Disconnector Position: Locking and Indication

What IEC 62271-102 requires to secure the open or closed position of a disconnector, indicate it visibly and signal it with auxiliary contacts.

By Shadai García, CEO and protection engineer at Tiza Group.

operatingmechanismforcelimitermechanicallockmoving contactsvisualindicatorpower chain:passes through the limiterlocked openpoles reach positioncommon signal and locked closedpole 1 in positionpole 2 in positionpole 3 in positionsignalcommonThe common signal requires all threepoles in position: auxiliary contactstied to the indicatorChainMechanismLimiterMoving contactsIndicatorCommon signal© tizagrp.comoperatingmechanismforcelimitermechanicallockmoving contactsvisualindicatorpower chain:passes through the limiterlocked openpoles reach positioncommon signal and locked closedpole 1 in positionpole 2 in positionpole 3 in positionsignalcommonThe common signal requires all threepoles in position: auxiliary contactstied to the indicatorChainMechanismLimiterMoving contactsIndicatorCommon signal© tizagrp.com
Disconnector position, locking and indication (IEC 62271-102): power chain, indicator chain and common signal of the three poles. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

IEC 62271-102 requires that a disconnector not leave its open or closed position through gravity, wind, vibration or accidental contact, that it allow temporary mechanical locking in both positions and that its position can be known: through a visible isolating distance or a reliable visual indicator attached to each moving contact. The electrical signal may be given only once the contacts have reached their position.

Short answer

A disconnector is operated with no appreciable current and, when open, provides the isolating distance between two parts of the installation. Its position therefore cannot be an assumption. IEC 62271-102 (2001 edition with Amendment 1:2011 and Amendment 2:2013) gathers three requirements in clause 5.104:

RequirementClauseWhat it asks
Secure the position5.104.1The disconnector does not leave open or closed by itself and allows temporary mechanical locking
Indicate the position5.104.3.1The position must be knowable, with a visible distance or a reliable indicator
Signal the position5.104.3.2The electrical signal from auxiliary contacts is faithful to the position of all poles

Securing the position: clause 5.104.1

Disconnectors and earthing switches, with their mechanisms, must be designed so that they cannot leave their open or closed position through:

  • Gravity.
  • Wind pressure.
  • Vibration.
  • Reasonable shocks.
  • Accidental contact with the operating-system rods.

They must also allow temporary mechanical locking, both open and closed, for safety, for example during maintenance. This last requirement does not apply to hot-stick operated equipment.

For motor-operated mechanisms, clause 5.104.2 also requires a means of manual operation. When the manual device, for example a crank, is engaged, the motor’s control energy must be safely interrupted.

Indicating the position: clause 5.104.3.1

It must be possible to know the position of the disconnector. For the open position, the standard considers this met in either of two cases:

  • The isolating distance or gap is visible.
  • The position of each moving contact that ensures that distance is shown by a reliable visual device.

The standard notes that, in some countries, the disconnector design is such that the isolating distance is visible.

The indicator is considered reliable when its kinematic chain, from the moving contacts to the indicator, meets these conditions:

  • It is a continuous mechanical connection, so that the drive is positive.
  • It has enough mechanical strength to pass the tests of Annex A.
  • The force-limiting device, if any, is not part of that chain.

The indicator may be marked directly on a mechanical part of the power chain.

If all poles are mechanically coupled to operate as one unit, a single common indicator is allowed.

Signaling the position: clause 5.104.3.2

The electrical signal from auxiliary contacts follows these rules:

  • Neither the indication nor the signaling of closed or open may be given until the moving contacts have reached their closed or open position and clause 5.104.1 is met.
  • A signal common to all poles is issued only if all poles have a position conforming to the above.

The definition of closed position (3.6.110) adds that the predetermined continuity means that the contacts are fully engaged to carry the rated normal current and the rated short-circuit current, as applicable.

How the open-position indication is met
  • Is the isolating distance or gap visible?
    • Yes: Meets clause 5.104.3.1 with no need for an indicator
    • No: Does each moving contact have a visual indicator attached through a continuous mechanical chain?
      • Yes: Meets it if the indicator passes the tests of Annex A
      • No: Does not meet clause 5.104.3.1

How the position indicator is tested

Clause 6.105 applies when a position indicator is used instead of a visible isolating distance, and the details are in Annex A. It is an optional type test. It has two parts:

  • Test of the power kinematic chain. The moving contact of the disconnector is blocked in the closed position, and the force or torque that the mechanism transmits when trying to operate is measured. Then a force of 1.5 times the measured value is applied to the chain, downstream of the opening point. In manual mechanisms, the force applied to the handle can be up to 750 N.
  • Test of the indicator kinematic chain. It is made by blocking the indicator instead of the moving contact. No test is required if the indicator is marked directly on a part of the power chain. Nor is one required if the part between the two chains is inside an enclosure with a minimum degree of protection IP2XC that passed a 2 J impact test.

The test is passed if, at the end, the indicator still correctly shows the position of the moving contact and the indicator chain has no permanent deformation.

In the routine test, during the mechanical operations it is verified that the indicator correctly marks the open and closed positions.

Effect on other tests

  • Dielectric tests in the open position are made with the minimum isolating distance at which the indicator or signaling can still give the open position, or with the minimum compatible with the locks of clause 5.104, whichever is smaller.
  • When the design requires adjusting the indicator or signaling, the adjustment is made according to the instruction manual. No deviation of these devices is allowed in the dielectric and short-circuit tests.
  • The mechanical endurance test verifies the specified operation of the auxiliary contacts and position indicators.

The interlocking that uses these signals is explained in mechanical and electrical interlocking, and its applications in the busbar disconnector and the line disconnector. The operation is covered in the motor-operated mechanism. The mechanical endurance of the disconnector is covered in M0, M1 and M2 classes of the disconnector. You can practice the order of operations with the interlocking table.

What not to do

  • Do not take a position signal into an interlocking logic without checking that it comes from auxiliary contacts that follow the actual position of the contacts.
  • Do not assume that the «open» signal and the «closed» signal are the negation of each other: the standard requires that each signal be given only when the contacts have reached their position. There is an intermediate state with neither.
  • Do not remove or adjust the indicator without following the manufacturer’s manual: the standard requires no deviation in the tests.
  • Do not rely on an indicator whose connection to the contacts passes through a force-limiting device.

What to request from the manufacturer

  • The way the open position is indicated: visible distance or indicator, with its Annex A test report.
  • The mechanical locks provided for the open and closed positions.
  • The auxiliary contacts available and their relation to the position of each pole.

When to call us

At Tiza Group we test disconnectors in AIS and GIS substations and verify that the actual position of the contacts matches the local indication and the signal that reaches the control system and the interlocks. Field work is done in Colombia, or elsewhere on request. See our testing and commissioning services or write to us with your substation data and we will send a quotation.

References

  • IEC 62271-102, High-voltage switchgear and controlgear - Part 102: Alternating current disconnectors and earthing switches, 2001 edition with Amendment 1:2011 and Amendment 2:2013, clauses 3.6.110, 5.12, 5.104.1 to 5.104.3.2, 6.102.3, 6.105 and Annex A.

Frequently asked questions

How must the open position of a disconnector be indicated?

Clause 5.104.3.1 of IEC 62271-102 accepts two ways: the isolating distance or gap is visible, or the position of each moving contact that ensures that distance is shown by a reliable visual device.

When may the position signal be sent through auxiliary contacts?

Only when the moving contacts have reached their closed or open position and the disconnector cannot leave it through gravity, wind or other stress. In addition, a signal common to all poles is given only if all poles are in the signaled position.

What makes a position indicator reliable?

That its kinematic chain is a continuous mechanical connection with positive drive, strong enough to pass the tests of Annex A, and that the force-limiting device, if any, is not part of that chain.