FERC Order No. 2023 changed how transmission providers study generator interconnection requests. Requests are studied together in clusters, projects must show readiness through deposits and site control, and late studies carry penalties for the transmission provider. Each operator files its own version of the rules, so the details depend on the region.
Short answer
Order No. 2023 of the Federal Energy Regulatory Commission (FERC) is the rule that changed how most US transmission providers study generator interconnection requests. Instead of reviewing one request at a time in the order they arrived, the provider studies a group of requests together in a cluster. A request advances if the developer proves it is ready, which is the first-ready, first-served idea. The order was issued on 28 July 2023, and Order No. 2023-A followed on rehearing on 21 March 2024. For the general stages see interconnection study stages explained. For where the order sits among US rules, see the US electrical codes and grid interconnection guide.
What the order changed
The main changes for a developer, in plain terms:
- Cluster study instead of serial review. Requests received in the same window are studied together. A cluster restudy follows when requests withdraw or change. A facilities study then defines the work and its cost. The older feasibility step is not part of the pro forma process.
- Readiness requirements. The developer provides site control, study deposits and commercial readiness deposits that grow as the project advances. A request that cannot show readiness does not proceed.
- Withdrawal penalties. A project that leaves after others have been studied around it can be charged, because its exit forces a restudy.
- Deadlines for the provider. The transmission provider faces penalties if it misses study deadlines, which gives developers some schedule certainty.
- Affected systems. Procedures were added so that neighbouring systems, which may be affected by the plant, study it in a defined way and on a defined schedule.
- Technical requirements. The order added requirements for non-synchronous generation such as ride-through, and for accurate models. See NERC PRC-029 and IEEE 2800 model and simulation requirements for the related standards.
- Other items. The order also covers co-located resources, such as solar with storage on one request, surplus interconnection service and consideration of alternative transmission technologies.
Who must follow it
Transmission providers under FERC jurisdiction file a compliance version of the rules in their tariff. The regional operators, independent system operators and regional transmission organizations (ISO/RTO), then run their own processes: see the guides on CAISO, PJM and MISO. The Electric Reliability Council of Texas (ERCOT) is outside this framework, and its process is covered in the ERCOT guide. Distribution connections are state and utility matters; California is explained in the Rule 21 guide. Because compliance details differ, the operator’s current tariff decides, not this summary.
Why clusters change project risk
In a serial queue, a project paid for the upgrades its own request triggered. In a cluster, the cost of a shared upgrade is spread over the requests that need it, and a withdrawal by one request changes the numbers for the others. That is why the order pairs clusters with readiness deposits: it tries to keep speculative requests out of the study. For the developer, the practical effect is that the quality of your own request matters, and so does the behavior of the other requests near you, which you cannot control.
Worked example (illustrative)
The values are assumptions, not data from a real cluster.
Assumptions. A cluster has 10 requests totaling 1,200 MW. All are tested against one 230 kV line with 80 MW of headroom. The average distribution factor on the line, meaning the share of output that flows through it, is 0.08.
Step 1. Flow added by the full cluster. 1,200 × 0.08 = 96 MW.
Step 2. Compare with headroom. 96 MW is above the 80 MW headroom, so the study finds an overload of 16 MW and assigns an upgrade.
Step 3. Withdrawals. Four requests with 400 MW withdraw before the restudy. The cluster is now 800 MW.
Step 4. Flow after the restudy. 800 × 0.08 = 64 MW, which is under the 80 MW headroom.
Step 5. Result. The overload disappears and the upgrade is no longer needed in this simplified case. The remaining projects benefit, and the projects that withdrew may owe penalties under the tariff. The reverse case also exists: when a large project withdraws late, the remaining projects can see a larger share of an upgrade. Real studies use many lines and many contingencies, so one line is only a teaching case.
Checklist for the engineer
- Identify the operator, its compliance version of the rules and the open study window.
- Confirm site control, deposits and readiness evidence before the deadline.
- Check that technical data and models are complete and match the equipment.
- List the milestones where the project can withdraw and what each exit costs.
- Prepare for restudies: keep data current and respond to the provider on time.
- Check whether neighbouring systems may need an affected system study.
- Have the engineer of record review any study result before a decision.
Legal frame
This summary is general orientation and does not replace the order, the pro forma procedures or an operator’s tariff. Tiza does not sign, seal or certify work in the United States. We deliver studies and engineering ready for your engineer of record to review and stamp.
How Tiza can help
A pre-application screening of voltage, fault level and dynamic response shows what a cluster study is likely to raise before you commit deposits. Tiza provides power-system studies ready for your engineer of record to review and stamp. Contact us with your single-line diagram and connection point.
Figure: timeline of a cluster process with the application window, cluster study, restudy and facilities study, and the deposit at each step.
Related guides
- Which interconnection study each market requires
- IEEE 2800-2022 for inverter-based resources
- NERC MOD-026 and MOD-027 model verification
- Electrical codes and grid connection compared by country
References
- FERC Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements (issued 28 July 2023), and Order No. 2023-A (issued 21 March 2024).
- The pro forma Large Generator Interconnection Procedures and Agreement and each transmission provider’s compliance tariff.
Frequently asked questions
What does first-ready, first-served mean?
It means a request moves forward because the developer has proved it is ready, with a deposit, site control and complete data, not because it arrived first. Requests that cannot show readiness are removed from the cluster.
Does Order No. 2023 apply in Texas?
No. ERCOT is outside FERC's interconnection rules and follows the Public Utility Commission of Texas. Order No. 2023 applies to transmission providers under FERC jurisdiction.
Does the order set technical requirements for inverter plants?
Yes. It added requirements for non-synchronous generation, including ride-through, and for the models developers must provide. The detail of each requirement is in the pro forma procedures and agreements and in the transmission provider's tariff.