CAISO Interconnection: Cluster Studies and the RIS Tariff

How CAISO interconnection works: the GIDAP and RIS tariffs, the annual cluster study, the fast track for small projects and what the developer must supply.

By Shadai García, CEO and protection engineer at Tiza Group.

Interconnection request(Grid Resource Interconnection Portal)Which route?Cluster study:completed request,deposit, site control,technical dataFast track:up to 5 MW,energy-only,passes all screens;any time of yearAffected system:project in anotherbalancing area thatmay affect theCAISO gridReport meeting,deliverabilitystepGenerator interconnection agreement900 MW availableA 300B 250C 400D 500E 950550950depend on upgradescapacity 900 MWABC fits 350 of 4002,400 / 900 = 2.7 times the capacityA + B = 550; A + B + C = 950900 - 550 = 350 MW left: C fits 87.5%D, E and 50 MW of C need upgradesStepsRequestRouteStudyDeliverabilityAgreement© tizagrp.comInterconnection request(Grid Resource Interconnection Portal)Which route?Cluster study:completed request,deposit, site control,technical dataFast track:up to 5 MW,energy-only,passes all screens;any time of yearAffected system:project in anotherbalancing area thatmay affect theCAISO gridReport meeting,deliverabilitystepGenerator interconnection agreement900 MW availableA 300B 250C 400D 500E 950550950depend on upgradescapacity 900 MWABC fits 350 of 4002,400 / 900 = 2.7 times the capacityA + B = 550; A + B + C = 950900 - 550 = 350 MW left: C fits 87.5%D, E and 50 MW of C need upgradesStepsRequestRouteStudyDeliverabilityAgreement© tizagrp.com
CAISO interconnection: a flow chart of the three routes, cluster study, fast track for projects up to 5 MW and affected system study, that lead to the generator interconnection agreement, and a worked example of 2,400 MW of ranked requests against 900 MW of capacity where request C fits 350 of its 400 MW. Location in the system and operating principle. Illustrative: real values come from the nameplate and the manufacturer's manual.
Short answer

CAISO studies most generator interconnection requests in annual clusters. The Generator Interconnection and Deliverability Allocation Procedures (GIDAP) governed earlier clusters and the Resource Interconnection Standards (RIS) tariff governs the later ones, starting with Cluster 15. Projects of up to 5 MW seeking energy-only deliverability can use a fast track. Requests are filed through CAISO's portal with a deposit, site control and technical data.

Short answer

CAISO, the California Independent System Operator, studies most new generation and storage requests together in annual clusters. Earlier clusters followed the Generator Interconnection and Deliverability Allocation Procedures (GIDAP), which are tariff Appendix DD. The Resource Interconnection Standards (RIS), tariff Appendix KK, contain the cluster study process used from Cluster 15. A fast track exists for projects of up to 5 MW that request energy-only deliverability. The process builds on the rules of the Federal Energy Regulatory Commission (FERC), explained in FERC Order 2023 cluster studies. The wider US framework is in the US electrical codes and grid interconnection guide.

The routes into CAISO

A new resource begins by submitting an interconnection request into a tariff-defined study process. Requests are accepted only through CAISO’s Grid Resource Interconnection Portal. There are three options:

  1. Cluster study. The route for most projects. It needs a completed request, a study deposit, evidence of site control and technical data.
  2. Fast track. For projects developing or adding up to 5 MW that request energy-only deliverability. The project must pass all the screens, and it can apply at any time of the year.
  3. Affected system study. For projects in other balancing authority areas that may affect the reliability of the CAISO-controlled grid.

Energy-only deliverability means the plant can sell energy but does not receive the status that counts toward resource adequacy. Deliverability is a separate question from the connection itself, and it has its own study and allocation. For distribution-level generation in California, the route is different: see Rule 21.

How a cluster moves

CAISO validates requests before the study. A request with deficiencies after the validation date is deemed invalid and is not studied. For Cluster 15, CAISO also published intake scoring results, which ranked requests before the study. After the study, CAISO holds a cluster study report meeting with the requests in the cluster. Then come the transmission plan deliverability step, the generator interconnection agreement and the implementation phase. The timing of each step is in CAISO’s published study timeline. Cluster 16 is the next window after Cluster 15.

FERC accepted CAISO’s interconnection process enhancements, which brought in the RIS, on 30 September 2024 (docket ER24-2671). The rules keep changing, so a schedule needs the current cluster, tariff version and dates from CAISO.

What the developer must supply

  • Site control and the exact point of interconnection.
  • Technical data and a plant model that matches the equipment.
  • Deposits as the tariff sets them.
  • A deliverability choice, since it affects what is studied.
  • Commercial interest evidence where the tariff requires it.

Model requirements for inverter plants follow the standards discussed in IEEE 2800 model and simulation requirements. The stage-by-stage logic is explained in interconnection study stages. For the other regions see PJM, MISO and ERCOT.

Worked example (illustrative)

All values are assumptions that show why ranking matters.

Assumptions. An area can deliver 900 MW of new generation without major upgrades. A cluster has requests totaling 2,400 MW. Suppose the requests are ranked in this order: A 300 MW, B 250 MW, C 400 MW, D 500 MW, E 950 MW.

Step 1. Oversubscription. 2,400 ÷ 900 = 2.7 times the available capacity.

Step 2. Cumulative total. A 300; A+B 550; A+B+C 950.

Step 3. Where capacity runs out. After A and B, 900 − 550 = 350 MW remain. Request C needs 400 MW, so only 350 of its 400 MW fit, which is 87.5 percent.

Step 4. Others. D and E, or the part of C that does not fit, depend on upgrades. Their cost and time are the developer’s main risk.

Step 5. Reading the result. A request’s rank, size and the capacity of its area can matter as much as its own technical quality. This example does not describe CAISO’s actual scoring or allocation rules, which are in the tariff.

Checklist for the engineer

  • Confirm which cluster is open and which tariff section governs it.
  • Decide whether the fast track fits, and if the project passes every screen.
  • Choose the deliverability option with the commercial team.
  • Confirm site control and the deposit before the window closes.
  • Prepare the model and check it against the equipment.
  • Plan for restudies and possible withdrawal consequences.
  • Have the engineer of record review the data package.

The routes above are general orientation. CAISO’s tariff and published notices decide each case, and they change often. Tiza does not sign, seal or certify work in the United States. We deliver studies and engineering ready for your engineer of record to review and stamp.

How Tiza can help

Before you file, a screening of the connection point and the likely upgrades shows what a cluster study may find. Tiza provides power-system studies, ready for your engineer of record to review and stamp. Contact us with your single-line diagram and the point of interconnection.

Figure: diagram of the three CAISO routes, cluster, fast track and affected system, leading to the interconnection agreement.

References

  • CAISO tariff, Appendix KK (Resource Interconnection Standards) and Appendix DD (GIDAP).
  • CAISO interconnection request and study page and its Cluster 15 and Cluster 16 notices.
  • FERC order of 30 September 2024 accepting the CAISO tariff amendment on interconnection process enhancements (docket ER24-2671).

Frequently asked questions

What is the difference between GIDAP and RIS?

Both are CAISO tariff appendices. GIDAP is Appendix DD and governed earlier clusters. The Resource Interconnection Standards, Appendix KK, contain the cluster study process, the fast track and the affected system study used for Cluster 15 and later clusters.

Is there a fast way to connect a small project?

CAISO has a fast track study process for projects of up to 5 MW that request energy-only deliverability. The project must pass all the screens. Projects that fail go through customer options meetings.

What does a developer submit to CAISO?

A completed interconnection request through CAISO's portal, a study deposit, evidence of site control and technical data. CAISO validates the request, and a request with deficiencies can be deemed invalid.