IEEE 80: Safety in Substation Grounding

What IEEE Std 80-2013 is, which substations it covers, how it is organized and what limits the safety guide for AC substation grounding has.

By Shadai García, CEO and protection engineer at Tiza Group.

line52to the substationstructureground faultsoilburied gridIg to remote earthtouchstepnormal service: grid at zero potentialground fault on the structureIg enters the grid: GPR = Ig · Rgtouch voltage: hand and feetstep voltage: at the grid edge52 clears: GPR returns to zeroVsurface potentialGPREtEpEtEpdashed lines: IEEE 80 limitsStudySoil resistivityIg y RgGPR and profileTouch and step (IEEE 80)© tizagrp.comline52to the substationstructureground faultsoilburied gridIg to remote earthtouchstepnormal service: grid at zero potentialground fault on the structureIg enters the grid: GPR = Ig · Rgtouch voltage: hand and feetstep voltage: at the grid edge52 clears: GPR returns to zeroVsurface potentialGPREtEpEtEpdashed lines: IEEE 80 limitsStudySoil resistivityIg y RgGPR and profileTouch and step (IEEE 80)© tizagrp.com
Grounding grid: ground fault, potential rise and touch and step voltages. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

IEEE Std 80-2013 is the guide for safety in AC substation grounding. It sets the limits on the potential difference a person can withstand during a fault and offers a grid design procedure to stay within them. It is a guide, not a closed recipe.

Short answer. IEEE Std 80-2013, Guide for Safety in AC Substation Grounding, is an international guide for designing the grounding of an AC substation with one main goal: that no person receives, during a ground fault, more current through the body than they can withstand. It does not stop at setting a grid resistance. It starts from the human body, defines which potential differences are tolerable and proposes a procedure so that the grid does not exceed them.

What it covers and what it leaves out

The scope (clause 1.1) is outdoor AC substations, conventional or gas-insulated. It includes distribution, transmission and generating-plant substations. With due care, its methods also work for the indoor parts of those substations or for fully enclosed substations.

DC substation problems and the quantitative analysis of lightning are left out. The guide focuses on power frequencies of 50 Hz to 60 Hz. Even so, a grounding system designed with it offers some protection against steep-front waves entering the substation.

What it was written for

Clause 1.2 lists its purposes:

  1. To establish, as a design basis, the limits of potential difference that can exist during a fault between points that the human body can touch.
  2. To review grounding practices with attention to safety and to define design criteria.
  3. To give a procedure for designing practical grounding systems with those criteria.
  4. To develop analytical methods that help to understand and solve typical voltage gradient problems.
  5. To provide reference cases for comparing the guide’s equations with commercial software.

One idea that organizes the whole guide

Clause 4.1 sets two objectives for a safe grounding system. The first is to carry currents into the earth, in normal operation and in a fault, without exceeding equipment limits or affecting service continuity. The second is to reduce the risk that a person near the grounded facilities is exposed to a critical electric shock.

To achieve this, the guide separates two interacting systems. The intentional system is the buried electrodes. The accidental system is the one temporarily formed when a person is exposed to a potential gradient. A direct consequence: a low grid resistance, by itself, does not guarantee safety. The guide says so plainly, because there is no simple relation between the resistance of the system and the maximum current that could flow through a person.

How it is organized

The standard groups its content in three blocks, plus annexes:

BlockChaptersWhat it covers
Safety criteria1 to 8Definitions, electric shock, tolerable body current, the accidental circuit and the tolerable step and touch voltages
Practical design aspects9 to 13Design considerations, GIS substations, conductors and connections, soil characteristics, soil structure and soil model
Evaluation procedures14 to 20Grid resistance, maximum grid current, design procedure, special areas, construction, field measurements and physical scale models

The annexes include the bibliography, worked calculation examples, the current division analysis, simplified equations for step and mesh voltages, the equivalent uniform soil, a parametric analysis, grounding methods for high-voltage substations with a grounded neutral and the reference cases (benchmarks).

The guides in the series, by topic

Each IEEE 80 topic has its own guide. This list groups them in the order in which they are usually consulted during a design.

Safety of people.

Soil and grid resistance.

Design and calculation.

Special cases, construction and verification.

Field measurement of resistivity and grid resistance is covered in detail in the IEEE 81 guide and in the ground resistance test guide. The effects of step and touch voltage on an installation in service are in step and touch voltage and in substation ground grid.

The design method at a glance

Chapter 16 brings the procedure together. The site data that weigh most are the maximum grid current, the duration of the fault and of the shock, the soil resistivity, the surface layer resistivity and the grid geometry. The area occupied by the grid is the most influential geometric factor in its resistance: the larger the area, the lower the resistance and the lower the potential rise.

The procedure compares the voltages that the grid produces with those that the body tolerates. Since in design the mesh voltage is usually the worst possible touch inside the substation, the guide takes it as the reference and then checks the step voltage. If the grid does not comply, it is modified (spacing, conductor length, depth, rods) and the check is repeated. The guide specifies the steps and the equations; this article does not reproduce them because they are applied with each project’s own data.

What you can and cannot do with the guide

The guide gives the criterion and the equations. It does not replace the judgment of the designer. Its equations assume uniform soil and defined geometries, and the standard itself warns when more precise methods are advisable, for example with highly non-uniform soils, irregularly shaped grids or large areas.

Nor does it replace the local code. The local code and the utility’s requirements set requirements of their own, which are verified together with it. For a first calculation with your data you can use our free grounding resistance tool, which applies the method of the guide to a rectangular grid.

We carry out your grounding study

At Tiza Group we design the grounding of medium, high and extra-high voltage substations and of industrial plants. We measure or receive the soil resistivity, calculate the grid current with your short-circuit study and verify the step and touch voltages against the tolerable limits. See the engineering design and studies service or write to us through contact.

References

  • IEEE Std 80-2013, IEEE Guide for Safety in AC Substation Grounding: clauses 1.1 and 1.2 (scope and purpose), 4.1 (basic problem), 16 (grounding system design) and annexes A to H.
  • IEEE Std 81, IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System.

Frequently asked questions

Is IEEE 80 mandatory?

It is a recommended practice guide. It becomes enforceable when a code, the utility or the project contract cites it. Confirm which document applies to your project before fixing the design criterion.

Does the guide apply to indoor or gas-insulated substations?

Yes. It covers conventional and gas-insulated (GIS) substations for distribution, transmission and generating plants. For fully enclosed substations it states that its methods also apply, with due care.

What does IEEE 80 not cover?

It does not deal with the specific problems of DC substations, nor does it give a quantitative analysis of the effects of lightning. It is aimed at frequencies of 50 Hz to 60 Hz.