEC 61850PTOC (unbalance)PTRCGOOSEXCBR© tizagrp.com
Capacitor bank unbalance (60): double wye and staircase. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

Unbalance protection (ANSI 60) detects failed elements or units inside a capacitor bank by comparing currents or voltages that are practically equal while the bank is healthy: the current between the neutrals of a double wye, the neutral voltage, or the voltage at a tap point of each phase. It alarms on the first failures and trips the bank before the healthy units are subjected to an overvoltage higher than they can withstand.

What unbalance protection protects

A capacitor bank is made of many units in series and in parallel, and each unit of many elements. When an element fails, the capacitance of its group changes and the voltage is shared differently: the remaining elements in that group see more voltage. If they keep failing, the overvoltage grows until it causes a cascading failure and, in the worst case, the rupture of a unit with an internal arc.

Unbalance protection protects the bank units against that progressive overvoltage. It alarms on the first failures, so replacement can be scheduled, and trips the bank breaker before the healthy units exceed their limit. It is the main protection of the bank; overcurrent and overvoltage cover other risks.

  • ANSI/IEEE C37.2: 60, voltage or current balance relay.
  • IEC 61850: there is no specific logical node for bank unbalance; it is modeled on overcurrent or overvoltage classes (PTOC, PTOV) and the bank itself is represented by ZCAP.
  • IEC 60617: no dedicated symbol.

Where it is applied

BankLVMVHV and EHVIndustryUsual scheme
Grounded wyeNot applicableYesYesUncommonNeutral current or voltage differential
Ungrounded wyeAutomatic banks with contactorsYesUncommonYesNeutral voltage
Ungrounded double wyeNoYesYesLarge banksCurrent between neutrals
H-bridgeNoUncommonYesNoCurrent in the center branch of each phase
Harmonic filtersNoYesYesYesSame as the bank, with the reactor tuning

At low voltage, banks are protected by fuses and by the controller devices, and element-level unbalance protection is rarely applied. The connection and its variants are explained in capacitor bank.

Operating principle

All schemes look for the same thing: a quantity that is almost zero with the bank healthy and that grows with each failure.

  • Current between neutrals (double wye): the bank is split into two equal wyes with their neutrals tied through a CT. When healthy, no current flows; when an element fails in one wye, current appears through the CT.
  • Neutral voltage (ungrounded wye): a VT between neutral and ground measures the neutral shift caused by an unbalanced leg.
  • Neutral current (grounded wye): a CT in the neutral-to-ground connection.
  • Voltage differential: in each phase, the voltage at a tap point of the bank is compared with the scaled bus voltage. It is used in large grounded banks and identifies the faulted phase.
  • H-bridge: a CT in the center branch of each phase measures the unbalance between its two halves.

Inherent unbalance compensation. A small signal already exists with the bank healthy. The relay measures it and subtracts it as a phasor; some schemes also compensate for system voltage unbalance.

Internally fused, externally fused or fuseless. With external fuses, each failure removes a complete unit and the signal per failure is large. With internal fuses only one element is removed and the signal is small, so the scheme must be more sensitive and the inherent unbalance compensation more careful. In fuseless banks, the failed element is shorted and its voltage is shared by the other series groups of the string; the signal per failure is clear, but the bank tolerates fewer failures. The fuse type defines how many steps fit before the trip.

The characteristic

The characteristic is best understood as a staircase: on the horizontal axis, the number of failed elements or units in the most affected group; on the vertical axis, the unbalance signal and the overvoltage on the healthy elements. Each failure climbs one step.

  • Alarm: at the step that corresponds to the first failure, or to the number considered acceptable.
  • Trip: at the step where the overvoltage on the healthy elements would reach the limit the unit can withstand, with margin.
  • Time delay: short, to avoid operating on switching transients, and coordinated with the fuses.
From failed element to trip
  1. Element failure. The capacitance of its group changes
  2. Voltage redistribution. Healthy elements in the group see more voltage
  3. Unbalance signal. Neutral current or voltage, or voltage differential
  4. Alarm. First steps, to schedule the replacement
  5. Trip. Before healthy elements exceed their overvoltage limit

Setting criteria

The step calculation depends on the bank configuration, the number of units and elements and the fuse type. The general criteria of IEEE C37.99 are:

  • Calculate the unbalance signal and the overvoltage on the healthy elements for each number of failures.
  • Set the trip to act before the unit overvoltage limit is exceeded, and the alarm on the first failures.
  • Check that the first failure gives a signal clearly larger than the inherent unbalance.
  • Review coordination with the fuses.

You can estimate the behavior with our free capacitor bank tool. The calculation for a real bank is part of a protection coordination study.

Interaction with other functions

  • Bank overcurrent 50/51: covers faults in the connections and between phases, not the elements.
  • Overvoltage 59: protects the bank against high system voltage. See overvoltage 59.
  • Undervoltage 27: opens the bank on loss of voltage, so it is not re-energized while still charged.
  • Automatic control: the controller must not reconnect the bank before the discharge time. See automatic capacitor bank control.
  • Breaker failure 50BF: initiated by the unbalance trip.

How each manufacturer implements it

  • Siemens SIPROTEC (DIGSI): capacitor bank protection functions with current and voltage unbalance.
  • SEL (AcSELerator QuickSet): capacitor bank relays with unbalance elements, compensation and faulted-phase identification.
  • Hitachi Energy and ABB Relion (PCM600): in the 615 series, current unbalance is CUBPTOC; in the 670 series, dedicated capacitor bank functions.
  • GE Vernova Multilin (EnerVista): bank unbalance elements with compensation.
  • Schneider MiCOM and Easergy: current unbalance or neutral voltage stages.

IEC 61850 logical node

The bank is represented by ZCAP and its breaker by XCBR. Unbalance is modeled on PTOC (current) or PTOV (voltage), with manufacturer-specific names such as CUBPTOC in the ABB 615. Alarm and trip go through PTRC and reach XCBR by GOOSE or by a hardwired output.

How it is tested

In general the test verifies:

  • The capacitance of each unit and each branch, and the inherent unbalance, before energizing.
  • The ratio, polarity and insulation of the neutral CT or VT.
  • With secondary injection, the alarm and trip thresholds, the times and the compensation.
  • After energizing, the actual signal with the bank healthy and its compensation.

Typical mistakes

  • Not compensating the inherent unbalance, or compensating it with a failed bank.
  • Steps calculated for another fuse type or another configuration.
  • Neutral CT ratio too high, giving no useful signal on the first failure.
  • Replacing units without measuring capacitance, which changes the inherent unbalance.
  • Repeating the compensation after a trip without finding the failed unit.

Did your bank trip on unbalance, or do you need its steps reviewed? At Tiza Group we review events and settings remotely, worldwide. See our remote relay configuration service or contact us.

References

  • IEEE C37.99, Guide for the Protection of Shunt Capacitor Banks: unbalance schemes and step calculation.
  • IEEE 18, Standard for Shunt Power Capacitors: unit limits.
  • IEC 60871-1, Shunt capacitors for a.c. power systems having a rated voltage above 1 000 V – Part 1: General.
  • IEEE C37.2, Standard for Electrical Power System Device Function Numbers, Acronyms, and Contact Designations: device 60.
  • IEC 61850-7-4, Compatible logical node classes and data object classes: ZCAP, PTOC, PTOV and PTRC nodes.

Frequently asked questions

Why is a capacitor bank protected by unbalance and not only by overcurrent?

Because the failure of one element changes the total bank current very little, but it redistributes the voltage among the remaining elements. Overcurrent does not notice it; unbalance does. If it goes undetected, failures cascade and end in a major fault inside the bank.

What is the inherent unbalance of a bank?

It is the unbalance signal present with the bank healthy, caused by small capacitance differences between units and by the unbalance of the system voltage. The relay measures it during commissioning and subtracts it, so that the setting responds only to new failures.

Does the protection change if the bank is internally fused, externally fused or fuseless?

Yes. With external fuses, each failure removes a complete unit; with internal fuses, one element is removed; in a fuseless bank, the failed element is shorted and its voltage is shared by the others. Each case changes the signal size per failure and the number of failures the bank tolerates before tripping.