SAS specification: what the tender should require

What a substation automation system specification must define: architecture, availability, protocols, signals, cybersecurity, FAT and SAT, deliverables.

By Shadai García, electrical engineer, founder and CEO of Tiza Group. Reviewed by the Tiza Group engineering team · .

control center104 / DNP3station busHMIgatewayclockstationprocess bus21BCUbayMU52 IEDprocess52control centerstationbayprocessGOOSEMMS104 / DNP3steady state: SV, PTP and reports on changefault: trip by GOOSE on the process busthe event goes up to the HMI over MMSand over 104 or DNP3 to the control centerSV and PTP: continuous process bus trafficLevelsSV · PTPProtectionMMS · GOOSE104 / DNP3Center© tizagrp.comcontrol center104 / DNP3station busHMIgatewayclockstationprocess bus21BCUbayMU52 IEDprocess52control centerstationbayprocessGOOSEMMS104 / DNP3steady state: SV, PTP and reports on changefault: trip by GOOSE on the process busthe event goes up to the HMI over MMSand over 104 or DNP3 to the control centerSV and PTP: continuous process bus trafficLevelsSV · PTPProtectionMMS · GOOSE104 / DNP3Center© tizagrp.com
Substation communication architecture: levels, buses and protocols. Location in the system, operating principle and IEC 61850. Illustrative: actual values come from the nameplate and the manufacturer's manual.
Short answer

A good substation automation system (SAS) specification defines functions and results, not brands: architecture and levels, availability and redundancy, protocols inside the substation and to the control center, signal list, time synchronization, cybersecurity, FAT and SAT, documentation and the configuration files to be delivered. What the tender does not require, the supplier does not include.

Why the specification decides the outcome

In an automation project, most commissioning problems originate in the specification: signals nobody asked for, redundancy nobody planned, tests that were not in the scope, configuration files the contractor has no obligation to deliver. What the tender does not require, the supplier does not price; and what is not priced is argued about on site. In an existing substation, the tender for a SAS retrofit adds the survey of what is installed and the coexistence with the old system.

CIGRE devoted its Technical Brochure 329, Guidelines for specification and evaluation of substation automation systems, to this subject, with the aim of helping prepare specifications for substation automation systems and compare the bids. This guide summarizes, at a general level, what a tender should cover; the final text depends on each project and on the utility.

What the tender must define

TopicWhat to defineTypical error if missing
Scope and boundariesWhich bays, which equipment, where the SAS ends and SCADA or the DCS beginsSignals left «between two contracts»
ArchitectureProcess, bay and station levels; station bus and, if applicable, process busBids that cannot be compared
FunctionsProtection, control, interlocking, sequences, recording, metering, per bayImplicit functions nobody included
Availability and redundancyWhich single failure the system must tolerate: network, gateway, HMI, clockA single point of failure that blinds the control center
ProtocolsIEC 61850 inside the substation, required edition; protocol and profile to each control centerUnplanned gateways, incompatible editions
SignalsSignal list or, at least, the template per bay typeIncomplete lists that grow on site
TimeTime source, synchronization protocol and required accuracyScrambled sequences of events
CybersecurityRequirements for access, segmentation, logging, patching and hardeningEquipment installed with no way to comply with the owner’s policy
Environment and compatibilityIEC 61850-3 or IEEE 1613 requirements for network and station equipmentOffice switches or computers in the substation
TestingContent of the FAT, SAT and point-to-point tests, and who witnesses themTests cut short on site for lack of time
Documentation and filesWhat is delivered, in which format and with which versionThe owner cannot extend the system without the original supplier
Training and supportFor operation and for engineering, and the warranty periodTotal dependence on the contractor

Architecture, redundancy and network

The specification sets the levels and the failure each one must tolerate. Writing «redundant system» is not enough: it has to say what happens if a switch, a gateway, the HMI or the clock fails, and how quickly communication recovers. For the substation network, that translates into the topology, the redundancy protocol (for example PRP or HSR) and traffic separation. The technical basis is in substation communication network.

Protocols and engineering

For IEC 61850 it is worth requiring:

  • the required edition and how coexistence with devices of another edition will be handled, according to IEC 61850 Edition 1, 2 and 2.1;
  • IED conformance certificates per IEC 61850-10 and their conformance statements;
  • the use of GOOSE for interlocking or tripping, if desired;
  • the SCD as a deliverable, together with the engineering tool and who will hold its license.

Toward the control center, the protocol and its profile (data types, events, synchronization, link redundancy) are normally set by the utility. The specification transcribes them and defines who does the mapping in the gateway.

Cybersecurity

The specification must ask for verifiable requirements, not statements: individual user authentication, roles, security event logging, disabled ports and services, segmentation between the substation network and the outside, and the way updates are applied. IEC 62443 (ISA/IEC 62443) gives the framework for the system and its components, and IEC 62351 for the protocols. In North America the owner’s NERC CIP obligations also shape these requirements. We develop the subject in IEC 62443 in substations.

FAT and SAT

The tender defines the content of the tests and their acceptance criteria:

Test stages worth specifying
  1. 01Type and routine testsCertificates for each device according to its standard
  2. 02System FATIntegrated system at the factory: functions, communications, HMI, gateway and redundancy
  3. 03SATInstalled system, with its final wiring and network
  4. 04Point-to-point testsEvery signal from the yard to the HMI and the control center
  5. 05Commissioning and energizationOn-load tests and final verification before operation

Each stage must have a procedure approved before it starts, with acceptance criteria and a list of who approves the results. The applicable standards (IEC 61850-4, IEC 62381 as a model, CIGRE TB 637) are in standards for commissioning, FAT and SAT, and the on-site process in substation commissioning.

Documentation and files to be delivered

Require explicitly:

  • the final SCD and the files of each IED;
  • settings and logic of relays and controllers, in native format and in a readable format;
  • gateway, HMI and network configuration;
  • the final signal list;
  • updated as-built drawings;
  • approved test records.

And define who maintains that information afterwards: IED and SCD configuration management keeps the system from going out of date with the first change.

How to evaluate the bids

A point-by-point compliance table, with each requirement of the tender and the bidder’s answer, allows bids to be compared objectively. It is also worth asking for the proposed architecture as a diagram, the equipment list with its certificates and experience in similar integrations.

We help you specify and execute

At Tiza Group we configure and test automation systems in medium, high and extra-high voltage substations and in industry, and we know first-hand what fails when the specification falls short. For secondary engineering and the specification, see secondary engineering; for on-site integration, control, protection and communications configuration, in Colombia, or elsewhere on request.

References

  • CIGRE, Technical Brochure 329, Guidelines for specification and evaluation of substation automation systems, WG B5.18, 2007.
  • CIGRE, Technical Brochure 637, Acceptance, commissioning and field testing techniques for protection and automation systems, 2015.
  • IEC 61850-3, -4, -6 and -10.
  • IEC 62443, security for industrial automation and control systems.
  • IEC 62351, communication security for power systems.
  • IEEE 1613, environmental and testing requirements for communications networking devices in electric power substations.

Frequently asked questions

Should the specification name relay brands?

In general it is better not to: functions, standards and performance requirements are specified. There are reasonable exceptions, such as requiring compatibility with the brand already installed in an extension or with the utility's standard, and in that case the tender justifies it.

Which standard governs a SAS specification?

There is no single standard. IEC 61850 covers communication and its Part 4 project management; CIGRE published a guide for specifying and evaluating a SAS (TB 329); and each utility usually has its own technical specification, which prevails where it applies.

Which files must be delivered at the end of the project?

At a minimum, the final SCD and the files of each IED, the settings and logic of relays and controllers, the gateway and HMI configuration, the network configuration, the final signal list and the approved test records. All in versions consistent with what is installed.