The interconnection study you need depends on the market and on the size and voltage of the plant. In the US, transmission-level generators go through cluster studies under FERC Order 2023. In Great Britain, small plants use the ENA G99 application and large ones the Grid Code route through NESO. In Australia, performance standards are negotiated and agreed with AEMO under chapter 5 of the National Electricity Rules. In Canada, each utility sets its own technical requirements.
Short answer
Which interconnection study each market requires depends on three things: where the plant connects, how large it is and who operates the network. The US, the UK, Australia and Canada all study the effect of a new generator on the grid before they agree to connect it. They package the study differently. For the wider picture, see the electrical codes and grid connection comparison.
United States
For generators connecting to transmission systems under the jurisdiction of the Federal Energy Regulatory Commission (FERC), Order No. 2023 replaced the old one-request-at-a-time review with a cluster approach. Several requests received in the same window are studied together, and projects that show readiness move ahead of those that do not (a first-ready, first-served logic). The pro forma process has three study stages: a cluster study, a cluster restudy when requests change or withdraw, and a facilities study. The older feasibility study is gone from the pro forma process, although many state and utility processes still use it. Developers pay study deposits and post commercial readiness deposits that rise at each stage. The rule also sets penalties for transmission providers that deliver studies late.
Each regional operator implements the order through its own tariff filings, so the details of the process depend on the region. ERCOT, in Texas, is outside FERC’s interconnection rules and follows the Public Utility Commission of Texas. Interconnection to distribution systems, and small plants, follow state and utility rules, normally with IEEE 1547 and UL 1741 as the technical base.
Great Britain
Generators up to 16 A per phase (3.68 kW per phase at 230 V) can use EREC G98, a connect-and-notify route. Above that, EREC G99 applies, with an application to the distribution network operator (DNO) before connection. Many DNOs offer a pre-application step, followed by the full application on the standard ENA form with a single-line diagram. For the larger G99 types, the DNO issues an operational notification before the plant runs in normal operation. Larger plants connected to the transmission system work with the National Energy System Operator (NESO) under the Grid Code and a site-specific connection agreement. The Grid Code is generic and the agreement is specific to the site, so the project’s obligations combine both.
Australia
Plants connecting to the National Electricity Market work under chapter 5 of the National Electricity Rules. The developer proposes performance standards against the access standards in schedule 5.2. Under clause 5.3.4A, a proposal below the automatic access standard must be as close as practicable to it, and no less onerous than the minimum access standard. The network service provider negotiates the proposal, and the Australian Energy Market Operator (AEMO) advises on the matters reserved to it. The agreed standards then become the registered performance standards of the plant. AEMC has rule changes in progress that affect the access standards, so check the AEMC rule change page before relying on a threshold.
Canada
There is no single national process. Each province has its own system operator and utilities, and utilities such as Hydro One and Hydro-Québec publish their own technical interconnection requirements, with different documents for small and large generators. The study content is similar to the other markets, but the forms, the timelines and the cost allocation follow the utility’s rules.
Common content of the studies
Whatever the route, expect the operator to review the same technical questions:
- Thermal loading of the lines and transformers with the plant exporting.
- Voltage rise or drop at the connection point, with the plant’s reactive power control.
- Short-circuit contribution and the effect on switchgear ratings.
- Protection coordination and anti-islanding.
- For inverter-based plants, ride-through and dynamic behaviour, covered in the ride-through comparison.
A numeric example
A 5 MW plant connects at 11 kV through a feeder with R = 0.6 Ω and X = 1.2 Ω per phase. The values are illustrative. A quick screening of the voltage rise uses ΔV ≈ (P·R + Q·X) / V², with P in MW, Q in Mvar, R and X in ohms and V the line voltage in kV. The approximation holds for small voltage changes with the sending end at nominal voltage.
- At unity power factor, Q = 0: ΔV = (5 × 0.6) / 11² = 3.0 / 121 = 2.48 %.
- The plant absorbs reactive power at power factor 0.95: Q = 5 × tan(acos 0.95) = 1.64 Mvar, and the term changes sign: ΔV = (5 × 0.6 − 1.64 × 1.2) / 121 = 1.03 / 121 = 0.85 %.
- A second screening uses the short-circuit ratio (SCR). The feeder impedance is |Z| = √(0.6² + 1.2²) = 1.34 Ω. Ignoring the source behind the feeder, the fault level at the connection point is at most 11² / 1.34 = 90.2 MVA, so SCR ≤ 90.2 / 5 = 18.0. A weaker point with 25 MVA would give SCR = 25 / 5 = 5.
The lower ratio and the larger voltage rise are the cases where the operator will ask for more detailed studies. This screening does not replace the operator’s study; it tells the developer what to expect.
Checklist for the engineer
- Plant size, voltage and connection point confirmed with the operator.
- Connection route identified (simplified notification, full application, cluster or negotiated standards).
- Single-line diagram, equipment data and inverter or generator model files ready.
- Voltage rise, fault level and short-circuit ratio screened before applying.
- Deposit, fee and timeline requirements listed.
- Protection and anti-islanding requirements reviewed with the operator.
- Study results reviewed by the engineer of record before any submission.
Legal frame
This guide is general orientation. Operator processes and fees change, and the rules in force where the project is located decide. Tiza does not stamp, sign or certify; we deliver studies and engineering ready for your engineer of record to review and stamp. In the UK that is usually a chartered engineer who signs off, and in Queensland a Registered Professional Engineer of Queensland (RPEQ).
How we can help
We run load flow, short-circuit and dynamic screening studies for generation and storage projects abroad, delivered ready for your engineer of record to review and stamp. See power-system studies and contact us with your single-line diagram and the point of connection.
Related guides
- Electrical codes and grid connection compared by country
- Ride-through requirements compared: US, UK, Australia
- How to commission remote design and studies for foreign projects
- Load flow study: what it delivers and when it is needed
- Short-circuit study: sources, IEC 60909 and ANSI/IEEE
- Interconnection relays: SEL-700GT, M-3410A, InteliPro
- Power system studies with software: what to specify
References
- FERC Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements.
- ENA Engineering Recommendations G98 and G99; ENA standard G99 application form.
- Grid Code (NESO), connection conditions; NESO guidance for power park modules.
- National Electricity Rules, chapter 5, clause 5.3.4A and schedule 5.2; AEMO network connections guidance.
- Hydro One and Hydro-Québec technical interconnection requirements.
Frequently asked questions
Is an interconnection study the same in every country?
No. The name, the stages, who runs the study and who pays for it differ by market. What is common is the content: load flow, short-circuit and, for inverter-based plants, dynamic or transient checks at the point of connection.
Who performs the interconnection study?
Usually the network operator or transmission provider, using the data the developer supplies. The developer's own engineer often runs a parallel study first to know what to expect and to check the operator's results.
Can a developer run its own studies before applying?
Yes, and it is good practice. A pre-application load flow and short-circuit screening shows the likely voltage rise and fault level at the connection point, so the application can be sized and documented properly. It does not replace the operator's study.