How IEC 60071-2 applies to distribution substations up to 36 kV: which lightning level to choose, and what changes with a transformer or cable connection.

By Shadai García, CEO and protection engineer at Tiza Group.

A Overhead line to transformeroverhead linetransformerswitchgearLV cables: ≥ 0.05 µF per phaseB Overhead line to cableswitchgearsurge arrestercableincidentreflectedtransmitted (lower)reflections at the ends raise the voltage in the cableLower lightning impulse values sufficeif: a) no overhead line, b) transformerand 0.05 µF per phase on LV, c)line arrives directly with arrestersOther cases or high security:higher lightning impulse valuesWith cable: higher values and arrestersat the line-cable junction; withwood poles, also at the cable entryThe transformer transfers waveselectrostatically and electromagneticallyChainNetwork connectionTransformer or cableArresterLightning impulse© tizagrp.comA Overhead line to transformeroverhead linetransformerswitchgearLV cables: ≥ 0.05 µF per phaseB Overhead line to cableswitchgearsurge arrestercableincidentreflectedtransmitted (lower)reflections at the ends raise the voltage in the cableLower lightning impulse values sufficeif: a) no overhead line, b) transformerand 0.05 µF per phase on LV, c)line arrives directly with arrestersOther cases or high security:higher lightning impulse valuesWith cable: higher values and arrestersat the line-cable junction; withwood poles, also at the cable entryThe transformer transfers waveselectrostatically and electromagneticallyChainNetwork connectionTransformer or cableArresterLightning impulse© tizagrp.com
Insulation coordination up to 36 kV, IEC 60071-2 clause 7.2.1: overhead line to transformer and to cable. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Up to a highest voltage for equipment of 36 kV, IEC 60071-1 specifies only power-frequency and lightning impulse withstand voltages, and phase-to-earth switching voltages are covered by the power-frequency one. The standard's lower lightning impulse values are suitable if the installation is not connected to overhead lines, is connected only through a transformer with cable of at least 0.05 µF per phase, or has adequate surge arresters. In all other cases the higher values are used.

Short answer

In distribution substations up to a highest voltage for equipment (Um) of 36 kV, IEC 60071-1 specifies only power-frequency and lightning impulse withstand voltages. Phase-to-earth switching voltages are covered by the power-frequency one; phase-to-phase switching voltages must be considered when choosing one of the two. The lower lightning impulse values are suitable for three types of installation, and in all other cases the higher ones are used. When there is an overhead line in between, the transformer or cable that separates it from the equipment matters. This guide follows clause 7.1 and clauses 7.2.1 to 7.2.1.2 of IEC 60071-2, 1996 edition.

What is verified in this range

Range I of IEC 60071-1 covers from above 1 kV up to 245 kV, in distribution and transmission. Within it, up to 36 kV, coordination is resolved with two voltages: short-duration power frequency and lightning impulse. The standard voltages are in the rated voltage of switchgear and their verification in the rated insulation level.

As a general guide, the required phase-to-earth switching voltages can be assumed to be covered by the standard power-frequency withstand voltage. The phase-to-phase ones must be considered when choosing the lightning impulse or the power-frequency voltage.

When the lower lightning impulse values are suitable

As long as phase-to-phase slow-front overvoltages are covered, equipment designed for the lower values of table 2 of IEC 60071-1 may be suitable in three cases:

CaseCondition
aIndustrial systems and installations not connected to overhead lines
bConnected to overhead lines only through transformers, if the cables on the low-voltage side of the transformer total at least 0.05 µF of capacitance to earth per phase
cConnected directly to overhead lines, with adequate surge arrester protection

In case b, the cables may not reach that capacitance. Capacitors are then added next to the transformer terminals, on the switchgear side, until the total reaches 0.05 µF per phase. In any other case, or when a very high degree of security is needed, the higher lightning impulse value is used.

Which lightning impulse value to choose up to 36 kV
  • Is the installation connected to an overhead line?
    • No: The lower values of table 2 of IEC 60071-1 may be suitable
    • Yes: How is it connected to the line?
      • Through a transformer: Do the low-voltage cables total 0.05 µF per phase or more, with capacitors if needed?
        • Yes: The lower values may be suitable
        • No: Use the higher values
      • Directly: Are there adequate surge arresters?
        • Yes: The lower values may be suitable
        • No: Use the higher values
      • Through a cable: In general, higher values and surge arresters at the line-cable junction

If high security is required, the standard calls for the higher value in all cases.

Equipment connected to an overhead line through a transformer

Equipment connected to the low-voltage side of a transformer fed from an overhead line does not directly receive the line’s lightning or switching overvoltages. However, the transformer transfers them from the high-voltage winding to the low-voltage winding electrostatically and electromagnetically, and those overvoltages must enter the procedure, with protection if needed.

Annex E of IEC 60071-2 explains the transfer modes. Temporary overvoltage can appear on a secondary with isolated neutral when an earth fault unbalances the primary voltages. Capacitive transfer is usually critical only from high to low voltage, and the winding capacitance is supplied by the manufacturer. Inductive transfer is normally the most important, and to estimate its magnitude direct measurements give more reliable information than simplified equations. The standard itself indicates that its equations serve for a rough estimate.

Equipment connected to an overhead line through a cable

Here the coordination must protect the substation and the cable. When a lightning wave travelling along the line reaches the cable, it splits into a reflected and a transmitted wave, and the transmitted amplitude is much smaller than that of the incident wave. But successive reflections at each end of the cable usually raise the voltage along the cable above that initial value.

For that reason, in general:

  • the higher values of lightning impulse from table 2 of IEC 60071-1 are chosen;
  • surge arresters are installed at the line-cable junction;
  • with wood poles and a single line connected to the substation, additional surge arresters may be needed where the cable enters the substation.

Wood poles raise the amplitude of the incoming waves, because the line’s insulation to earth is high. For the equipment, see the surge arrester and power cables.

What stresses the substation may see

IEC 60071-2 describes the voltage stresses in a substation in its clause 7.1:

  • Operating voltage: equal to the highest system voltage, on all parts.
  • Temporary overvoltage: an earth fault on the load side affects an entire phase equally. Load rejection may affect only the parts between the breaker and the transformer.
  • Slow front: from energization or re-energization of lines and from faults and their clearing.
  • Fast front: lightning can appear throughout the substation, with different amplitudes depending on the distance to the surge arrester. Fast-front switching overvoltages appear only in the section being switched.

What not to do

  • Do not choose the lower lightning impulse value just because the voltage level is medium voltage: it depends on how the installation is connected to the network.
  • Do not forget the low-voltage cables when evaluating the transformer connection: their capacitance to earth is a condition of the standard.
  • Do not ignore reflections at the cable ends: they raise the voltage inside it above the initial transmitted wave.
  • Do not mix this case with the low-voltage surge protective devices of a plant, which follow other rules.

To go further, see Insulation coordination in substations from 52 to 245 kV and Overvoltages transferred through a transformer.

When to call us

Choosing the lightning impulse, locating the surge arresters and reviewing the cable connection are substation engineering decisions. At Tiza Group we make them within engineering design and studies, remotely and worldwide, and we verify the result with testing and commissioning in Colombia, or elsewhere on request. Write to us and we will send you a quote.

References

  • IEC 60071-2:1996, Insulation co-ordination, Part 2: Application guide, clauses 7.1, 7.2.1, 7.2.1.1 and 7.2.1.2, and annex E.
  • IEC 60071-1:2006, Insulation co-ordination, Part 1: Definitions, principles and rules, table 2.

Frequently asked questions

Which lightning impulse level is chosen in a medium-voltage substation?

It depends on how it is connected to the network. IEC 60071-2:1996 (clause 7.2.1) accepts the lower values of table 2 of IEC 60071-1 if the installation is not connected to overhead lines, if it is connected only through a transformer with sufficient capacitance to earth on the low-voltage side, or if it is connected directly and has adequate surge arresters. In all other cases, or if a very high degree of security is required, the higher values are used.

What happens when a lightning overvoltage reaches a cable?

The wave splits into a reflected and a transmitted wave, with the transmitted amplitude greatly reduced. But successive reflections at the cable ends usually raise the voltage along the cable above that initial value. That is why the higher lightning impulse values are chosen and surge arresters are installed at the line-cable junction.

Does a substation fed through a transformer from an overhead line receive the line overvoltages?

Not directly. But the transformer transfers overvoltages from the high-voltage side to the low-voltage side electrostatically and electromagnetically, and those overvoltages must be considered in the coordination, with protection if necessary. Annex E of IEC 60071-2 gives expressions to estimate them.