What a Substation Engineering Design Includes

Before hiring a substation design: basic and detailed engineering, input data, deliverables, utility approval and warning signs when comparing offers.

By Shadai García, CEO and protection engineer at Tiza Group.

clientoperatorUPME / XMinspectionreadingstudiesfilingreviewsettingsapprovalconstructionverificationstaged processfeasibility and utility technical standardsingle-line, grounding grid, short circuit and meteringfiling of the signed packagereview: 7 or 15 working dayssettings: 30 working daysnew revisiondesign approvalconstruction per the designthe inspector compares works and designreadingstudiesfilingreviewsettingsapprovalconstructionverificationgridkWhmeas.52loaddeadlines for distribution-system usersPartiesCustomerUtilityUPME / XMCompliance inspection© tizagrp.comclientoperatorUPME / XMinspectionreadingstudiesfilingreviewsettingsapprovalconstructionverificationstaged processfeasibility and utility technical standardsingle-line, grounding grid, short circuit and meteringfiling of the signed packagereview: 7 or 15 working dayssettings: 30 working daysnew revisiondesign approvalconstruction per the designthe inspector compares works and designreadingstudiesfilingreviewsettingsapprovalconstructionverificationgridkWhmeas.52loaddeadlines for distribution-system usersPartiesCustomerUtilityUPME / XMCompliance inspection© tizagrp.com
Drawing and design requirements for the utility. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

A substation engineering design brings together primary engineering (single-line diagram, yard, equipment, grounding and lightning protection), secondary engineering (protection, control, metering, panels and station service), communications engineering and the studies that support them. Local electrical codes require a complete design for every substation, and whoever grants the connection, the utility or the transmission owner, reviews and approves it before construction.

What a substation engineering design is

The engineering design is the set of calculations, drawings, specifications and lists that define a substation before it is built. It tells the buyer which equipment to order, the manufacturer how to build the panels, the installer where everything goes, and the utility that the installation is safe and does not harm its system.

Electrical codes in most countries require a design for every substation, and the utility asks for it before it grants the connection. The topics of a detailed design usually include risk analysis, lightning risk, insulation coordination, short-circuit and ground fault levels, grounding, mechanical calculation of structures, single-line diagrams, construction drawings, specifications and safety clearances. The designer states in the design report which topics do not apply and why. Which standards govern depends on the country and the utility; IEC 61936-1 and IEEE 80 are common references.

This guide is for anyone about to hire a design: what it must include, what information you need to provide, what you should receive and how it is approved.

The four parts of the design

PartWhat it definesTypical deliverables
Primary engineeringPower system: configuration, equipment, yard, grounding, lightning protectionSingle-line diagram, plan and sections, ground grid, equipment specifications
Secondary engineeringProtection, control, metering and station serviceSchematics, three-line diagrams, wiring, terminal blocks, panels, signal lists
Communications engineeringSubstation network, control center link, teleprotection, time, cybersecurityNetwork architecture, switch and gateway specifications, SCADA lists
StudiesThe calculations that support all of the aboveShort circuit, protection coordination, load flow, depending on the case

The four depend on each other. The short-circuit current sets the rating of the breakers and the grid design; the protection scheme defines how many cores the current transformers need; the communications network depends on which signals travel by GOOSE. That is why it is best for one team to do them, or for someone to coordinate the interfaces.

Basic engineering and detailed engineering

Projects talk about two stages:

  • Basic engineering. It fixes the big decisions: the busbar configuration (from single bus to breaker-and-a-half), the single-line diagram, the general layout, the voltage levels and the main equipment. It is used to estimate costs, request the utility’s connection concept or tender the project.
  • Detailed engineering. It develops everything needed to buy, manufacture and build: calculation reports, construction drawings, point-to-point wiring, panel drawings, specifications and bills of material.

Some local codes also use the term “basic design” for a reduced version reserved for very small installations. A substation needs the detailed design.

What information you need to provide

The quality of the design depends on the input information. Have ready:

  • The feasibility response or connection concept, with the connection point and the short-circuit level given by the utility.
  • The utility’s technical standard or the transmission owner’s requirements.
  • The site survey and the soil study, and the soil resistivity if it has already been measured.
  • In expansions: updated drawings, single-line diagram, terminal block lists, nameplate data and photographs of the equipment that stays.
  • The preferred or required relay brand, and the control center requirements.
  • The expected load or generation and its growth.

What does not exist is surveyed in the field. The rest of the design can be done from the designer’s office.

Which deliverables to ask for

  • Calculation reports covering the items required by the applicable code, those that do not apply and why.
  • Single-line diagram with ratios and classes of instrument transformers and protection functions.
  • Physical layout drawings, ground grid and lightning protection.
  • Schematics, three-line diagrams, wiring and terminal blocks consistent with the single-line diagram.
  • Technical specifications of each device and panel, ready to quote.
  • Studies: short circuit and protection coordination, at the very least.
  • Lists of cables, materials and signals.
  • Revision control: each drawing with its version and the list of changes.

How the design is approved

On a distribution system, the utility reviews the design against its technical standard and the local regulation. Many regulators require utilities to publish their technical rules and set review times for the study or design, and give the user a fixed period to answer any comments. The detail is in drawing and design requirements for the utility.

On a transmission system, the grid code usually sets the order: connection agreement, the user’s design and submission to the transmission owner of designs, calculation reports, specifications and drawings. These typically include the list of standards, single-line and elementary diagrams, interlocks, protection schemes with their setting criteria, and telecommunications schemes. The transmission owner reviews and approves them within a set time, counted from when the documentation is complete. Equipment is purchased only after approval.

After that come construction, the inspection and certification required by the local code, in which the inspection body checks that what was built matches the design, and commissioning.

From design to commissioning
  1. Basic engineering. Configuration, single-line diagram, layout and main equipment
  2. Detailed engineering. Calculation reports, construction drawings, wiring and specifications
  3. Approval. The utility or the transmission owner reviews the design
  4. Purchase and construction. Equipment is bought after approval
  5. Inspection and certification. The inspection body checks that what was built matches the design
  6. Commissioning. Testing and energization

Warning signs when comparing offers

  • “Complete design” without a list of deliverables. A serious offer says which drawings, reports and specifications it delivers.
  • No short-circuit study. Without it you cannot verify the equipment ratings or calculate the grid.
  • Ground grid without measured resistivity. With an assumed value, the real step and touch voltages cannot be verified.
  • Primary and secondary without coordination. If different teams do them, ask who answers for the interfaces.
  • No one handles the utility’s comments. Returns are normal; define who resolves them and whether they are included.
  • Drawings without revision control. The installers end up working on an old version.
  • A designer who has never commissioned. Wiring and scheme errors show up in the tests.

We design your substation

Our team does primary engineering, secondary engineering, communications engineering and studies for medium, high and extra-high voltage substations and for industry. The work is done remotely from our office in Bogotá, for clients worldwide, adapted to your local code and your utility’s requirements. See the engineering design and studies service and send us the scope through contact; we will propose a plan.

References

  • IEC 61936-1:2021, Power installations exceeding 1 kV AC and 1.5 kV DC – Part 1: AC.
  • IEEE Std 80, IEEE Guide for Safety in AC Substation Grounding.
  • The electrical code and the utility or transmission owner requirements that apply to the project.

Frequently asked questions

What is the difference between basic and detailed engineering?

Basic engineering fixes the big decisions: configuration, single-line diagram, general layout and main equipment. Detailed engineering develops everything needed to buy, manufacture and build: calculations, construction drawings, wiring, panels, specifications and lists. A substation needs detailed design; a reduced design is for small installations.

Who approves a substation design?

Whoever grants the connection. For a distribution connection, the utility reviews it against its published technical standard and the local regulation. For a transmission connection, the grid code usually requires the user to submit designs, calculation reports, specifications and drawings to the transmission owner for approval.

Can a substation design be done remotely?

Yes, in large part. With existing drawings, survey data, nameplate data, photographs and the utility's requirements, the engineering is done in the office. A visit is needed when information is missing that exists only in the field, such as soil resistivity or wiring without drawings.