Tiza Group

Home / Guides / Industry and automation

Electrical Substation Maintenance: What It Includes

What maintenance of an industrial or utility substation covers: equipment, maintenance types, what local codes expect and what to get at the end.

By Shadai García, CEO and protection engineer at Tiza Group.

utility MV servicedisconnector52 MTMT/BTDyn11temporary ground52 BTLV busS1S2bank50/5150N~=charger123456plant in serviceopening and temporary grounding1 transformer: insulation, TTR and oil2 breaker and switchgear: contacts and timing3 CT: ratio, polarity and saturation4 relay: secondary injection and trip5 batteries and charger: capacity6 ground grid: resistancetemporary ground removalre-energization in stagesplant in servicein serviceopening and grounding1 transformer2 breaker and switchgear3 CT4 relay5 batteries6 groundingground removalre-energizationteach test with the asset de-energizedStoppagePlanSwitchingTestsReportRe-energization© tizagrp.comutility MV servicedisconnector52 MTMT/BTDyn11temporary ground52 BTLV busS1S2bank50/5150N~=charger123456plant in serviceopening and temporary grounding1 transformer: insulation, TTR and oil2 breaker and switchgear: contacts and timing3 CT: ratio, polarity and saturation4 relay: secondary injection and trip5 batteries and charger: capacity6 ground grid: resistancetemporary ground removalre-energization in stagesplant in servicein serviceopening and grounding1 transformer2 breaker and switchgear3 CT4 relay5 batteries6 groundingground removalre-energizationteach test with the asset de-energizedStoppagePlanSwitchingTestsReportRe-energization© tizagrp.com
Plant substation maintenance: where each asset is tested. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

Substation maintenance is the set of inspections, tests and corrections that keep the transformer, switchgear and breakers, instrument transformers, relays, DC system and grounding reliable. Local electrical codes and utility requirements usually call for a maintenance plan with the interval for each piece of equipment and for keeping records; the frequency depends on the type of substation, its condition and the environment.

What substation maintenance is

A substation, whether in an industrial plant or on a utility network, is maintained so that it keeps doing two things: delivering power without interruption and clearing a fault when one occurs. The first depends on the condition of the transformer, switchgear, cables and connections. The second depends on the relays, current and voltage transformers, breakers and the DC trip supply working together on the day they are needed.

That is why good maintenance is not limited to cleaning and tightening. It measures, compares against previous tests and checks that the complete protection chain operates. Compact installations of this kind are also called unit substations or transformer stations; the principle is the same.

What the standards expect

Maintenance obligations come from the electrical code that applies at the site and from the utility’s requirements when the substation connects to its network. They usually ask for periodic maintenance, a plan that covers every piece of equipment and the interval at which each is serviced, records of each activity, and a maintenance manual from the manufacturer or builder. The interval depends on the type of substation and the environmental conditions.

In the United States, and as a reference in many plants across the Americas, NFPA 70B moved in its 2023 edition from recommended practice to standard (Standard for Electrical Equipment Maintenance). Its approach is that frequency is set according to the condition of the equipment, its criticality and the environment where it operates. The NETA maintenance testing specifications (ANSI/NETA MTS) are the usual reference for acceptance values.

What equipment is checked

EquipmentWhat is looked forTypical tests
TransformerInsulation, moisture, hot spots, condition of the oil and accessoriesInsulation resistance, ratio, winding resistance, power factor, oil analysis
Switchgear and breakersContacts, mechanism, vacuum or SF6 chamber, interlocksContact resistance, operating times, vacuum integrity, withstand voltage
Instrument transformers (CT and VT)Ratio, polarity, insulation, secondary burdenRatio, polarity, excitation, insulation
Protective relaysThat they trip with the current settings and to the correct breakerSecondary injection, actual trip, event review
DC systemBatteries, charger, ground leakageBattery capacity, charger check
Grounding and surge arrestersContinuity and resistance; condition of the arrestersGround resistance, leakage current
Low-voltage boardsConnections, breakers, trip unitsInspection, thermography, trip tests

Primary equipment tests are explained one by one in testing of primary substation equipment. For switchgear, see medium-voltage switchgear, and for the DC system, battery bank maintenance.

Preventive, predictive and corrective

  • Preventive: on planned dates, almost always with the substation de-energized. This is when electrical tests, insulator cleaning and mechanism checks are done.
  • Predictive: with the equipment in service. Dissolved gas analysis in oil, thermography, online partial discharge and transformer monitoring show how condition evolves and allow a decision on when to shut down. See what an infrared thermography survey detects and how to read the report.
  • Corrective: after a fault or a finding. Here it matters not only to repair, but to understand the cause so that it does not repeat.

In a plant, a power outage costs production. Preventive maintenance is planned for the plant shutdown, with the test list, measuring equipment and personnel ready before the main breaker is opened.

How the outage is prepared

Work on a de-energized substation lasts a few hours or a few days, and whatever was not prepared beforehand is lost. A well-planned outage defines:

  • The scope per piece of equipment: which tests are done on each transformer, switchgear panel, relay and battery bank, and which acceptance criterion will be used.
  • Switching and lockout: opening sequence, temporary grounding points, lockout and tagout, and who authorizes each step. If the incoming supply belongs to the utility, its opening is coordinated with it.
  • Backup power: which critical loads stay supplied, by emergency generator or transfer, and for how long.
  • Spares: gaskets, fuses, contacts or batteries worth having on site in case a test finds a defect.
  • Re-energization: a checklist to remove temporary grounds, close in the correct order and confirm that each protection is enabled.

What is often forgotten

  • The protections. The transformer gets cleaned, but nobody checks that the relay trips with the current settings. A relay with a depleted backup battery, a changed setting or an open trip coil is only discovered on the day of the fault. Trip circuit supervision helps, but does not replace the test.
  • Documented settings. Many plants have no copy of their relay settings. Downloading and saving them at every maintenance avoids losing them if the device fails.
  • Comparison with the previous test. A single value says little; the trend says a lot. A report without the previous results loses half its value.
  • Grounding. It is measured at construction and then forgotten, although the soil and the connections change.

What maintenance should deliver

At the end you should receive a report with the condition of each piece of equipment, the measured results against the acceptance criteria and against the previous test, findings ordered by priority, recommendations and the current protection settings. That report is also the maintenance record that codes and utilities ask for. If you are going to contract this work, review what to ask for in a protection test report.

What IEC 61869 says

The installation and maintenance of an instrument transformer are explained in a guide of their own. More on the maintenance and inspection duties of a transformation center in Spain in inspection and maintenance of transformation centers.

How we help

At Tiza Group our team performs primary equipment tests, protection tests by secondary injection and commissioning in medium-, high- and extra-high-voltage substations and in industrial plants. We prepare the scope for the plant shutdown with you, carry out the tests and deliver the report with findings and recommendations. Field work is in Colombia, or elsewhere on request.

See our testing and commissioning, or write to us to prepare the maintenance of your substation.

References

  • NFPA 70B-2023, Standard for Electrical Equipment Maintenance.
  • ANSI/NETA MTS, Standard for Maintenance Testing Specifications for Electrical Power Equipment and Systems.
  • IEEE C57.152, Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers, Regulators, and Reactors.

Frequently asked questions

How often should an electrical substation be maintained?

There is no single interval. Codes and utilities usually ask that each substation have a plan with the interval for each piece of equipment, according to the type of substation and the environmental conditions, and NFPA 70B ties frequency to the condition, criticality and surroundings of the equipment. The manufacturer's recommendations and the test history set the real interval.

What is the difference between preventive and predictive maintenance in a substation?

Preventive maintenance is done on planned dates, normally with the substation de-energized: cleaning, tightening connections, electrical and protection tests. Predictive maintenance monitors condition with the equipment in service, such as oil analysis, thermography or online monitoring, to decide when to intervene.

Is maintenance of a plant substation mandatory?

In general, yes. Local electrical codes and the utility's requirements ask for periodic maintenance of power, control, protection, alarm and communication equipment by qualified personnel, with records that the authority having jurisdiction can request. The exact obligations are those of the code that applies at your site.

WhatsApp